Hundreds of trees were moved to open a 40m wide road in Hanoi

HỮU CHÁNH |

Hanoi - Authorities have basically completed the relocation of hundreds of trees to widen Tam Trinh Street to 40m, with an investment of more than 3,300 billion VND.

Recently, functional units have relocated hundreds of trees to implement the Tam Trinh Road Construction Investment Project (Hoang Mai District, Hanoi).

According to Lao Dong's records on September 25, the work of moving and relocating trees on Tam Trinh Street (along the sidewalk adjacent to Kim Nguu River) has been basically completed.

a
More than 400 trees on Tam Trinh Street (Hoang Mai District, Hanoi) have been relocated and cut down to serve the construction of Tam Trinh Street expansion. Photo: Huu Chanh
a
The sidewalk is currently littered with bricks and stones. Photo: Huu Chanh

According to research, there are more than 400 trees on the sidewalk of Tam Trinh Street within the project implementation boundary. Of these, more than 200 trees were relocated to new locations.

These trees are of many types such as banyan, purple-flowered lagerstroemia, banyan, bodhi, milk flower, muong, barringtonia, royal poinciana, tamarind... and are growing normally.

a
A rare tree on Tam Trinh Street that has not been relocated. Photo: Huu Chanh

Notably, more than 180 trees, including many urban trees with large diameters and many years of growth, were cut down, including species such as the Indian almond, Lagerstroemia, cotton, banyan, gao, hoa sua, muong, xa mat, phoenix, and sau sau trees...

The reason for cutting down a large number of trees during the Tam Trinh Road Expansion Project is that these trees were found to have rotten roots, rotten trunks, crooked, and broken tops...

q
Tam Trinh Street will be expanded to 40m with 6 lanes. Photo: Huu Chanh

Regarding the implementation of the Tam Trinh Road Expansion Project, the People's Committee of Hoang Mai District said that recently, the district has directed functional departments and 3 wards including Yen So, Hoang Van Thu, and Mai Dong to speed up the site clearance progress, basically completing it before October 1, 2024.

According to the People's Committee of Hoang Mai district, to implement the project, it is necessary to reclaim land related to 811 residential plots, 800 agricultural plots, and 20 organizational plots.

After having the site, the contractor will focus on construction and strive to basically complete the expansion of Tam Trinh Street by 2026.

Quan Hoang Mai dang day nhanh tien do giai phong mat bang de thi cong mo rong duong Tam Trinh. Anh: Huu Chanh
a
Hoang Mai District is speeding up site clearance to expand Tam Trinh Street. Photo: Huu Chanh

According to Lao Dong's research, the Tam Trinh Road construction investment project was approved by the Hanoi People's Committee in 2012.

The invested construction route is about 3.5km long, starting point connecting with Minh Khai street, ending point intersecting with Ring Road 3 with a total investment of 2,066 billion VND.

The project started in 2016 and was expected to be completed after 3 years, but until now it has not been able to be constructed for many reasons, the biggest difficulty of which is site clearance.

By December 2023, the Hanoi People's Committee issued a decision to adjust the project, increasing the investment capital to VND 3,354 billion, an increase of VND 1,287 billion. At the same time, the project implementation period was also adjusted from 2016-2026.

After being expanded, Tam Trinh Street will have a 40m cross-section with 6 lanes, expected to reduce traffic pressure on the main roads at the southern gateway of the capital.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi leaders talk about the roadmap to convert gasoline vehicles to electric vehicles

|

Hanoi will support the conversion of gasoline-powered vehicles to green fuel, applied first to people in Ring Road 1 and expanded in Ring Road 2.

The billiards community mourns Chang Jun-lin's sudden passing

|

The international billiards community was moved to commemorate player Chang Jung-lin, who recently passed away in Jakarta while participating in the 2025 PBC Indonesia tournament.

Super-small neighborhood in the heart of Ho Chi Minh City has a fire fighting system, people are still not assured

|

HCMC - Although the micro-neighborhood in the middle of HCMC has been installed with a fire fighting system by the locality, people are still worried about the risk of fire and explosion, so they open additional escape routes themselves.

Dead pigs dumped on the streets of Hanoi, Ministry of Agriculture and Environment speaks out

|

The Deputy Minister of Agriculture and Environment requested to resolutely prevent the situation of throwing dead pigs onto the road, causing the spread of the epidemic.

Top 10 localities with the most scores in 10 Math subjects, Hanoi leads

|

In the 2025 high school graduation exam, Hanoi is the leading locality in the country in terms of 10 points in Math.

Associate high school graduation exam scores: No 10 Literature scores

|

The Ministry of Education and Training has announced the scores for the 2025 high school graduation exam. Literature did not record a score of 10.

Hanoi gateway road to be expanded 6 times, capital of nearly 1,500 billion VND

HỮU CHÁNH |

The main gateway road to Hanoi is about to be widened from 7-8m to 52m to help reduce traffic congestion and contribute to the socio-economic development of the capital.

People demolish houses, hand over land to build 57km road through Hanoi

HỮU CHÁNH |

Hanoi - Many people in Me Linh district simultaneously demolished their houses to hand over the land for the Ring Road 4 project.

Hiện trạng giải phóng mặt bằng mở rộng đường Tam Trinh

NGỌC THÙY |

UBND quận Hoàng Mai (Hà Nội) đang nỗ lực đẩy nhanh tiến độ giải phóng mặt bằng phục vụ dự án mở rộng đường Tam Trinh.