The project to build a new Nam Dinh - Lac Quan - coastal road is a key project in Nam Dinh with a total investment of about 6,400 billion VND. The route is 24.66km long; passing through 5 districts: Nam Truc, Truc Ninh, Hai Hau, Xuan Truong and Giao Thuy.
Road size of a delta level, design speed of 100km/h, width of 39m road, 8 -lane road surface, ground clearance on the entire route with a cross -section of about 100m. The bridge, sewer on the route, synchronously designed works, ensures suitable for the road level. In particular, Xe River overpass (Giao Thuy district) is one of the large bridges under the project being built.

The bridge overpass has two units, each 17m wide, the distance between the heart of the two units is 23m, the distance between the two edges of the railing of the two units is 6m. The length of the bridge is calculated to the tail of the bridge 539.5m. The scope of the first point project at km21+931.51; The end point at Km22+493.29.
Mr. Dong Quy - Technical officer constructed Package 3 of the new road construction project Nam Dinh - Lac Quan - Coastal road, said that by this time, the bridge over the river has completed 75% of the volume. At present, construction of 16/26 beats, the upper and under the bridge is in the process of finishing. In the coming time, the unit will mobilize workers and machines to work overtime, determination to complete the project before 30.6.


According to the Nam Dinh Provincial Construction Investment Project Management Board, the So River Overpass and the new Nam Dinh - Lac Quan - coastal road, when completed, will contribute to the completion of the road traffic network, conveniently connecting with the regional and national transportation system. At the same time, shorten travel time from Nam Dinh city to communes in Giao Thuy district.