Hanoi begins to expand main road to 40m, capital of 3,300 billion

HỮU CHÁNH |

Hanoi - Contractors have begun construction to expand Tam Trinh Street in locations where the ground is cleared.

The Tam Trinh road construction investment project was approved by the Hanoi People's Committee in 2012, with a total investment of VND 2,066 billion.

The invested construction route is about 3.5km long, starting point connecting with Minh Khai street, ending point intersecting with Ring Road 3.

The project started in 2016 and was expected to be completed after 3 years, but was delayed due to difficulties in site clearance.

By December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion, an increase of VND 1,287 billion. At the same time, the project implementation period was also adjusted from 2016-2026.

Speaking with Lao Dong, Mr. Vu Tuan Dat - Director of the Hoang Mai District Land Fund Development Center - said that the Tam Trinh Road construction project has a total land acquisition area (after adjusting the boundary) of about 54,009 m2, involving about 1,590 households and 20 organizations, located in the area of ​​3 wards: Mai Dong, Hoang Van Thu and Yen So.

Regarding the progress of site clearance, Hoang Mai district has so far approved all plans of the organizations. Most of the organizations have received money and handed over the site for the project.

For land of households and individuals, local authorities have approved nearly 400 plans.

Hoang Mai District Land Fund Development Center and wards have conducted investigation, counting, and verification of time, origin, and land use process for the remaining cases.

Hoang Mai District strives to complete the approval of compensation, support, and resettlement plans when the State reclaims land to implement the Tam Trinh road construction project by the end of 2024 (3 months later than the district's plan).

According to Mr. Vu Tuan Dat, there are currently 4 locations on Tam Trinh Street that have clean land with relatively large areas for contractors to carry out construction of some items of the project.

a
According to Lao Dong, in recent days, contractors have begun construction to expand Tam Trinh Street in locations where the land has been cleared. In the photo is the area formerly known as Mai Dong Market, which has been cleared for the project. Photo: Huu Chanh
a
Another section of the route is also being expanded by the contractor, with machinery and workers being mobilized to widen the road. Photo: Huu Chanh
a
Machinery and workers deploy construction items of the project. Photo: Huu Chanh
a
The drainage system is being installed in front of the HC Electronics Supermarket area. Photo: Huu Chanh
Truoc do, co quan chuc nang cung da tien hanh di doi hang tram cay xanh tren duong Tam Trinh (doan ven song) de phuc vu thi cong mo rong du an. Anh: Huu Chanh
Previously, the authorities also moved hundreds of trees on Tam Trinh Street (the sidewalk section adjacent to Kim Nguu River) to serve the project construction. Photo: Huu Chanh
a
Workers at the construction site of the Tam Trinh road expansion project. Photo: Huu Chanh
a
Actual records show that most of the land on the route has not been handed over to the construction unit. Photo: Huu Chanh
a
People demolish their houses and hand over the site to the project. Photo: Huu Chanh
a
The site clearance work is expected to be completed by the end of 2024. When there is enough land, the contractor will carry out construction simultaneously on the entire route. The expansion of Tam Trinh Street is expected to be completed in 2026 with a cross-section of 40m and 6 lanes. Photo: Huu Chanh
HỮU CHÁNH
RELATED NEWS

SEA Games 33 Medal Schedule on December 12

|

Updated total medal table of the 33rd SEA Games on December 13.

Thailand dissolves the House of Representatives, opens the way for early elections

|

The Royal Thai newspaper has issued a decree to dissolve the House of Representatives after the Prime Minister admitted that the government is no longer capable of operating effectively.

Headache recruiting and retaining miners

|

Quang Ninh - High income, some earn more than half a billion VND/year along with many preferential mechanisms and policies, but recruiting and retaining miners is increasingly difficult.

Hanoi Traffic Police discovered a series of overnight passenger buses carrying more people, tying motorbikes to the roof

|

Hanoi - During the night, the traffic police inspected Thang Long Avenue and discovered many passenger buses violating the law such as carrying more people and tying motorbikes to the roof.

Weather today 12.12: The North has scattered rain before receiving strong cold air

|

Weather today, December 12, scattered rain in the North. Cold at night and morning, some mountainous areas are very cold. The Southern region will have scattered showers and thunderstorms.

Hanoi Secretary proposed to be awarded a Medal

|

Secretary of the Hanoi Party Committee Nguyen Duy Ngoc was proposed to be awarded the First Class Military Exploit Order for his outstanding achievements in implementing Project 06.

Vietnam sports competition schedule at the 33rd SEA Games today (December 12)

|

Update the competition schedule of the Vietnam Sports Delegation at today's 33rd SEA Games (December 12).

Coach Kim Sang-sik wants U22 Vietnam crowned at Rajamangala

|

U22 Vietnam beat Malaysia 2-0 to reach the semi-finals of the 33rd SEA Games, and coach Kim Sang-sik declared the team's goal to win the championship right at Rajamangala Stadium.

Hanoi reclaims land from more than 800 households to open a 40m wide road

HỮU CHÁNH |

Hanoi - Linh Nam Street (Hoang Mai District) is over 3km long and will be widened to 22.5-40m, with 829 households and 19 organizations having their land recovered.

Hanoi is about to forcibly reclaim land to widen the central road to 21m

HỮU CHÁNH |

Hanoi - Authorities are preparing to enforce land acquisition to expand a 720m road, costing about 400 billion VND, after many years of delay.

Two projects worth nearly 1,000 billion VND change the face of West Lake traffic

HỮU CHÁNH |

Hanoi - The completion of the Au Co Street expansion project and the Xuan Dieu Street upgrade project will help reduce traffic congestion and contribute to changing the traffic landscape of Tay Ho district.