The 2,300 billion VND project to relieve traffic jams in Go Vap is still in disarray

TÚ QUÂN |

HCMC - The project to expand Duong Quang Ham Street (Go Vap) with a total capital of 2,300 billion VND is still in disarray and unfinished despite the goal of opening to traffic by the end of 2024.

On November 22, at the Duong Quang Ham Street expansion site, many items such as drainage system, road and sidewalk expansion, and underground power grid are still being implemented. Some households are dismantling their houses to hand over the site.

Duong Duong Quang Ham ngon ngang, bui mu mit.  Anh: Anh Tu
Duong Quang Ham Street is messy and dusty. Photo: Anh Tu

However, the existing electric poles in the middle of the road have not been recovered, hindering construction and posing a potential risk of accidents.

Ms. Mai Thi Oanh (45 years old) - a household that has handed over the land for a long time, was upset: "Currently, the project is very messy and dusty, greatly affecting business. I just hope this road will be completed soon so that people will suffer less."

Nhieu tru dien van an ngu giua duong.  Anh: Anh Tu
Many electric poles still block the road. Photo: Anh Tu

The project to expand Duong Quang Ham Street, nearly 2.5 km long, connecting Go Vap Cultural Park to the railway bordering Binh Thanh District, has been expanded from 6 m to 32 m, with 6 traffic lanes.

Of the total investment of more than 2,300 billion VND, site clearance costs account for the majority, at about 1,750 billion VND.

The project started in April 2020, but after only 4 months it had to be temporarily suspended due to land issues. It was not until September 2023 that the project was restarted after Go Vap district handed over part of the land.

Nhung can nha chua thao do de ban giao mo rong duong.  Anh: Anh Tu
Houses that have not been demolished to hand over for road expansion. Photo: Anh Tu
Nguoi dan thao do nha ban giao mat bang.  Anh: Anh Tu
People dismantled their houses and handed over the land. Photo: Anh Tu

According to the Management Board of Traffic Construction Investment Projects of Ho Chi Minh City (Traffic Board - investor), up to now, the locality has only handed over the site for 415/425 cases. The remaining 10 cases have not been resolved, causing difficulties for synchronous construction.

Sections such as from Nguyen Thai Son Street to Road No. 2 are still stuck with 5 households, 3 bunkers and 2 defense land plots. Sections from Road No. 2 to Nguyen Van Luong are also facing obstacles because of 1 defense land plot and 1 bunker that has not been relocated.

Mot lo cot nam giua duong chua duoc thao do.  Anh: Anh Tu
A bunker in the middle of the road has not been dismantled. Photo: Anh Tu

The project was previously targeted to open to traffic by December 31, 2024. But with the current sluggish progress, the target of opening to traffic by the end of 2024 is unlikely to be achieved.

The Traffic Committee recommends that the Ho Chi Minh City People's Committee soon issue a document reporting to the Ministry of National Defense on the relocation and dismantling of the bunkers.

Go Vap District needs to hand over the remaining land soon and the electricity industry needs to speed up the progress of undergrounding the power grid and reclaiming existing power poles to ensure the project can be constructed synchronously.

Du an mo rong duong Duong Quang Ham cham tien do.  Anh: Anh Tu
The Duong Quang Ham Street expansion project is behind schedule. Photo: Anh Tu

Mr. Nguyen Van Hung - Head of the Compensation and Site Clearance Board of Go Vap District, said: "We are actively campaigning and propagating so that households understand the significance of the project. For cases of disagreement, the district will apply administrative measures to reclaim the site."

Ngam hoa luoi dien duong Duong Quang Ham.  Anh: Anh Tu
Underground power grid on Duong Quang Ham street. Photo: Anh Tu

According to Mr. Bui Trung Kien - Deputy General Director of Ho Chi Minh City Electricity Corporation, the Traffic Department has handed over more than 60% of the land to the electricity industry, but not continuously but in sections, so the existing power grid cannot be moved. Moreover, the materials and installation equipment must be imported, taking more time to transport and accept.

"It is expected that the undergrounding of the power grid and the recovery of the power poles will be completed by April 2025," said Mr. Kien.

TÚ QUÂN
RELATED NEWS

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

|

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.

6-lane road to reduce traffic congestion Tan Son Nhat delayed to open to traffic until 2.2025

|

HCMC - The 6-lane Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, at the gateway to Tan Son Nhat airport, has been postponed to February 2025, instead of the end of this year.

Ho Chi Minh City clears 1,270 households in Binh Thanh and Go Vap districts

|

HCMC - The Xuyen Tam Canal renovation project will affect 2,215 households and organizations in Binh Thanh and Go Vap districts, of which 1,270 households will be completely cleared.

Hanoi pilots Kham Thien street traffic organization for 3 months

|

Hanoi will pilot traffic organization adjustments on Kham Thien street for 3 months, including banning taxis and contract cars under 8 seats during peak hours to reduce congestion.

Russia ignores US tariffs, declares it still sends oil to save Cuba

|

Russia is actively discussing measures to help Cuba overcome the fuel crisis, while underestimating US tax threats.

Instructions for traveling at traffic hotspots in Ho Chi Minh City during the Lunar New Year

|

The Traffic Police Department of Ho Chi Minh City Police guides alternative routes in many areas that are frequently congested, helping people move conveniently and safely.

Ministry of Industry and Trade postpones gasoline and oil price management to the 4th day of Tet 2026

|

The gasoline and oil price adjustment period on February 19, 2026 will be moved by the Ministry of Industry and Trade to February 20, 2026 (4th day of Tet).

Northern peach blossoms enter Ho Chi Minh City, garden owners are excited because of fast consumption

|

Peach blossoms from northern garden villages have just entered Ho Chi Minh City and have attracted buyers. Many garden owners said that more than half of the goods have been sold in just a few days.

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

MINH QUÂN |

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.

6-lane road to reduce traffic congestion Tan Son Nhat delayed to open to traffic until 2.2025

MINH QUÂN |

HCMC - The 6-lane Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, at the gateway to Tan Son Nhat airport, has been postponed to February 2025, instead of the end of this year.

Ho Chi Minh City clears 1,270 households in Binh Thanh and Go Vap districts

MINH QUÂN |

HCMC - The Xuyen Tam Canal renovation project will affect 2,215 households and organizations in Binh Thanh and Go Vap districts, of which 1,270 households will be completely cleared.