Hanoi begins to expand main road to 40m, capital of 3,300 billion

HỮU CHÁNH |

Hanoi - Contractors have begun construction to expand Tam Trinh Street in locations where the ground is cleared.

The Tam Trinh road construction investment project was approved by the Hanoi People's Committee in 2012, with a total investment of VND 2,066 billion.

The invested construction route is about 3.5km long, starting point connecting with Minh Khai street, ending point intersecting with Ring Road 3.

The project started in 2016 and was expected to be completed after 3 years, but was delayed due to difficulties in site clearance.

By December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion, an increase of VND 1,287 billion. At the same time, the project implementation period was also adjusted from 2016-2026.

Speaking with Lao Dong, Mr. Vu Tuan Dat - Director of the Hoang Mai District Land Fund Development Center - said that the Tam Trinh Road construction project has a total land acquisition area (after adjusting the boundary) of about 54,009 m2, involving about 1,590 households and 20 organizations, located in the area of ​​3 wards: Mai Dong, Hoang Van Thu and Yen So.

Regarding the progress of site clearance, Hoang Mai district has so far approved all plans of the organizations. Most of the organizations have received money and handed over the site for the project.

For land of households and individuals, local authorities have approved nearly 400 plans.

Hoang Mai District Land Fund Development Center and wards have conducted investigation, counting, and verification of time, origin, and land use process for the remaining cases.

Hoang Mai District strives to complete the approval of compensation, support, and resettlement plans when the State reclaims land to implement the Tam Trinh road construction project by the end of 2024 (3 months later than the district's plan).

According to Mr. Vu Tuan Dat, there are currently 4 locations on Tam Trinh Street that have clean land with relatively large areas for contractors to carry out construction of some items of the project.

a
According to Lao Dong, in recent days, contractors have begun construction to expand Tam Trinh Street in locations where the land has been cleared. In the photo is the area formerly known as Mai Dong Market, which has been cleared for the project. Photo: Huu Chanh
a
Another section of the route is also being expanded by the contractor, with machinery and workers being mobilized to widen the road. Photo: Huu Chanh
a
Machinery and workers deploy construction items of the project. Photo: Huu Chanh
a
The drainage system is being installed in front of the HC Electronics Supermarket area. Photo: Huu Chanh
Truoc do, co quan chuc nang cung da tien hanh di doi hang tram cay xanh tren duong Tam Trinh (doan ven song) de phuc vu thi cong mo rong du an. Anh: Huu Chanh
Previously, the authorities also moved hundreds of trees on Tam Trinh Street (the sidewalk section adjacent to Kim Nguu River) to serve the project construction. Photo: Huu Chanh
a
Workers at the construction site of the Tam Trinh road expansion project. Photo: Huu Chanh
a
Actual records show that most of the land on the route has not been handed over to the construction unit. Photo: Huu Chanh
a
People demolish their houses and hand over the site to the project. Photo: Huu Chanh
a
The site clearance work is expected to be completed by the end of 2024. When there is enough land, the contractor will carry out construction simultaneously on the entire route. The expansion of Tam Trinh Street is expected to be completed in 2026 with a cross-section of 40m and 6 lanes. Photo: Huu Chanh
HỮU CHÁNH
RELATED NEWS

Fishermen hit big with tuna on the first sea trip of the year

|

Khanh Hoa - Tuna fishing vessels of fishermen dock at ports with holds full of seafood, bringing in large revenues.

Understanding taxes correctly: Business households need to "know" 5 important things when switching to declaration

|

Business households are required to memorize 5 things below when switching from fixed tax to declaration in 2026.

2026 weather forecast into the hottest heat group in 176 years

|

The latest weather forecast models show that 2026 may be in the group of 4 hottest years since 1850.

Gold price update morning of February 28: Suddenly soaring

|

Gold price update morning of February 28: World gold prices surge. Domestic market is likely to increase accordingly in the new trading session.

Russia has a lever of global influence stronger than oil and gas

|

Russia's oil and gas are subject to many sanctions, but nuclear energy is a different story.

People next to Lang street hope to remove the "bottleneck", returning a safe path

|

Hanoi - Lang Street is frequently congested, sidewalks are narrow; expansion is necessary to reduce traffic pressure and ensure travel safety.

Hanoi sets milestone to eliminate gasoline and oil taxis

|

Hanoi - The roadmap is to complete the conversion of all gasoline and oil taxis to electric and green-energy taxis in the city by 2030 at the latest.

Hanoi reclaims land from more than 800 households to open a 40m wide road

HỮU CHÁNH |

Hanoi - Linh Nam Street (Hoang Mai District) is over 3km long and will be widened to 22.5-40m, with 829 households and 19 organizations having their land recovered.

Hanoi is about to forcibly reclaim land to widen the central road to 21m

HỮU CHÁNH |

Hanoi - Authorities are preparing to enforce land acquisition to expand a 720m road, costing about 400 billion VND, after many years of delay.

Two projects worth nearly 1,000 billion VND change the face of West Lake traffic

HỮU CHÁNH |

Hanoi - The completion of the Au Co Street expansion project and the Xuan Dieu Street upgrade project will help reduce traffic congestion and contribute to changing the traffic landscape of Tay Ho district.