Belt 4
Do not allow households to share houses when giving up land to build Ring Road 4
|
In places where the Ring Road 4 project passes through, people all agree with the policy of implementing the project. Currently, life in the temporary residential area has also gradually stabilized.
Progress of Ring Road 4 parallel road through Hanoi, Hung Yen and Bac Ninh
|
Localities have completed site clearance for the Ring Road 4 project and are focusing on construction, ensuring the set schedule.
Ring Road 4 project receives 100% clean ground, contractor constructs during New Year's Day
|
Hanoi - Many engineers and workers postpone New Year holidays to stick to the construction site, accelerating the progress of the Ring Road 4 parallel road project in the Capital region.
Completing site clearance for Ring Road 4 project in the Capital region
|
Hanoi - Communes and wards have completed site clearance and handed over to investors to construct Ring Road 4 project in the Capital region.
After site clearance for Ring Road 4, people have stabilized in the temporary residential area
|
In places where the Ring Road 4 project passes through, people all agree with the policy of implementing the project. Currently, life in the temporary residential area has also gradually stabilized.
Hanoi still has nearly 6,000ha of land that has not been completed for site clearance
|
Hanoi - Director of the Department of Agriculture and Rural Development said that site clearance work is always a difficult stage, in which the Capital still has about 5,895.5ha unfinished.
Enforced land recovery for cases of not allocating land for Ring Road 4 construction
|
Hanoi - For cases of delay and non-compliance with site allocation for Ring Road 4 project, the government has issued a decision to enforce land recovery.
The largest road in the Southeast will start construction in 2026 and be completed in 2028
|
HCMC - The Ring Road 4 project, the largest route in the Southeast region passing through HCMC, Dong Nai and Tay Ninh, will start construction in September 2026 and be completed in 2028.
First image of the Red River overpass on Ring Road 4
|
Hanoi - At the Hong Ha bridge construction site of the Ring Road 4 project, machinery, barges, ships, construction materials... are gathered to serve the construction work.
Dust from Ring Road 4 construction site attacks houses, business stagnates
|
Hanoi - People and businesses along National Highway 6 are miserable because of the dust from the Ring Road 4 project, dusty houses, stagnant business, and health is threatened every day.
HCMC promotes investment in the largest road in the Southeast, to be completed in 2028
|
HCMC - The 207 km long Ring Road 4 project, with a total capital of more than VND 120,000 billion, passing through HCMC, Dong Nai and Tay Ninh, is being accelerated to start construction in 2026.
The Ministry of Construction responds to the Hanoi People's Committee on the content related to the Ring Road 4 project
|
The Ministry of Construction has just issued an official dispatch responding to Hanoi on the content related to the Ring Road 4 project in the Hanoi Capital Region.
HCMC speeds up the progress of land acquisition of 1,553 households to build a belt road
|
HCMC - The competent authorities of the HCMC People's Committee are speeding up the progress of land acquisition for 1,553 households to build the HCMC Ring Road 4.
Hanoi's Ring Road 4 parallel road lacks completion plan in 2025
|
The slow handover of the site makes it impossible for the Ring Road 4 parallel road project to be completed in 2025 as targeted by Hanoi.
Information on the progress and completion time of the Hanoi Ring Road 4 parallel road
|
According to the set target, the Ring Road 4 parallel road section through Hanoi will be basically completed by the end of 2025, after about 2.5 years of construction.