Still 8 days to hand over the entire site, the 694 billion VND project in Quang Ngai is still unfinished

VIÊN NGUYỄN |

Quang Ngai - The Thach Bich - Tinh Phong bridge connecting road project is unfinished due to site clearance issues. Provincial leaders request the handover of the entire site before September 30, 2026.

The road project connecting Thach Bich bridge to Tho Phong commune is only 6.11 km long, but in the process of implementation, many "bottlenecks" have appeared that have lasted for many years due to site clearance problems.

The project has a total investment of more than 694 billion VND, implemented from 2019 - 2025, invested by the Provincial Traffic Construction Investment Project Management Board. When completed, the project will reduce the load on National Highway 1 and National Highway 24B, especially the section through Truong Quang Trong ward and VSIP Industrial Park, and create motivation for local socio-economic development. However, to date, the project is still unfinished.

Dự án vẫn chưa thông tuyến vì vướng mặt bằng. Ảnh: Viên Nguyễn chụp sáng 22.9
The project has not yet been cleared due to site clearance issues. Photo: Vien Nguyen taken on the morning of September 22nd

According to reporters' records on September 22, at the starting point connecting National Highway 24B (Truong Quang Trong ward), the road surface has been paved with asphalt, painted, and planted with quite complete green trees, however, going about 300 m, the road suddenly "interrupted" because many houses have not been relocated, so mechanical equipment construction is slow.

According to the investor's report, to date, the project has handed over 80.5% of the site along the route length; the value of the implemented volume reached 222 billion VND, equal to 54.3% of the contract value. The 2026 capital plan alone was allocated 110 billion VND, and 103.4 billion VND has been disbursed, reaching 94% of the plan; the accumulated disbursed value from the beginning of the project to date has reached 91% of the allocated capital plan.

In the afternoon of September 19, Mr. Nguyen Cong Hoang - Vice Chairman of Quang Ngai Provincial People's Committee inspected the actual road project connecting Thach Bich bridge to Tinh Phong.

At locations still facing site clearance issues, Mr. Nguyen Cong Hoang directly inspected, grasped the situation, and requested units and localities to focus on finding solutions to remove obstacles and accelerate site clearance work.

Through inspection, Mr. Nguyen Cong Hoang requested departments, branches, localities and investors to focus, closely coordinate, and urgently remove difficulties and obstacles, especially in compensation and site clearance work, ensuring project implementation progress.

Một số hộ dân đã đồng thuận bàn giao mặt bằng. Ảnh: Viên Nguyễn chụp sáng 22.9
Some households have agreed to hand over the land. Photo: Vien Nguyen taken on the morning of September 22nd

Regarding Truong Quang Trong ward, Mr. Hoang requested the locality to urgently implement the assigned tasks, striving to hand over the entire entangled site in the ward to the investor by September 30, 2026, to serve the project construction.

Relevant localities continue to strengthen propaganda and mobilization, creating consensus among people in the process of project implementation; promptly resolve or propose to competent authorities to consider and handle arising difficulties and obstacles, contributing to accelerating the progress of key projects of the province.

VIÊN NGUYỄN
RELATED NEWS

Quang Ngai people agree to dismantle houses to expand National Highway 24B

|

Quang Ngai is accelerating site clearance for the National Highway 24B upgrade project, striving to hand over 70% of the site by the end of September to accelerate construction.

Quang Ngai promotes the progress of handling redundant housing and land after arranging administrative units

|

Quang Ngai - Chairman of the Provincial People's Committee requests 100% completion of the plan to handle and exploit redundant houses and land in October 2026.

Quang Ngai removes obstacles, accelerates social housing for Trade Unions

|

On September 8, the working delegation of the Vietnam General Confederation of Labour had a working session with the People's Committee of Quang Ngai province on the implementation of the Trade Union Social Housing project in Quang Ngai province.

Proposal to abolish tax on encroached land

|

Regarding non-agricultural land use tax, the Government proposes to remove the 0.2% tax rate for encroached and occupied land and not apply a limit.

Large warehouse fire near Vinh Tuy bridge foot, Hanoi

|

Hanoi - A large fire broke out at a warehouse on Bach Dang street.

Tay Tuu flower growers lose hundreds of millions of VND after floods

|

After the recent rain and flood, many flower and vegetable growing households in Tay Tuu flower village, Hanoi suffered heavy losses. Some families estimate losses of 300 - 400 million VND.

Tighten admission methods, abolish IELTS bonus points to end inflation of university benchmark scores

|

According to experts, removing bonus points and tightening admission methods will help reduce score inflation, returning certificates like IELTS to their correct function of measuring language proficiency.

Quang Ngai people agree to dismantle houses to expand National Highway 24B

VIÊN NGUYỄN |

Quang Ngai is accelerating site clearance for the National Highway 24B upgrade project, striving to hand over 70% of the site by the end of September to accelerate construction.

Quang Ngai promotes the progress of handling redundant housing and land after arranging administrative units

VIÊN NGUYỄN |

Quang Ngai - Chairman of the Provincial People's Committee requests 100% completion of the plan to handle and exploit redundant houses and land in October 2026.

Quang Ngai removes obstacles, accelerates social housing for Trade Unions

Viên Nguyễn |

On September 8, the working delegation of the Vietnam General Confederation of Labour had a working session with the People's Committee of Quang Ngai province on the implementation of the Trade Union Social Housing project in Quang Ngai province.