Determination to complete site clearance for 3 expressway projects in Lam Dong in August

Phúc Khánh |

Lam Dong - Provincial leaders request departments, branches, and localities to complete site clearance for 3 expressway projects in August and accelerate construction.

On August 5, the Construction Investment Project Management Board No. 1 of Lam Dong province said that it had reported to the Chairman of the Provincial People's Committee on the progress of 3 key expressway projects including: Tan Phu - Bao Loc, Bao Loc - Lien Khuong and Gia Nghia - Chon Thanh.

Sau khi được bàn giao mặt bằng, nhà thầu đang tiến hành thi công cao tốc Tân Phú - Bảo Lộc, đoạn qua xã Đạ Huoai. Ảnh: Phúc Khánh
After being handed over the site, the contractor is constructing the Tan Phu - Bao Loc expressway, the section passing through Da Huoai commune. Photo: Phuc Khanh

According to the report, the Tan Phu - Bao Loc expressway project is about 66km long, with a total investment of more than 18,000 billion VND, expected to be completed in the fourth quarter of 2027.

By the end of July 2026, localities had approved compensation plans for 856 households, reaching 90%; paid more than 534 billion VND.

The land handover area reached about 120ha, equivalent to 30% of the area to be recovered. The investor has deployed 7 construction teams with 68 equipment and 110 personnel.

Hiện, cao tốc Bảo Lộc - Liên Khương đã bàn giao khoảng 471ha mặt bằng, đạt gần 76% diện tích toàn dự án. Ảnh: Phúc Khánh
Currently, the Bao Loc - Lien Khuong expressway has handed over about 471ha of land, reaching nearly 76% of the total project area. Photo: Phuc Khanh

For the Bao Loc - Lien Khuong expressway project, more than 73km long, with a total investment of about 17,718 billion VND, localities have approved compensation plans for 97% of affected households, paid more than 2,402 billion VND and handed over about 471ha of land, reaching nearly 76% of the total project area.

Currently, the investor has arranged 13 construction teams with 149 personnel and 75 equipment, deploying many overpass items, intersections and roadbeds.

Ông Hồ Văn Mười - Ủy viên Ban Chấp hành Trung ương Đảng, Chủ tịch UBND tỉnh Lâm Đồng yêu cầu phải hoàn tất giải phóng mặt bằng 3 dự án cao tốc trọng điểm trong tháng 8. Ảnh: Hoàng Sa
At an online meeting on August 3, Mr. Ho Van Muoi - Member of the Party Central Committee, Chairman of Lam Dong Provincial People's Committee requested to complete site clearance for 3 key expressway projects in August. Photo: Hoang Sa

Regarding the Gia Nghia - Chon Thanh expressway project, Construction Investment Project Management Board No. 3 said that component project 2 is still slow due to design adjustments and obstacles in bauxite planning.

Component project 4 has handed over more than 108ha of land, reaching about 32% of the route length and disbursing about 65% of the 2026 capital plan.

Các nhà thầu đang tập trung đẩy nhanh tiến độ các dự án cao tốc trên địa bàn tỉnh Lâm Đồng. Ảnh: Phúc Khánh
Contractors are focusing on accelerating the progress of expressway projects in Lam Dong province. Photo: Phuc Khanh

Due to the application of the new compensation unit price, the total investment of component project 4 is expected to increase by about 180 billion VND.

Construction Investment Project Management Board No. 3 proposed to transfer about 90 billion VND of capital from component project 2 to serve compensation and resettlement support.

At an online meeting on August 3, Mr. Ho Van Muoi - Member of the Party Central Committee - Chairman of Lam Dong Provincial People's Committee requested departments, branches, and localities to focus on completing site clearance work in August, and at the same time accelerate the construction progress and disbursement of investment capital.

According to the Chairman of Lam Dong Provincial People's Committee, the progress of disbursement and site clearance is still not meeting requirements. Localities must review each location and dialogue with people to completely remove obstacles.

Theo chỉ đạo, giải phóng mặt bằng các dự án cao tốc đến đâu phải thi công đến đó. Ảnh: Phúc Khánh
According to the direction, site clearance for expressway projects must be carried out as soon as possible. Photo: Phuc Khanh

Mr. Ho Van Muoi emphasized that agencies and units need to focus maximum manpower, "working day and night" to complete site clearance in August.

Project management boards and contractors must immediately deploy construction at locations with clean ground, accelerate disbursement, and strive to complete projects on schedule in the fourth quarter of 2027.

Phúc Khánh
RELATED NEWS

Lam Dong urgently builds resettlement area to serve expressway project

|

Along with accelerating site clearance for the two Tan Phu - Bao Loc and Bao Loc - Lien Khuong expressways, Lam Dong province is accelerating the construction of resettlement areas, ensuring people have new housing before handing over land.

Lam Dong proposes to transfer 1,143 billion VND of capital from Bao Loc - Lien Khuong expressway due to low disbursement

|

Lam Dong - Provincial People's Committee proposes to transfer more than 1,143 billion VND of capital from the Bao Loc - Lien Khuong expressway project to 135 newly started projects due to low disbursement capacity.

Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

|

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.

5 candidates whose exam results in Quang Tri were canceled are allowed to re-register for the 2027 exam

|

Quang Tri - 5 candidates whose exam results were canceled due to negativity at the Le Truc High School exam site were registered to retake the exam in 2027.

School transcripts record unusual place names, Quang Tri Department of Education and Training requests police to verify

|

Quang Tri - The Provincial Department of Education and Training is coordinating with the police to verify the secondary school transcript of Vo Danh Thuan, Chairman of the Vietnam Fatherland Front Committee of Sen Ngu commune.

Sophisticated activities of Luong Son TV gambling ring

|

Quang Tri - Luong Son TV gambling ring operates sophisticatedly, disguised as illegal football broadcasting to attract viewers to participate in online betting.

Lam Dong urgently builds resettlement area to serve expressway project

Phúc Khánh |

Along with accelerating site clearance for the two Tan Phu - Bao Loc and Bao Loc - Lien Khuong expressways, Lam Dong province is accelerating the construction of resettlement areas, ensuring people have new housing before handing over land.

Lam Dong proposes to transfer 1,143 billion VND of capital from Bao Loc - Lien Khuong expressway due to low disbursement

Phúc Khánh |

Lam Dong - Provincial People's Committee proposes to transfer more than 1,143 billion VND of capital from the Bao Loc - Lien Khuong expressway project to 135 newly started projects due to low disbursement capacity.

Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

Phúc Khánh |

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.