Tomorrow, Hanoi will forcibly confiscate land for a 6,000 billion road

HỮU CHÁNH |

Hanoi - Phu Xuyen District People's Committee will forcibly confiscate land from 15 households to implement the construction of the southern trunk road project, expected tomorrow (August 13).

Talking to Labor, Mr. Dang Quang Duy - Chairman of the People's Committee of Hong Minh commune (Phu Xuyen district, Hanoi) - said that the People's Committee of Phu Xuyen district and the local government have a plan to coerce land recovery for implementation. Investment project to build the southern trunk road of Hanoi passing through the commune.

The forced land recovery will be carried out on August 13, involving 15 plots of land belonging to 15 households in Phu Bat village (Hong Minh commune) with a total area of ​​1,930.4 m².

"This is the last location within the 8.9 km southern trunk road through Phu Xuyen district that has not been able to clear the land for many years" - Mr. Duy said.

a
The area will be reclaimed to implement the southern Hanoi trunk road project. Photo: Huu Chanh

According to the People's Committee of Phu Xuyen district, 15 plots of land believed to belong to families in Phu Bat village, Hong Minh commune are within the area that must be cleared for construction of the southern trunk road construction project, originating from the Commune People's Committee. arbitrarily sold and sold illegally since 2008.

This land allocation violates land law and was handled by the Hanoi People's Court according to judgment No. 922/2016/HS-PT dated September 7, 2016.

At the time of land allocation, Hong Minh Commune People's Committee did not invest in building technical infrastructure, and households had fully fulfilled their financial obligations with an amount of 23,400,000 VND/household.

According to the provisions of Article 75 of the Land Law and decrees of the Government, there are no regulations on compensation or land support when the State recovers land in case of unauthorized land allocation after July 1, 2004, therefore , there is no basis to support these households, leading to them not agreeing to coordinate in site clearance.

The two bridges spanning Van Dinh canal have not been able to be connected for many years due to land problems. Photo: Huu Chanh
The two bridges spanning Van Dinh canal have not been able to be connected for many years due to land problems. Photo: Huu Chanh

Regarding this issue, Phu Xuyen District People's Committee has reported to relevant departments and branches.

On February 28, 2024, the Hanoi Department of Natural Resources and Environment issued Document No. 1300/STNT-KTĐ, affirming that there are no regulations on compensation or support for land when the State recovers land in case of unauthorized allocation. after July 1, 2004.

On May 24, Phu Xuyen District People's Committee coordinated with Hong Minh commune authorities to organize a dialogue, but households still did not agree with the compensation plan.

On July 12 and July 22, the compensation and support payment sessions were still unsuccessful when households did not receive funds and did not hand over the premises.

At the meeting on July 25, the internal affairs agency and the professional department of Phu Xuyen District People's Committee confirmed that the steps to clear the construction site for the project to build the southern trunk road through Hong Minh commune involving 15 households have been completed. comply with regulations.

Southern trunk road project passing through Hong Minh commune, Phu Xuyen. Photo: Huu Chanh
Southern trunk road project passing through Hong Minh commune, Phu Xuyen. Photo: Huu Chanh

The Phu Xuyen district government hopes the people will cooperate in handing over the site, because currently the project has basically completed the site clearance work, only the connection to Provincial Road 428, located in Hong Minh commune, remains a problem. .

In case people still do not comply, Phu Xuyen District People's Committee will forcibly reclaim the land to hand over the site to the investor to complete the project in accordance with the law.

The investment project to build the southern trunk road of Hanoi (formerly named the investment project to build the southern trunk road of Ha Tay province) has a length of more than 41 km through Ha Dong, Thanh Oai, Ung Hoa and Phu districts. Xuyen.

The project has a total investment of 6,076 billion VND, implemented in the form of BT (build-transfer contract), starting construction in 2008.

After 16 years of implementation, the project has completed 21km, passing through Ha Dong district, Thanh Oai district and Ung Hoa district.

