A series of traffic projects are unfinished in Nam Tu Liem

HỮU CHÁNH |

Hanoi - Difficulties in site clearance have caused a series of transport projects in Nam Tu Liem to be unfinished for many years.

Vu Quynh route connecting to Le Duc Tho - Pham Hung road is an important traffic project of Nam Tu Liem district (Hanoi), connecting with main routes such as Me Tri road and the route from Me Tri to Do Duc Duc.

The project is 1.4km long, meeting 6 lanes, passing through Phu Do, My Dinh 1 and My Dinh 2 wards.

The project has a total investment of 253 billion VND, starting from 2020. According to the plan, the project will be completed after 450 days.

However, after about 5 years of construction, the project has not been able to reach the finish line even though most of the volume has been completed.

Mot phan mat bang doan nut giao duong Vu Quynh - Dinh Thon chua duoc giai phong. Anh: Huu Chanh
Part of the site at the intersection of Vu Quynh - Dinh Thon road (Nam Tu Liem, Hanoi) has not been cleared. Photo: Huu Chanh

According to the People's Committee of Nam Tu Liem District, the site clearance progress of the project has been completed by more than 70%. Currently, there are more than 1.5 hectares of land belonging to a number of agencies and organizations and part of it is residential land of the people.

The People's Committee of Nam Tu Liem District has requested a first extension for the project until December 31, 2023. By August 15, 2023, the People's Committee of Nam Tu Liem District had organized the compulsory land recovery and handover of the site for project construction.

However, when the site clearance for the project passing through 3 wards is still not possible, there are changes to the 2024 Land Law, so policies related to site clearance must be re-implemented.

Currently, Nam Tu Liem District continues to request a second extension until the end of 2025.

Another project that is also being implemented sluggishly in Nam Tu Liem district is the road connecting Do Duc Duc Street to Me Tri Street.

The project was approved by the city, allowing the People's Committee of Nam Tu Liem District to conduct investment since 2014 with a scale of more than 264 billion VND, the length of the route is 828.58m.

The total land acquisition area in the project is 29,287.9m2, including residential land, pond land, agricultural land, public land, related to 146 households and 5 organizations.

Duong noi tu duong Do Duc Duc - Me Tri (Nam Tu Liem, Ha Noi) trien khai i ach nhieu nam. Anh: Huu Chanh
The road connecting Do Duc Duc - Me Tri road has been sluggishly implemented for many years. Photo: Huu Chanh

According to the People's Committee of Me Tri Ward, the site clearance process has been carried out since 2016. Currently, there are still 8/54 households on residential land that have not had their compensation plans approved; 4/76 households on pond land have handed over the site but have not received compensation and support, 2 households have not received the money and handed over the site.

On December 10, 2024, the People's Committee of Nam Tu Liem District issued Decision No. 2931/QD-UBND approving the adjustment of the project implementation time to the end of 2026.

On January 20, 2025, the Nam Tu Liem District Investment and Construction Project Management Board issued Document No. 44/QLDA to the District People's Committee, the District Land Valuation Council, and the District Department of Natural Resources and Environment to propose approving specific residential land prices for projects that need to be priced for residential land for approval in 2025, including the Me Tri - Do Duc Duc connecting road project.

Currently, this unit is coordinating with the District Department of Natural Resources and Environment to promptly advise the District People's Committee to issue a Decision approving specific land prices as a basis for developing a compensation, support and resettlement plan according to regulations.

Unfinished construction is also happening on the road connecting Pham Hung Street to Le Duc Tho Street. This is part of the project of the road connecting Ring Road 3 and Ring Road 3.5 with a total length of 6km.

The section from Pham Hung intersection to Le Duc Tho has a length of 1.12km approved since 2017, expected to open to traffic in 2021, but is still in disarray and cannot be put into operation. The project has a total investment of 300 billion VND.

s
Many households within the construction area of the road connecting Le Duc Tho - Pham Hung road have not been cleared. Photo: Huu Chanh

According to the People's Committee of Nam Tu Liem District, the site clearance work at Lane 252 My Dinh Street is still stuck because people and functional units have not agreed on the compensation price.

In addition, some new regulations in the 2024 Land Law have also caused the consensus on compensation unit prices to not achieve results.

Currently, the authorities of Nam Tu Liem district are focusing on removing obstacles to site clearance to soon complete the project.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi reclaims land from more than 300 households to build 2 roads 30-93.3m wide

|

Hanoi will reclaim land from 316 households and organize the construction of two important transport projects in Hoang Mai and Tay Ho districts.

Hanoi is about to build bridges and roads with an investment capital of more than 20,000 billion VND

|

The Hanoi People's Committee has just approved the Tu Lien bridge project across the Red River and the Ring Road 3 project through Dong Anh, with a total investment of more than 20,000 billion VND.

Roads in Nam Tu Liem are being implemented slowly, delaying the completion date to 2026

|

Hanoi - Due to land clearance problems, the project to build a nearly 1km long road, with a capital of more than 260 billion VND in Nam Tu Liem, had to postpone the completion date to 2026.

The Department of Food Safety proposes Hikid Milk advertising to violate regulations

|

The Department of Food Safety - Ministry of Health has just sent a written request to inspect and handle organizations and individuals that commit acts of advertising Hikid dairy products that violate regulations.

Leaders of the Central Committee of the Vietnam Fatherland Front congratulate the Easter in Hanoi

|

On the occasion of Easter 2025, on April 16, the leader of the Central Committee of the Vietnam Fatherland Front visited and congratulated the Easter at the Vietnam Protestant Church (the North), the Archdiocese of the Archdiocese of Hanoi and the Vietnam Catholic Solidarity Committee.

Police soldiers, army trained at Bien Hoa airport

|

Dong Nai - Under the intense heat at Bien Hoa Airport, the "steel roses" radiant in the final training session, ready for the Great Ceremony 30.4.

The communes and wards of central in Quang Ninh bring the names of district units

|

Quang Ninh - In order to preserve the old landmarks, most of the central communes and wards in Quang Ninh are proposed to name the districts, towns and cities today.

Find solutions to manage short -term accommodation models in the apartment

|

Ho Chi Minh City - Ho Chi Minh City Department of Construction is collecting suggestions for the short -term residence model in the apartment building.

Hanoi reclaims land from more than 300 households to build 2 roads 30-93.3m wide

HỮU CHÁNH |

Hanoi will reclaim land from 316 households and organize the construction of two important transport projects in Hoang Mai and Tay Ho districts.

Hanoi is about to build bridges and roads with an investment capital of more than 20,000 billion VND

HỮU CHÁNH |

The Hanoi People's Committee has just approved the Tu Lien bridge project across the Red River and the Ring Road 3 project through Dong Anh, with a total investment of more than 20,000 billion VND.

Roads in Nam Tu Liem are being implemented slowly, delaying the completion date to 2026

HỮU CHÁNH |

Hanoi - Due to land clearance problems, the project to build a nearly 1km long road, with a capital of more than 260 billion VND in Nam Tu Liem, had to postpone the completion date to 2026.