The billion-dollar road in Ho Chi Minh City is expanding but the electric pole is still in the middle of the road

MINH QUÂN - ANH TÚ |

HCMC - The project to expand Duong Quang Ham Street (Go Vap) with a length of nearly 2.5 km has been paved with many sections, but hundreds of electricity poles have not been relocated.

The project to expand Duong Quang Ham Street extends from Go Vap Cultural Park to the railway line bordering Binh Thanh District.

The road has been upgraded from 6 m to 32 m with 6 lanes, with a total investment of more than VND 2,300 billion, of which the cost of site clearance accounts for more than VND 1,926 billion.

The project started in April 2020 but after only 4 months it had to be temporarily suspended due to problems in site clearance. In September 2023, the project was restarted when Go Vap District handed over part of the site.

According to records, many sections have been paved with asphalt to help reduce dust and improve travel conditions for people.

Doan duong Duong Quang Ham giap duong ray xe lua da trai nhua va thong thoang.  Anh: Anh Tu
The section of Duong Quang Ham Street adjacent to the railway line has been paved and cleared. Photo: Anh Tu

However, many sections of the road still have hundreds of electric poles that have not been relocated, causing congestion and posing a potential risk to traffic safety.

"A vehicle often drives fast on a newly paved road, if not familiar with the road, it is easy to be dangerous, especially at night" - Mr. Mai Van Thanh, a resident of Go Vap district shared.

Cot dien o duong Duong Quang Ham dang duoc rao chan ton xung quanh, son phan quang trang do.  Anh: Anh Tu
The electric pole on Duong Quang Ham Street is being fenced with corrugated iron and painted with red white reflection. Photo: Anh Tu

According to the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board - investor), before the Lunar New Year, Duong Quang Ham Street was temporarily opened to traffic to reduce traffic pressure on neighboring routes such as Phan Van Tri, Nguyen Thai Son, Le Duc Tho.

However, because many electric poles have not been relocated, the contractor has temporarily installed surrounding corrugated iron barriers, painted white - red reflectors and installed warning lights at night to ensure safety for road users.

According to the original plan, the project to upgrade and expand Duong Quang Ham Street will be completely completed by the end of 2024.

However, according to the Traffic Department, the construction process encountered many difficulties due to a series of electric poles that had not been relocated.

To speed up the progress, the Traffic Department has recommended that the electricity industry urgently construct the undergrounding of the power grid and reclaim all power poles before March 30, 2025. If this is completed on schedule, the project can open to traffic on April 30, 2025.

Nganh dien can di doi tru dien
Workers collect electric wires. Photo: Anh Tu

In addition to the problem with electric poles, the site clearance work has not been completed. Currently, Go Vap District People's Committee has handed over 421/427 cases, 6 cases have not been resolved.

Of which, one household (the gas station on the right side of the route) has not yet handed over the land, 3 lots located on the road have not been dismantled and 2 land areas under the management of the Ministry of National Defense have not yet had a decision to transfer.

Mot cay xang chua ban giao mat bang.  Anh: Anh Tu
The gas station has not yet handed over the site. Photo: Anh Tu
Cac lo cot tren duong Duong Quang Ham chua di doi.  Anh: Anh Tu
The lots on Duong Quang Ham Street have not been relocated. Photo: Anh Tu

The Ho Chi Minh City People's Committee has issued a document requesting the Ministry of National Defense to agree to hand over the national defense land to implement the project.

To ensure progress, the Traffic Committee recommends that the Go Vap District People's Committee soon complete the enforcement of the gas station on the right side of the route in February 2025.

At the same time, it is recommended that the Ministry of National Defense quickly issue a document approving the removal from the payroll, relocation and dismantling of 3 lots, as well as agreeing to transfer the national defense land area to the two units for management, creating conditions for the project to be implemented according to plan.

MINH QUÂN - ANH TÚ
TIN LIÊN QUAN

HCMC proposes to establish a Department of Transport

|

HCMC - The Department of Transport was established from the Department of Transport, receiving the Traffic Safety Committee and infrastructure management tasks from the Department of Construction.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

|

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

1,500 billion VND project to expand gateway to Ho Chi Minh City is stuck with 5 land plots

|

HCMC - The project to expand National Highway 50, the southern gateway of HCMC, with a total capital of VND1,500 billion, is still stuck with 5 sites, affecting the construction progress.

10 police officers in Hanoi ask to hold lower positions

|

Hanoi - 10 Department Heads and District Police Heads voluntarily applied to hold positions lower than the positions they are holding after streamlining the apparatus.

Where each household has a railway crossing in Hanoi

|

Hanoi - On Ngoc Hoi Street (Thanh Tri District), there is a residential area where each household has its own access to the railway.

Pi digital money is priced, Pi players still find it difficult to sell

|

Pi Digital currency has been officially listed, however, many "Pi players" despite owning thousands of Pi digital currency have not been able to participate in buying and selling.

Investigation of signs of violations of a residential area project in Thanh Hoa

|

Thanh Hoa province has just directed the relevant authorities to urgently provide full documents related to the Dong Tho residential area project, Thanh Hoa city.

Mr. Nguyen Van Duoc becomes Chairman of the Ho Chi Minh City People's Committee

|

HCMC - With the majority of votes, Mr. Nguyen Van Duoc - Deputy Secretary of the HCMC Party Committee was elected to hold the position of Chairman of the HCMC People's Committee for the 2021 - 2026 term.

HCMC proposes to establish a Department of Transport

MINH QUÂN |

HCMC - The Department of Transport was established from the Department of Transport, receiving the Traffic Safety Committee and infrastructure management tasks from the Department of Construction.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

MINH QUÂN |

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

1,500 billion VND project to expand gateway to Ho Chi Minh City is stuck with 5 land plots

MINH QUÂN |

HCMC - The project to expand National Highway 50, the southern gateway of HCMC, with a total capital of VND1,500 billion, is still stuck with 5 sites, affecting the construction progress.