27-span flyover on Hanoi's Ring Road 4 to be completed in 2025

NHÓM PV |

Hanoi - It is expected that by the second quarter of 2025, the North-South railway overpass, nearly 590m long, with 27 spans (part of the Ring Road 4 parallel road project through Me Linh) will be completed.

Component project 2.1 invests in the construction of a parallel road system (urban road) of Ring Road 4 through Hanoi with a total route length of about 58.2km.

The route passes through 7 districts including Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

According to Lao Dong, the 23km long package No. 8, the construction of a parallel road through Soc Son and Me Linh districts, has taken shape after about 17 months of construction.

Mr. Nguyen Hoai Nam - Head of Technical Department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - said that package No. 8 has about 15km of parallel roads that have been paved with asphalt.

Currently, about 7km of the route is being constructed by the contractor with crushed stone.

Package No. 8 also undertakes the construction of 3 overpasses on the route, including the Ca Lo River overpass connecting Soc Son with Me Linh, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

Among these, the railway overpass is the largest bridge built under package number 8. The project is nearly 590m long with 27 spans on both sides, the width of the bridge deck is 15m on each side.

Mr. Nguyen Hoai Nam said that for the area that is not affected by the site, the contractor has installed all the beams, poured the bridge deck and is constructing the railing item.

Currently, there are 4 remaining bridge piers and 8 remaining spans that cannot be constructed due to the obstruction of 220kV and 50kV power lines.

"According to the plan, the power lines will be relocated by the end of December. After the site is cleared, the contractor will construct the remaining 4 bridge piers and 8 spans. It is expected that the bridge will be closed by April. After that, the contractor will complete the remaining items within 2 months," said Mr. Nam.

The remaining two bridges in package 8, including Ca Lo bridge and Hau village bridge, are also being ensured by the contractor to ensure construction progress.

Regarding the progress of the entire package No. 8, Mr. Nam said that up to this point, the joint venture contractor has completed about 64% of the construction volume, ensuring progress compared to the plan.

In addition to the land being stuck at the construction site of the railway overpass, two residential areas in Dai Thinh and Chu Phan communes (Me Linh) have not yet had their land handed over to the project.

"With the sections that have cleared land, the joint venture contractor is committed to completing the construction of the Ring Road 4 parallel road project through Me Linh and Soc Son in June 2025," Mr. Nam affirmed.

Trong anh la cau vuot duong sat Bac - Nam tuyen Ha Noi - Lao Cai dang duoc xay dung tren tuyen. Anh: Nhom PV
In the photo is the North-South railway overpass on the Hanoi-Lao Cai route under construction on the parallel route of Ring Road 4 through Me Linh (Hanoi). Photo: PV Group
Nha thau da hoan thanh xay lap nhieu tru cau. Anh: Nhom PV
The contractor has completed the construction of many bridge piers. Photo: PV Group
Cau co 27 nhip voi chieu dai gan 590m, mat cat ngang moi ben 15m. Anh: Nhom PV
The bridge has 27 spans with a length of nearly 590m, with a cross-section of 15m on each side. Photo: PV Group
Hien co 4 tru cau va 8 nhip dam chua duoc thi cong, lao lap vi vuong 2 duong day dien 220kV va 50kV. Anh: Nhom PV
Currently, there are 4 bridge piers and 8 girder spans that have not been constructed or installed because of the obstruction of 220kV and 50kV power lines. Photo: PV Group
Du kien cau vuot duong sat se duoc hop long vao thang 4.2025, hoan thanh toan bo cac hang muc vao thang 6.2025. Anh: Nhom PV
The railway overpass is expected to be closed in April 2025, with all items completed in June 2025. Photo: PV Group
Trong anh la khu vuc duc dam cau. Anh: Nhom PV
In the photo is the bridge girder casting area. Photo: PV Group
Trong anh la cau vuot song Ca Lo cung dang duoc xay dung.
The Ca Lo River overpass (the border between Me Linh and Soc Son) is also under construction. Photo: PV Group
Nhieu hang muc chinh cua cau da co ban hoan thanh.
Many main items of the bridge have been basically completed. Photo: PV Group
Trong anh la cau thon Hau cung thuoc goi thau so 8 xay dung duong song hanh Vanh dai 4. Anh:
In the photo is Hau village bridge, also part of package 8 of the construction of the parallel road of Ring Road 4. Photo: PV Group
Cac hang muc cau cung dang trong qua trinh thi cong. Anh: Huu Chanh
Bridge items under construction. Photo: PV Group
Duong song hanh Vanh dai 4 qua Soc Son, Me Linh (Ha Noi) du kien hoan thanh vao thang 6.2025.
The parallel road of Ring Road 4 through Soc Son and Me Linh (Hanoi) is expected to be completed in June 2025. Photo: PV Group
NHÓM PV
TIN LIÊN QUAN

Total construction force, completion of parallel road of Ring Road 4 by 2025

|

According to plan, the parallel road of Ring Road 4 through Hanoi, Hung Yen and Bac Ninh will be completed in 2025. Contractors are focusing on construction, closely following the schedule.

Spacious resettlement area formed next to Ring Road 4

|

Hanoi - Some houses in the Ring Road 4 resettlement area in Me Linh district have been completed, and people have begun moving into their new homes.

Small traders cling to old, dilapidated markets despite new, spacious markets

|

Can Tho - About 5 years since it was put into use, traders still refuse to move to Truong Xuan market (new market), determined to stick with Ba Dam market (old market).

Flight tickets for Lunar New Year 2025 are getting "hotter"

|

One month before the 2025 Lunar New Year holiday, domestic airfares, especially from the South to the North, are still high, with many routes sold out.

Hanoi bus station expects 300% increase in passengers during Lunar New Year

|

Hanoi bus stations plan to increase passenger vehicles to meet the increasing travel demand of people during the peak period of the Lunar New Year 2025.

Why are people in Ninh Binh rushing to change their driving licenses?

|

Ninh Binh - The situation of people rushing to do procedures to change and reissue driving licenses is due to psychology and lack of information.

Nearly completed multi-agency headquarters worth hundreds of billions in Thai Nguyen

|

Thai Nguyen - After more than 1 year of construction, the Office Building project of the agencies (Pho Yen City) with a total cost of 400 billion VND has been basically completed.

Ministry of Public Security prioritizes investment in 6 forces to modernize

|

The 80th National Public Security Conference solemnly opened this morning (December 26) in Hanoi.

Hiện trạng nơi xây cầu vượt sông Hồng, sông Đuống trên Vành đai 4

NHÓM PV |

Có 3 cây cầu lớn trên Vành đai 4 sẽ được đầu tư xây dựng gồm Hồng Hà và Mễ Sở qua sông Hồng, cầu Hoài Thượng qua sông Đuống.

Total construction force, completion of parallel road of Ring Road 4 by 2025

NHÓM PV |

According to plan, the parallel road of Ring Road 4 through Hanoi, Hung Yen and Bac Ninh will be completed in 2025. Contractors are focusing on construction, closely following the schedule.

Spacious resettlement area formed next to Ring Road 4

HỮU CHÁNH - KHÁNH AN |

Hanoi - Some houses in the Ring Road 4 resettlement area in Me Linh district have been completed, and people have begun moving into their new homes.