Hanoi gateway road to be expanded 6 times, capital of nearly 1,500 billion VND

HỮU CHÁNH |

The main gateway road to Hanoi is about to be widened from 7-8m to 52m to help reduce traffic congestion and contribute to the socio-economic development of the capital.

The Hanoi People's Committee recently approved the project to expand National Highway 3 according to the plan (from the intersection of National Highway 18 to the intersection of the road to Soc Temple) in Soc Son district.

The project is about 6.7km long, with a land use scale of about 35.7 hectares, belonging to group B project.

The total investment for the road expansion is about 1,482 billion VND, from the Hanoi City budget. The project implementation progress is from 2024-2027.

The expanded route has a normal roadbed cross-section of 52m. National Highway 3 will become an urban road with a design speed of 80km/h.

Quoc lo 21B doan qua huyen Soc Son, Ha Noi. Anh: Huu Chanh
National Highway 3 through Soc Son district, Hanoi. Photo: Huu Chanh

Living for decades next to National Highway 3, Ms. Nguyen Thi Diem (Phu Linh commune, Soc Son district) said that the stream of cars running noisily, honking their horns... is a common sight here.

"The road is narrow, there are many vehicles, especially large cars, so just a little carelessness can easily cause an accident," said Ms. Diem.

Therefore, when hearing the news that National Highway 3 (the section from the intersection of National Highway 18 to the intersection of the road to Soc Temple) was about to be expanded, Ms. Diem was very excited, hoping that the project would soon be completed to clear the congestion and accidents in the area.

"The locality has organized meetings for people to grasp information about the project. We all support the policy of opening the road, but the compensation and site clearance policy must be reasonable so that people are not disadvantaged when giving up land for the project," said Ms. Diem.

Xe tai, container chay nuom nuop moi ngay tren tuyen Quoc lo 3 Soc Son. Anh: Huu Chanh
Trucks and containers run continuously every day on National Highway 3 through Soc Son. Photo: Huu Chanh

Mr. Le Xuan Sang (34 years old, Tien Duoc commune, Soc Son) said that in addition to serious accidents, minor collisions between vehicles happen "like daily meals" on National Highway 3.

"There are also many people who drive motorbikes recklessly or drive in the wrong direction, crossing the road without looking, so accidents are more likely to happen," said Mr. Sang.

Therefore, Mr. Sang also hopes that the project will be implemented on schedule so that people's travel will be convenient and the lives of households along the route will also have many changes.

Quoc lo 3 thuong xuyen xay ra tai nan. Anh: Huu Chanh
Highway 3 is a frequent site of accidents. Photo: Huu Chanh

According to Lao Dong, the current status of National Highway 3 through Soc Son district for many years has only been a grade 3 road.

The road cross-section is only 7-8m wide, there are no sidewalks, no trees, the lighting is not uniform, it is relatively narrow, and traffic jams are frequent during rush hour.

As the main traffic axis in the North of Hanoi, National Highway 3 always receives many trucks and containers passing through every day. Just two large trucks going in opposite directions can almost completely occupy the road surface, forcing motorbikes to weave through the gaps.

Mat cat ngang tuyen duong hien chi rong 7-8m. Anh: Huu Chanh
The current cross-section of the road is only 7-8m wide. Photo: Huu Chanh

According to the assessment of the People's Committee of Soc Son district, investment in expanding the route is necessary and urgent, contributing to completing the planned traffic network, helping to conveniently connect the central area of ​​the capital to the northern provinces.

At the same time, create space for development of the central area of ​​Soc Son district, gradually complete infrastructure, develop socio-economy, ensure national defense and security of Soc Son district in particular and Hanoi city in general.

HỮU CHÁNH
RELATED NEWS

After the reflection of Lao Dong Newspaper, people have gone to the commune to work on the issuance of red books

|

Hanoi - People in Thanh Oai commune said that the family representative had gone to the commune People's Committee to work on the issue of granting red books after the reflection of Lao Dong Newspaper.

Order to open the bottom spillway of Tuyen Quang hydroelectric reservoir early this afternoon

|

1 bottom spillway of Tuyen Quang hydroelectric reservoir was opened at 1:00 p.m. on October 9.

Da Nang coast is seriously eroded, sandbags of tens of tons are helpless in the face of strong waves

|

serious landslides are occurring in Tan Thanh coastal area (Hoi An Tay ward, Da Nang city), many shops have to use sandbags of tens of tons to block the shore.

Latest update on flooded areas in Hanoi, some flooded areas up to 1m

|

As of 8:00 a.m. on October 9, Hanoi still had many flooded areas due to heavy rain after storm No. 11 (storm Matmo), including 9 deeply flooded areas that prevented vehicles from moving.

The Government Party Congress implements two important contents

|

The 1st Government Party Congress, term 2025-2030, took place over 2 days, from October 12-13, implementing 2 important contents.

Employment situation at Tan Thuan Phong Hai Phong Company after a series of leaders were arrested

|

Hai Phong - About 200 workers of Tan Thuan Phong Company Limited are still maintained their jobs after a series of key leaders of this company were arrested for investigation.

Hamas signs peace agreement with Israel

|

Hamas has approved a peace plan initiated by President Donald Trump, paving the way for an end to the war with Israel in Gaza.

More than 1,800 households in Bac Ninh are isolated due to floods

|

Bac Ninh - More than 10,000 households had to move their homes to safe places, more than 1,800 households were isolated due to floods.

Road expansion project in Ho Chi Minh City is 81% complete and then shelved

NHƯ QUỲNH |

Ho Chi Minh City - The Lien Phuong road expansion project, with an investment capital of more than 300 billion VND, was 81% completed and then "shelved" for nearly 3 years.

Hà Nội còn 1 tháng giải phóng mặt bằng mở rộng đường lên 40m

HỮU CHÁNH |

Hà Nội - So với mốc 1.10 do quận Hoàng Mai ấn định, các đơn vị liên quan chỉ còn 30 ngày để hoàn thành giải phóng mặt bằng dự án mở rộng đường Tam Trinh.

Hiện trạng giải phóng mặt bằng mở rộng đường Tam Trinh

NGỌC THÙY |

UBND quận Hoàng Mai (Hà Nội) đang nỗ lực đẩy nhanh tiến độ giải phóng mặt bằng phục vụ dự án mở rộng đường Tam Trinh.