The rest goes through the communes: Hoang Long, Tri Trung, Phu Tuc, Chau Can of Phu Xuyen district, which is still under construction. Particularly, the section passing through Hong Minh commune has been "stagnant" for many years because of land clearance problems.

HỮU CHÁNH
TIN LIÊN QUAN

Đường nổi tiếng ùn tắc ở Hà Nội sắp mở rộng lên 4 làn xe

HỮU CHÁNH |

Hà Nội - Đường Nguyễn Tuân là điểm nghẽn ùn tắc ở quận Thanh Xuân suốt nhiều năm qua, sắp được mở rộng lên 21m với 4 làn xe.

Hà Nội ấn định ngày thông xe 2 dự án giao thông quan trọng

HỮU CHÁNH |

Hà Nội - Dự án đường Lê Quang Đạo kéo dài và đường nối Ngọc Thụy - Nguyễn Văn Cừ, tổng vốn đầu tư gần 2.000 tỉ đồng dự kiến thông xe tháng 10.2024.

Đường nổi tiếng làm lâu ở Hà Nội sẽ xong vào cuối tháng 7

Hữu Chánh |

Hà Nội - Dự án mở rộng đường Âu Cơ - Nghi Tàm dài 3,7 km dự kiến sẽ thông xe toàn tuyến vào cuối tháng 7.2024 sau thời gian dài chậm trễ.

Cầu thủ SLNA bị nghi gian lận tuổi: Bất thường quá trình học

QUANG ĐẠI |

Cầu thủ B.V.B, đội U11 Sông Lam Nghệ An, có nhiều điểm bất thường trong quá trình học tập liên quan đến nghi án gian lận tuổi.

Thủy điện Tuyên Quang đóng toàn bộ 8 cửa xả đáy

Việt Bắc |

Đến sáng 17.9, Thủy điện Tuyên Quang đã đóng cửa xả đáy cuối cùng sau khi phải mở toàn bộ 8 cửa xả trước mưa lũ lịch sử.

Áp thấp mạnh lên thành bão, mưa lớn ở Bắc Bộ, Trung Bộ

Khương Duy |

Cục Quản lý đê điều và Phòng, chống thiên tai vừa phát đi tin áp thấp nhiệt đới gần Biển Đông và cảnh báo mưa lớn ở nhiều nơi.

Mệt mỏi vì bơm xong lại ngập trong biệt thự chục tỉ ở Hà Nội

Đền Phú - Vân Trường |

Hà Nội - Sau khi được bơm nước, dọn dẹp sau bão số 3, nhiều biệt thự tại KĐT Nam An Khánh lại ngập sau cơn mưa lớn.

Đại diện quán cơm bị tẩy chay ở Hạ Long xin lỗi khách hàng

Nguyễn Hùng |

Quảng Ninh - Thông tin từ UBND TP Hạ Long sáng 17.9, tại buổi làm việc giữa các bên hôm qua, đại diện quán Cơm sạch bà Liên đã lên tiếng xin lỗi khách hàng.

Famous congested road in Hanoi to be expanded to 4 lanes.

HỮU CHÁNH |

Hanoi - Nguyen Tuân Street is a bottleneck congestion point in Thanh Xuan district for many years, soon to be expanded to 21m with 4 lanes.

Hanoi has scheduled the opening day for 2 important transportation projects

HỮU CHÁNH |

Hanoi - The Lê Quang Đạo road project is being extended and the road connecting Ngọc Thụy - Nguyễn Văn Cừ, with a total investment of nearly 2,000 billion VND, is expected to be completed and open to traffic in October 2024.

The famous road that took a long time to build in Hanoi will be completed by the end of July

Hữu Chánh |

Hanoi - The 3.7 km long Au Co - Nghi Tam road expansion project is expected to open the entire route by the end of July 2024 after a long delay.