The Cun slope renovation project on Highway 6 is behind schedule again

Minh Chuyên |

Hoa Binh - The project to handle traffic safety risks at Cun slope on National Highway 6 did not finish on time, the investor continued to request a second extension.

The project to handle traffic safety risks at Cun slope (Km78+500 - Km85+100) on National Highway 6 was approved by the Directorate of Vietnam Roads (now the Vietnam Road Administration) with a total investment of 130 billion VND, with the Hoa Binh Department of Transport as the investor.

The project started in August 2023 and is expected to be completed in the first quarter of 2024. By the beginning of the second quarter of 2024, the progress was not as planned, so the investor had to request an extension until September 30, 2024.

However, the project continued to encounter many difficulties. At the end of September 2024, the Department of Transport of Hoa Binh once again had to ask the Vietnam Road Administration to extend the implementation period of the construction contract, the construction supervision consultancy contract and the insurance contract, belonging to the project of Handling traffic safety risks on the Cun slope.

Nguoi dan, lai xe mong moi du an xu ly diem den tai doc Cun som hoan thanh. Anh: Minh Chuyen
Drivers hope the project to deal with black spots at Cun slope will be completed soon. Photo: Minh Chuyen

Document No. 3056 of the Department of Transport of Hoa Binh province stated that during the project implementation, many force majeure events were encountered, along with difficulties and obstacles in compensation and site clearance (GPMB).

From Km78+721 - Km78+760 (Hoa Binh city), there are currently 2 households with assets (houses) on land within the scope of demolition and relocation, but up to now, the People's Committee of Hoa Binh city has just approved the compensation plan and the Provincial People's Council has also rearranged the capital source for compensation and site clearance work. It is expected that the households will be paid in September 2024.

As for the section from Km82+290 - Km83+710 (in Dinh Cun hamlet, Thu Phong commune, Cao Phong district), currently 60/136 households do not agree to hand over the construction site to the investor.

For this section, the review shows that the construction site is basically within the scope of land acquisition and clearance of the project to upgrade and renovate National Highway 6, Hoa Binh - Son La section (2002 - 2005). The People's Committee of Cao Phong district said that it will develop a construction protection plan for the contractor from the end of September 2024 and has committed to land acquisition and clearance for the entire route in the district before November 15, 2024.

In addition, during the implementation process, the Hoa Binh Department of Transport had to direct the contractor to temporarily stop construction to ensure traffic during the holidays of the year.

Also according to the Department of Transport of Hoa Binh, the remaining work mainly focuses on blasting rocks at the section Km79+243 - Km79+517 with a rock blasting volume of over 100,000m3. Because above and near the construction area are 35KV and 110KV power lines, the blasting plan was approved with a small amount of explosives for each explosion, the construction area is narrow, so on average only about 700m3 of raw rock can be blasted and transported per day.

"Based on the regulations on contract adjustment and objective reasons due to natural disasters, difficulties, along with the progress of commitment to complete site clearance work, as well as the plan to organize rock breaking by blasting analyzed above, the unit has reported and submitted to the Vietnam Road Administration for approval to extend the implementation period to March 31, 2025" - Hoa Binh Department of Transport said.

Nhieu vi tri dang trong qua trinh thi cong. Anh: Minh Chuyen
Many locations are under construction. Photo: Minh Chuyen

On the morning of September 30, Lao Dong Newspaper reporters observed that at the project site under construction, convoys of vehicles were moving busily on the road. Many locations in the project have been basically completed, and the Cun slope has been widened much more than before and has become more open, ensuring traffic participation.

Ms. Bui Thi Linh (residing in Kim Boi district) said that the Cun slope area has a large volume of traffic, many blind spots, and limited visibility, and was once known as the slope of death. Hopefully, the project will be completed soon to reduce traffic accidents and ensure the safety of people and vehicles when passing through here.

Minh Chuyên
RELATED NEWS

Parents' representative board pays support money to a class after being accused of overcharging

|

Gia Lai - Being reflected by parents about mobilizing donations, the Parents' Representative Board agreed to refund money to a class because the donation was not in accordance with the spirit of voluntariness.

Ministry of Industry and Trade introduces Acting Minister Le Manh Hung to run for National Assembly Deputy of the XVI term

|

100% of delegates from the Ministry of Industry and Trade unanimously introduced Acting Minister Le Manh Hung to run for National Assembly deputy of the XVI term.

Prolonged congestion in Thu Thiem tunnel

|

Ho Chi Minh City - Long lines of vehicles including cars, motorbikes... lined up, moving little by little in Thu Thiem tunnel. The traffic jam lasted for about 1 km.

Minister Nguyen Kim Son introduced to run for National Assembly Deputy of the XVI term

|

100% of voters in the workplace voted for Minister Nguyen Kim Son to run for National Assembly Deputy of the XVI term, term 2026-2031.

Dengue fever decreases in Hanoi, Ho Chi Minh City still has many severe cases

|

The number of dengue fever cases has decreased in Hanoi, but in Ho Chi Minh City, many severe cases are still recorded, posing a risk of complications and death.

Building a bridge worth over 20,000 billion VND connecting Ho Chi Minh City and Dong Nai

|

Dong Nai - After more than 30 years of waiting, the Cat Lai bridge project worth more than 20,000 billion VND officially grounded, increasing the connection between Ho Chi Minh City - Dong Nai, escaping the scene of crossing rivers and ferries.

Sa Dec flowers in the Tet season, gardeners consider reasonable selling prices to retain customers

|

Dong Thap - the flower capital of Sa Dec is entering the Tet season, however, the concern of gardeners is that production costs have skyrocketed, and there is a possibility of having to increase selling prices by 5-10%.

Drunk driver, driving 130km/h to escape traffic police on Highway 6

Minh Nguyễn - Cao Thiên |

Son La - After more than 1 hour of chasing, the traffic police force was able to stop a truck driver with an alcohol concentration exceeding the limit on National Highway 6.

Scene of landslide that crushed 2 cars on Highway 6

Minh Nguyễn |

Son La - A large amount of rock and soil collapsed on National Highway 6 through Moc Chau district, crushing 2 cars and injuring 8 people.

Landslide crushed 2 cars on Highway 6

Minh Chuyên |

Son La - Prolonged rain caused a large landslide that crushed two cars traveling on National Highway 6.