Completing the Ring Road 4 parallel road in October is impossible

HỮU CHÁNH |

Hanoi - The completion of the Ring Road 4 parallel road in October is impossible, because the site handover progress of localities is too slow.

The Ring Road 4 project in the Capital Region started construction in June 2023 with a total length of 112.8km, passing through Hanoi, Hung Yen and Bac Ninh. The project has a total investment of more than 85,000 billion VND.

In Hanoi alone, the route is more than 57km long, passing through the districts: Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

a
A residential area in Tan Chau village (Chu Phan commune, Me Linh) has not yet handed over the site for the Ring Road 4 project. Photo: Huu Chanh

According to Lao Dong's records in package 8 - construction of the Ring Road 4 parallel road through Soc Son and Me Linh districts, the underground and above-ground infrastructure works have been basically relocated.

However, up to now, there are still two residential areas in Dai Thinh and Chu Phan communes (Me Linh district) that have not handed over the site for the project.

In package No. 9 - construction of Ring Road 4 through Dan Phuong and Hoai Duc districts, there are still land issues in three residential areas in Duc Thuong, Dong La communes (Hoai Duc) and Ha Mo commune (Dan Phuong).

In the Hong Ha bridge construction area, in Hong Ha commune (Dan Phuong district) and Van Khe commune (Me Linh district), many households have not yet agreed to hand over the site.

a
The factory and residential area in Duc Thuong commune (Hoai Duc, Hanoi) have not been cleared. Photo: Huu Chanh

Similarly, some sections of the site in package 10 - construction of parallel roads through Ha Dong district and Thanh Oai district have also many points that have not been handed over. The main obstacles are residential areas, factories and underground and above-ground technical infrastructure.

In package 11, the section through Thuong Tin district, residential areas within the project have been cleared. Currently, there are more than 10 points that have not been handed over, mainly underground and above-ground infrastructure works.

Regarding the site clearance for the Ring Road 4 project, Chairman of the Hanoi People's Committee Tran Sy Thanh has requested districts to complete land acquisition before April 15. Mr. Thanh emphasized that this is the deadline, no delays are allowed.

However, speaking with a reporter from Lao Dong Newspaper, Mr. Tran Viet Son - Commander of Package 11 (Cicenco 4 contractor) - said that completing site clearance before April 15 is very difficult.

"Previously, the city required localities to hand over enough land to contractors in the first quarter, then postponed it until before April 15. But until now, many sections are still in disarray. If the problems are resolved quickly, it will not be until the end of April at the earliest for the site clearance work to be completed" - Mr. Son said.

q
To Lich Bridge (package No. 11) cannot be constructed synchronously because the power line has not been relocated. Photo: Huu Chanh

In package No. 9, Commander Nguyen Hoang Hai said that the contractor regularly contacts Hoai Duc and Dan Phuong districts to update the site clearance progress. All localities are committed to handing over the land soon.

"Relevant units are relocating underground and above-ground technical infrastructure. However, the handover time for construction in the three residential areas is still unclear" - Mr. Hai said.

The delay in site handover by localities is seriously affecting the progress of the Ring Road 4 parallel road project, while the Chairman of the Hanoi People's Committee requested the project to be completed by October 2025, welcoming the City Party Congress.

"Completing the Ring Road 4 parallel road in October is not feasible, because the local site handover progress is too slow. Not to mention, the rainy season is approaching and will last for many months, greatly affecting the construction" - said the Commander of Package 9.

HỮU CHÁNH
RELATED NEWS

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

|

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Guarding for holidays, sticking to the construction site of Ring Road 4

|

Many workers and engineers postpone the Hung Vuong Commemoration Day holiday to stay at the construction site, speeding up the progress of the Ring Road 4 parallel road project in the Capital region.

River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

|

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Nepal has the first female prime minister

|

Former Supreme Court chief Justice Sushila Karki was sworn in as interim prime minister of Nepal on September 12, becoming the first woman to lead the country.

Big fire in Do Son Hai Phong Industrial Park, smoke column rises hundreds of meters high

|

Hai Phong - On the night of September 12, a major fire broke out at a company specializing in shoe production and processing in Do Son Industrial Park.

Appointment and assignment of personnel in Quang Ngai, Quang Tri, Hue, Ho Chi Minh City

|

From September 8 12.9, in the provinces/cities: Quang Ngai, Quang Ninh, Quang Tri, Hue City, Da Nang, Ho Chi Minh City... decisions on election, appointment, and appointment of personnel will be implemented.

O Thu leads soldiers across Thach Han River in real life and o Hong in the movie Red Rain

|

Quang Tri - O Thu is the person who rowed a boat to cross the river and the character O Hong in the movie Red Rain moved many people, reminiscing them of the tragic memories along the Thach Han River.

Vingroup has filed a lawsuit against Facebook account owner Hien Nguyen in a court in the US

|

Vingroup sued Facebooker Hien Nguyen in a US court for posting false information, demanding an end to his behavior and compensation for damages.

Accelerating the construction of Hanoi Ring Road 4, many sections have been revealed

HỮU CHÁNH |

Hanoi - The packages of the Ring Road 4 parallel road project are being accelerated to complete in 2025.

Guarding for holidays, sticking to the construction site of Ring Road 4

Hữu Chánh |

Many workers and engineers postpone the Hung Vuong Commemoration Day holiday to stay at the construction site, speeding up the progress of the Ring Road 4 parallel road project in the Capital region.

River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

HỮU CHÁNH |

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.