River-crossing bridges and railways on Hanoi's Ring Road 4 take shape

HỮU CHÁNH |

Hanoi - The three river-crossing bridges and railway of the Ring Road 4 parallel road project through Me Linh district have been revealed and are under construction.

Component project 2.1 invests in the construction of a parallel road system (urban road) of Ring Road 4 through Hanoi with a total length of about 58.2km.

The route passes through 7 districts including Soc Son, Me Linh, Dan Phuong, Hoai Duc, Ha Dong, Thanh Oai and Thuong Tin.

Recorded in package No. 8 - construction of a parallel road through Soc Son and Me Linh districts, after 21 months since the start of construction, the parallel road has revealed its shape.

Duong song hanh Vanh dai 4 doan qua huyen Me Linh (Ha Noi). Anh: Huu Chanh
The parallel road of Ring Road 4 through Me Linh district (Hanoi) has reached about 70% of the workload after 21 months from the start of construction. In the distance is the Hau village overpass under construction. Photo: Huu Chanh

Speaking with Lao Dong, Mr. Nguyen Hoai Nam - Head of the Technical Department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - said that package No. 8 has a total length of about 23km, of which about 20km of parallel roads have been paved with asphalt.

Some sections on the route are being constructed with crushed stone by the contractor.

s
In the photo is the overpass of the North-South railway line Hanoi - Lao Cai under construction on the Ring Road 4 parallel road through Me Linh (Hanoi). Photo: Huu Chanh
Cau co 27 nhip voi chieu dai gan 590m, mat cat ngang moi ben 15m. Anh: Huu Chanh
The bridge has 27 spans with a length of nearly 590m, with a cross-section of 15m on each side. Photo: Huu Chanh

Package 8 also undertakes the construction of 3 overpasses on the route including the Ca Lo River overpass connecting Soc Son with Me Linh, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

Of these, the railway overpass is the largest bridge built under package No. 8. The project is nearly 590m long with 27 spans on both sides, the width of the bridge deck is 15m on each side.

"2 weeks ago, the power line within the scope of the project was relocated. After the ground, the contractor conducted the construction of 4 bridges and the remaining 8 beats. It is expected that by June, the bridge will basically complete the construction.

The contractor is also ensuring the construction progress of the remaining 2 bridges in package 8, including Ca Lo bridge and Hau village bridge.

Cau vuot song Ca Lo da co ban hoan thanh cac hang muc chinh. Anh: Huu Chanh
The Ca Lo River overpass connecting Soc Son and Me Linh districts has basically completed the main items. Photo: Huu Chanh
Cong nhan dang thi cong hang muc lan can cau vuot song Ca Lo. Anh: Huu Chanh
Workers are constructing the railing of the Ca Lo River overpass. Photo: Huu Chanh

Regarding the progress of package No. 8, Mr. Nam said that up to this point, the contractor consortium has completed about 70% of the construction volume, ensuring progress compared to the plan.

According to Mr. Nguyen Hoai Nam, there are still 2 residential areas in Dai Thinh and Chu Phan communes (Me Linh) that have not been handed over the project.

"With the sections that have cleared the ground, the contractor consortium is committed to completing the Ring Road 4 parallel road project through Me Linh and Soc Son in 2025" - Mr. Nam affirmed.

HỮU CHÁNH
TIN LIÊN QUAN

Land reclamation for more than 180 households to build a road in the center of Hanoi

|

Hanoi - Tay Ho District will reclaim 36,482.5m2 of land from more than 180 households, organized to build Dang Thai Mai Street, 1.2km long, with an investment capital of more than 550 billion VND.

There is still 1 month left to hand over enough land to expand Tam Trinh Street

|

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

Hanoi begins construction of nearly VND2,400 billion intersection

|

Hanoi - The project of the different level of the intersection between Ring Road 3.5 and Thang Long Avenue, with an investment capital of nearly VND 2,400 billion, has begun construction.

HCMC installs 20 LED screens for people to watch the parade on the morning of April 30

|

Ho Chi Minh City has installed 20 LED screens on major roads in the central area for people and tourists to directly watch the parade and parade to celebrate the 50th anniversary of the country's reunification.

Restaurant fire in Hanoi

|

Hanoi - The fire that broke out at a restaurant in Nam Tu Liem district late in the afternoon of April 3, 2025 caused panic among people.

The death anniversary of Hung Vuong's great monk in Phu Tho is a grand festival

|

Phu Tho - The Hung Temple historical relic site is being decorated with many colors from the cultural funds of 13 districts, cities and towns in the area.

Lam Dong reforms to become an attractive destination for investors

|

Lam Dong - The locality is committed to strongly reforming administrative procedures, aiming to make the province an attractive destination for investors.

Dry port project in Hoai Duc abandoned for many years

|

The ICD My Dinh dry port project in Hoai Duc, Hanoi has been approved for nearly 10 years but has not been completed. However, the project's land has shown signs of lease.

Land reclamation for more than 180 households to build a road in the center of Hanoi

HỮU CHÁNH |

Hanoi - Tay Ho District will reclaim 36,482.5m2 of land from more than 180 households, organized to build Dang Thai Mai Street, 1.2km long, with an investment capital of more than 550 billion VND.

There is still 1 month left to hand over enough land to expand Tam Trinh Street

HỮU CHÁNH |

Hanoi - Hoang Mai District scheduled to hand over enough land to expand Tam Trinh Street on April 30. Thus, there is 1 month left for the locality to complete this target.

Hanoi begins construction of nearly VND2,400 billion intersection

SÓNG HỮU - KHÁNH LINH |

Hanoi - The project of the different level of the intersection between Ring Road 3.5 and Thang Long Avenue, with an investment capital of nearly VND 2,400 billion, has begun construction.