Lam Dong proposes to transfer 1,143 billion VND of capital from Bao Loc - Lien Khuong expressway due to low disbursement

Phúc Khánh |

Lam Dong - Provincial People's Committee proposes to transfer more than 1,143 billion VND of capital from the Bao Loc - Lien Khuong expressway project to 135 newly started projects due to low disbursement capacity.

At the 4th session of the 11th Lam Dong Provincial People's Council (term 2026 - 2031) taking place from June 30 to July 1, the Provincial People's Committee submitted to the People's Council for consideration the adjustment to reduce VND 1,143 billion of the 2026 capital plan of the Bao Loc - Lien Khuong expressway construction investment project (phase 1) according to the PPP method.

The capital source of the Bao Loc - Lien Khuong expressway project proposed for transfer belongs to the Lam Dong lottery source.

Tại kỳ họp thứ 4, HĐND tỉnh Lâm Đồng khóa XI, UBND tỉnh đề xuất điều chuyển hơn 1.143 tỉ đồng vốn của dự án cao tốc Bảo Lộc - Liên Khương sang 135 dự án khởi công mới. Ảnh: Phúc Khánh
At the 4th session of the 11th Lam Dong Provincial People's Council, the Provincial People's Committee proposed to transfer more than 1,143 billion VND of capital from the Bao Loc - Lien Khuong expressway project to 135 newly started projects. Photo: Phuc Khanh

According to the Provincial People's Committee, through reviewing the implementation situation and disbursement capacity, the project has lower capital demand than planned due to slow progress, incomplete compensation and site clearance work, and many items not meeting construction conditions.

The adjusted capital will be supplemented for 135 newly started projects to accelerate the implementation progress, improve capital efficiency and promote public investment disbursement in 2026.

According to the report of the Provincial People's Committee, the total public investment capital plan for 2026, including the capital source for 2025 allowed to be extended to 2026, is more than 20,115 billion VND.

However, by the end of June, the locality had disbursed more than 3,036 billion VND, reaching 15.09% of the plan.

Dự án cao tốc Bảo Lộc - Liên Khương đang được các đơn vị đẩy nhanh tiến độ khi có mặt bằng. Ảnh: Phúc Khánh
The Bao Loc - Lien Khuong expressway project is being accelerated by units when land is available. Photo: Phuc Khanh

The Provincial People's Committee assessed that the disbursement progress is still low compared to the requirements, while Lam Dong set a GRDP growth target of 10% in 2026.

The main reason is that compensation, site clearance and resettlement arrangement at many projects are still slow; some key traffic projects encounter obstacles in the implementation process.

In addition, fluctuating prices of building materials and fuels also increase investment costs, affecting the progress of construction contracts.

These difficulties make it difficult for many projects to disburse all the capital allocated in the year, including the Bao Loc - Lien Khuong expressway project.

Phúc Khánh
RELATED NEWS

Lam Dong Provincial People's Council approves 24 important resolutions on local development resources

|

Lam Dong - The Provincial People's Council passed 24 important resolutions, focusing on perfecting mechanisms and policies, improving management efficiency and developing local resources.

Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

|

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.

Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

|

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.

Progress of deploying a series of bridges over the Red River and Duong River

|

Hanoi - bridge projects over the Red River and Duong River are being implemented simultaneously, striving to be completed before the APEC 2027 Summit.

Vietnam U18 women's volleyball team has a favorable start at the 2026 AFC U18 Championship

|

The Vietnam U18 women's volleyball team had an impressive debut at the 2026 Asian Championship when they defeated U18 Taiwan (China) with a score of 3-0.

A year of rearranging the country - Compact, close to the people, effective

|

At 8:10 PM on July 1, 2026, Lao Dong Newspaper respectfully introduces to readers the documentary "One year of rearranging the country - Compact, close to the people, effective" produced by Vietnam Television. The work has a duration of 30 minutes, focusing on reflecting the largest overhaul of the administrative apparatus in the 40-year history of Doi Moi, in order to prepare for the new era of development of the country.

National A01 combination valedictorian chooses self-study, understands the essence to achieve high scores

|

Hung Yen - A male student from An Thi High School became the national valedictorian of the A01 combination with 29.75 points thanks to a learning method that emphasizes understanding the essence and self-study spirit.

Stocks increase in the first trading session of Q3/2026

|

Cash flow pouring into large-cap groups helped the stock market maintain its green color.

Lam Dong Provincial People's Council approves 24 important resolutions on local development resources

Phúc Khánh |

Lam Dong - The Provincial People's Council passed 24 important resolutions, focusing on perfecting mechanisms and policies, improving management efficiency and developing local resources.

Bao Loc - Lien Khuong expressway is slow to construct due to incomplete design documents

Phúc Khánh |

Lam Dong - Although more than 67% of the site has been handed over, the Bao Loc - Lien Khuong expressway project cannot be implemented due to incomplete technical design documents.

Lam Dong removes land bottlenecks on Bao Loc - Lien Khuong expressway

Phúc Khánh |

Lam Dong - After more than 5 months of construction, the Bao Loc - Lien Khuong expressway is facing site clearance problems, it is necessary to focus on removing them to ensure progress.