The project to renovate and upgrade National Highway 1A, Van Dien - Ngoc Hoi section (Km 185 - Km 189) in Thanh Tri district was approved for investment by the Hanoi People's Committee in 2010.
The project has a total investment of nearly 890 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.
The building has a length of 3.8km, through 4 communes of Tu Hiep, Ngu Hiep, Ngoc Hoi and Lien Ninh, the cross section is expanded to 46 - 56m.
In 2010, Thanh Tri district carried out site clearance work, reclaiming more than 185,000 square meters of land to implement the project.
In 2012 - 2013, Thanh Tri District People's Committee approved the compensation and support plan and handed over 92,674m2 of land to the investor. This area has been completed and put into use.
The remaining area of 93,072 square meters related to 806 households, individuals and organizations has not been able to recover and clear the land for many years.
In early 2023, the Hanoi People's Committee approved the adjustment of the implementation time of the National Highway 1A upgrading project, Van Dien - Ngoc Hoi section (Km 185 - Km 189). Accordingly, the project implementation time will only be carried out until the end of 2024.
During the implementation process, Thanh Tri District People's Committee has approved all 806 plans and organized compensation and support payments to households, individuals and organizations.
Most cases have agreed to receive compensation and hand over the site, while some remaining cases have not complied.
Faced with pressure on progress as directed by the Hanoi People's Committee, the Thanh Tri District People's Committee has developed a plan to organize forced land recovery for cases that do not receive compensation and resettlement support.
Up to now, Thanh Tri district has basically completed site clearance for the land area serving the National Highway 1A expansion project from Van Dien to Ngoc Hoi section according to the progress requirements. The authorities have handed over the cleared site to the construction unit to implement the project.