Technical exploitation of Long Thanh airport runway before April 30

HÀ ANH CHIẾN |

Vietnam Airports Corporation (ACV) is determined to direct construction units to complete and technically exploit the runway and taxiway of Long Thanh airport before April 30, 2025.

7,000 experts, engineers, and workers working on the construction site

According to Vietnam Airports Corporation (ACV), for Component Project 3 - Long Thanh Airport Construction Investment Project Phase 1 - up to now, the site clearance compensation and leveling work have been basically completed on schedule, ensuring quality, security, safety and environmental sanitation.

For the main packages being implemented at the construction site, the Long Thanh Airport Project Management Board has directed the construction units to speed up the construction progress of the packages, organizing hundreds of construction teams with nearly 7,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment, organizing the construction site scientifically, professionally, and orderly, ensuring security and safety during the construction process.

Package 5.10, construction of the passenger terminal, considered the heart of the entire Long Thanh airport project, phase 1, is currently installing the terminal's steel roof. Up to now, the main steel truss installation has been 100% completed in the wing area and 47% completed in the central area. We are striving to complete the roof steel structure work before the 2025 rainy season to ensure the installation of equipment systems inside the terminal.

For package 4.6, runway construction, ACV is determined to direct construction units to complete and technically exploit the runway and taxiway before April 30, 2025 to celebrate the 50th anniversary of National Reunification Day (April 30, 1975 - April 30, 2025), 3 months ahead of schedule in the contract.

For package 6.12, the construction of 2 routes connecting Long Thanh airport is also scheduled to strive to complete and technically open Route 1 before April 30, 2025 and complete and hand over the project for use before September 2, 2025.

In addition, ACV has proactively adjusted the contractor selection plan with the goal of synchronizing operations with the passenger terminal. For the remaining packages of the project (cargo terminal, parking lot, ICT system...), ACV has built a schedule and is determined to complete them according to the Prime Minister's direction.

Mr. Duong Quang Dien - Permanent Deputy Director of Long Thanh Airport Project Management Board - said: "In 2025, we are determined to basically complete the construction work of Long Thanh airport project phase 1".

Construction during Tet at Long Thanh airport construction site

To complete the progress quickly and ensure quality, ACV said that in the coming time, the construction site will continue to increase the construction force, taking advantage of favorable dry season weather to speed up and urgently carry out construction.

ACV requires that the construction site maintain over 70% of the construction workers during the Lunar New Year 2025. In addition to working during the holiday, contractors will also work at night. ACV also requires contractors to plan construction during the Tet holiday, ensuring the best construction volume, but also creating a favorable environment for workers to be happy, warm, and feel the care of the units during the project implementation process.

According to Mr. Nguyen Duc Thuan - Deputy Executive Director of the Joint Venture for Package 5.10, construction of Long Thanh airport passenger terminal, to ensure the progress of the project, the joint venture contractor has planned to mobilize workers and engineers to work through the 2025 Lunar New Year, maintaining 70% of the workforce throughout the holiday.

Lieutenant Colonel Le Van Tien - of the Aviation Construction Corporation (ACC) - Commander of the Joint Venture of Package 4.6, construction of the Long Thanh airport runway - informed: The Joint Venture of Contractors has come up with a plan, construction teams on duty during Tet and construction through Tet, human resources, machinery and equipment are guaranteed to remain the same and divided into construction teams to ensure the construction work meets and exceeds the schedule.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Progress of 6,268 billion VND package at Long Thanh airport project

|

Dong Nai – According to Vietnam Airports Corporation (ACV), package 4.7 worth 6,268 billion VND at Long Thanh airport project has completed many works.

Dong Nai invests in building 8 km of new road connecting Long Thanh airport

|

Dong Nai Provincial People's Committee will invest 1,400 billion VND to build a new DT 769E road connecting the eastern gate of Long Thanh airport with DT 770B road, passing through Long Thanh and Cam My districts.

Construction of 11,066 billion VND package at Long Thanh airport project

|

Dong Nai – Vietnam Airports Corporation (ACV) informed that package 4.8 of Long Thanh airport project is simultaneously implementing main items.

Progress of the 2,880 billion VND package at Long Thanh airport project

|

Dong Nai - According to Vietnam Airports Corporation (ACV), the Long Thanh airport aviation fuel supply package has tested bored pile construction.

The "sea monster" hunter

|

There it was. The real monster. The silhouette of a bull shark looming through the dark blue water made my heart nearly jump out of my chest...

Supermarkets and markets in Ho Chi Minh City reopen, goods are abundant

|

On January 30 (the second day of Tet), supermarkets and markets in Ho Chi Minh City reopened to serve people's shopping needs.

Army adjusts 2,700 organizations

|

Implementing the streamlining policy, the army completed adjusting over 2,700 organizations; built over 1,200 organizational and staffing charts in a streamlined direction.

US plane collides with Black Hawk helicopter, many people died

|

A US plane carrying 64 people collided with a Black Hawk helicopter carrying 3 people near Reagan airport, both fell into the river.

Progress of 6,268 billion VND package at Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai – According to Vietnam Airports Corporation (ACV), package 4.7 worth 6,268 billion VND at Long Thanh airport project has completed many works.

Dong Nai invests in building 8 km of new road connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Provincial People's Committee will invest 1,400 billion VND to build a new DT 769E road connecting the eastern gate of Long Thanh airport with DT 770B road, passing through Long Thanh and Cam My districts.

Construction of 11,066 billion VND package at Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai – Vietnam Airports Corporation (ACV) informed that package 4.8 of Long Thanh airport project is simultaneously implementing main items.

Progress of the 2,880 billion VND package at Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - According to Vietnam Airports Corporation (ACV), the Long Thanh airport aviation fuel supply package has tested bored pile construction.