Hundreds of trees were moved to open a 40m wide road in Hanoi

HỮU CHÁNH |

Hanoi - Authorities have basically completed the relocation of hundreds of trees to widen Tam Trinh Street to 40m, with an investment of more than 3,300 billion VND.

Recently, functional units have relocated hundreds of trees to implement the Tam Trinh Road Construction Investment Project (Hoang Mai District, Hanoi).

According to Lao Dong's records on September 25, the work of moving and relocating trees on Tam Trinh Street (along the sidewalk adjacent to Kim Nguu River) has been basically completed.

a
More than 400 trees on Tam Trinh Street (Hoang Mai District, Hanoi) have been relocated and cut down to serve the construction of Tam Trinh Street expansion. Photo: Huu Chanh
a
The sidewalk is currently littered with bricks and stones. Photo: Huu Chanh

According to research, there are more than 400 trees on the sidewalk of Tam Trinh Street within the project implementation boundary. Of these, more than 200 trees were relocated to new locations.

These trees are of many types such as banyan, purple-flowered lagerstroemia, banyan, bodhi, milk flower, muong, barringtonia, royal poinciana, tamarind... and are growing normally.

a
A rare tree on Tam Trinh Street that has not been relocated. Photo: Huu Chanh

Notably, more than 180 trees, including many urban trees with large diameters and many years of growth, were cut down, including species such as the Indian almond, Lagerstroemia, cotton, banyan, gao, hoa sua, muong, xa mat, phoenix, and sau sau trees...

The reason for cutting down a large number of trees during the Tam Trinh Road Expansion Project is that these trees were found to have rotten roots, rotten trunks, crooked, and broken tops...

q
Tam Trinh Street will be expanded to 40m with 6 lanes. Photo: Huu Chanh

Regarding the implementation of the Tam Trinh Road Expansion Project, the People's Committee of Hoang Mai District said that recently, the district has directed functional departments and 3 wards including Yen So, Hoang Van Thu, and Mai Dong to speed up the site clearance progress, basically completing it before October 1, 2024.

According to the People's Committee of Hoang Mai district, to implement the project, it is necessary to reclaim land related to 811 residential plots, 800 agricultural plots, and 20 organizational plots.

After having the site, the contractor will focus on construction and strive to basically complete the expansion of Tam Trinh Street by 2026.

Quan Hoang Mai dang day nhanh tien do giai phong mat bang de thi cong mo rong duong Tam Trinh. Anh: Huu Chanh
a
Hoang Mai District is speeding up site clearance to expand Tam Trinh Street. Photo: Huu Chanh

According to Lao Dong's research, the Tam Trinh Road construction investment project was approved by the Hanoi People's Committee in 2012.

The invested construction route is about 3.5km long, starting point connecting with Minh Khai street, ending point intersecting with Ring Road 3 with a total investment of 2,066 billion VND.

The project started in 2016 and was expected to be completed after 3 years, but until now it has not been able to be constructed for many reasons, the biggest difficulty of which is site clearance.

By December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion, an increase of VND 1,287 billion. At the same time, the project implementation period was also adjusted from 2016-2026.

After being expanded, Tam Trinh Street will have a 40m cross-section with 6 lanes, expected to reduce traffic pressure on the main roads at the southern gateway of the capital.

HỮU CHÁNH
RELATED NEWS

Going stormy to celebrate U22 Vietnam, people still stop at red lights "all the way"

|

Hanoi - On the evening of December 18, thousands of people took to the streets to celebrate U22 Vietnam defeating U22 Thailand 3-2, winning the gold medal at the 33rd SEA Games.

Mr. Kim Sang-sik's special milestone at Rajamangala Stadium

|

In less than a year, coach Kim Sang-sik and his Vietnamese football team defeated Thailand twice at Rajamangala Stadium.

Ho Chi Minh City Ring Road 3 construction site is brightly lit all night, waiting for technical traffic opening on December 19

|

HCMC - Before the technical opening time (December 19), the Ho Chi Minh City Ring Road 3 construction site was brightly lit all night, workers and engineers raced to complete the final items.

Traffic participants feel more secure thanks to AI cameras

|

Hanoi - installing AI cameras on many routes helps traffic participants feel safer, raises awareness of law compliance and reduces violations.

Preventing the sale of social insurance books is the responsibility of Vietnam Social Insurance

|

Recently, the situation of buying, selling, and mortgaging social insurance books (SI) has continued to occur publicly on social networks and in many localities.

SEA Games 33 Medal Schedule on December 18

|

Updated total medal rankings at the 33rd SEA Games today (December 18).

Hanoi gateway road to be expanded 6 times, capital of nearly 1,500 billion VND

HỮU CHÁNH |

The main gateway road to Hanoi is about to be widened from 7-8m to 52m to help reduce traffic congestion and contribute to the socio-economic development of the capital.

People demolish houses, hand over land to build 57km road through Hanoi

HỮU CHÁNH |

Hanoi - Many people in Me Linh district simultaneously demolished their houses to hand over the land for the Ring Road 4 project.

Hiện trạng giải phóng mặt bằng mở rộng đường Tam Trinh

NGỌC THÙY |

UBND quận Hoàng Mai (Hà Nội) đang nỗ lực đẩy nhanh tiến độ giải phóng mặt bằng phục vụ dự án mở rộng đường Tam Trinh.