Complete the expansion of Hanoi's central road in September 2025

HỮU CHÁNH |

Hanoi - According to the plan, the project to expand Nguyen Tuan Street to 720m long, with an investment capital of nearly 400 billion VND, will be completed in September 2025.

The project to renovate and expand Nguyen Tuan Street was approved by the People's Committee of Thanh Xuan District (Hanoi) in 2018, with a total investment of nearly 400 billion VND.

The project is 720m long, starting at the intersection with Nguyen Trai Street, ending at Lane 162 Nguyen Tuan, with a cross-section of 21m, including a 15m wide roadway and 3m wide sidewalks on both sides.

To implement the project to renovate and expand Nguyen Tuan Street, Thanh Xuan District will reclaim and clear 14,334m2 of land from 11 organizations and 160 households and individuals.

However, the Nguyen Tuan Street expansion project could not be implemented according to the original plan because many households did not agree to hand over the site.

After many times of propaganda and mobilizing people, it was not until November 2024 that the site clearance work for the Nguyen Tuan Street expansion project was basically completed.

After the site was available, the leaders of Thanh Xuan District People's Committee directed the Construction Investment Project Management Board and the contractor to deploy the steps to construct the project.

According to the Steering Committee of the Thanh Xuan District Construction Investment Project Management Board, many trees on the route have been relocated and cut down by authorities; the power line and telecommunication cables are also being relocated by the Project Management Board in coordination with related units.

Currently, the main work being implemented by the contractor on the construction site is the construction of a wastewater drainage system. The location is being implemented in front of the Institute of Industrial Ceramics and glass (Ministry of Industry and Trade).

According to this person, up to now, there is still a 2-storey apartment building (next to Son La Guest House) whose compensation plan has not been approved.

"From now until the construction of the drainage system to that location, the Project Management Board will coordinate with relevant parties to complete site clearance to hand over to the construction contractor" - said the leader of the Thanh Xuan District Construction Investment Project Management Board.

According to Lao Dong's records on the first day of March, machinery and personnel are being mobilized by the contractor to implement some items of the project.

Nguyen Tuan is an important route in Thanh Xuan District, with a large volume of people and vehicles participating in traffic, which makes the contractor have to both construct and ensure traffic.

The investor's representative said that according to the plan, the project will be completed in September 2025.

After being expanded, Nguyen Tuan Street will help reduce traffic congestion in the area, beautify the urban area, and contribute to the socio-economic development of Hanoi in general and Thanh Xuan District in particular.

Diem dau du an tai nut g
In the photo is the starting point of the project to expand Nguyen Tuan Street at the intersection with Nguyen Trai Street (Thanh Xuan District, Hanoi). Photo: Huu Chanh
Den nay cong tac giai phong mat bang da co ban hoan thanh
Up to now, most of the site has been handed over by the investor to the construction contractor. Photo: Huu Chanh
Hien con duy nhat khu tap the
Currently, there is only one 2-storey apartment complex on the route that has not been cleared. Photo: Huu Chanh
Nhieu cay xanh
Many trees on Nguyen Tuan Street have been relocated and cut down by authorities. Photo: Huu Chanh
s
The road will start to be expanded from the end of 2024. Photo: Huu Chanh
Nha thau tien hanh rao chan nhung doan da co mat bang de thi cong mo rong duong Nguyen Tuan. Anh: Huu Chanh
The contractor has fenced off sections with available land to construct the expansion of Nguyen Tuan Street. Photo: Huu Chanh
s
Construction site of the project to expand Nguyen Tuan Street through the Institute of Industrial Ceramics and glass (Ministry of Industry and Trade). Photo: Huu Chanh
s
The Nguyen Tuan Street expansion project is expected to be completed in September 2025 with a cross-section of 21m, helping to reduce traffic congestion, contributing to local socio-economic development. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

After more than 10 years, the billion-dollar road in Hanoi has only reached 40% progress

|

Hanoi - After more than 10 years of construction, the Dam Hong - National Highway 1 Ring Road 2.5 project is still unfinished, affecting people's travel and daily life.

The billion-dollar road unfinished in Hanoi before restart date

|

Hanoi - After the problem is resolved, the contractor will implement the construction of the belt section worth more than 1,300 billion VND after many years of unfinished work.

Relocating many trees to open the central road of Hanoi to 21m

|

Hanoi - The authorities have relocated many trees to implement the construction of the 720m-long Nguyen Tuan Street expansion, with an investment capital of nearly 400 billion VND.

Weather forecast for the next 10 days from 4.3 to 13.3 in all three regions

|

The National Center for Hydro-Meteorological Forecasting forecasts the weather for the next 10 days (from the night of March 3 to March 13.) in areas across the country.

Audiences mention Tu Long after Hoa Minzy's MV Bac Bling

|

A series of artists were mentioned when Hoa Minzy released a new MV in her hometown of Bac Ninh.

Ukrainian President Zelensky declares he will not be easily replaced

|

Ukrainian President Volodymyr Zelensky has said that replacing him at this time is not simple, but he is ready to resign on one condition.

The Ministry of Home Affairs proposes to review the quantity and quality of commune civil servants

|

The Ministry of Home Affairs requests the People's Committees of provinces and centrally run cities to review the quantity and quality of commune-level cadres and civil servants as of December 31, 2024.

Controversy giacks over attack on Russia- Europe gas pipeline

|

Hungary has warned that if the Russia-China gas pipeline TurkStream is disabled, it will seriously affect the country's energy security.

After more than 10 years, the billion-dollar road in Hanoi has only reached 40% progress

HỮU CHÁNH |

Hanoi - After more than 10 years of construction, the Dam Hong - National Highway 1 Ring Road 2.5 project is still unfinished, affecting people's travel and daily life.

The billion-dollar road unfinished in Hanoi before restart date

HỮU CHÁNH |

Hanoi - After the problem is resolved, the contractor will implement the construction of the belt section worth more than 1,300 billion VND after many years of unfinished work.

Relocating many trees to open the central road of Hanoi to 21m

HỮU CHÁNH |

Hanoi - The authorities have relocated many trees to implement the construction of the 720m-long Nguyen Tuan Street expansion, with an investment capital of nearly 400 billion VND.