Roundabouts in Gia Lai will be adjusted to ensure traffic

Xuyên Đông |

A roundabout on National Highway 19 in An Phu Commune, Pleiku City, Gia Lai Province, designed to be 15m wide, will be reduced to 10m to ensure traffic safety.

Recently, Gia Lai voters proposed to design a drainage culvert on National Highway 19 through Pleiku city and Dak Po district, through village 1, An Phu commune, Chu A commune, Pleiku city and the section from Km83+700 to Km83+900, Ta Ly bridge area, Dak Po district.

In addition, voters proposed to reduce the size of the traffic island (roundabout) between National Highway 19 and Pleiku bypass in An Phu commune.

According to voters, the current size of traffic islands is very large, affecting the circulation of vehicles.

Responding to this issue, on September 23, the Ministry of Transport said that according to the approved technical design documents, at the intersection between National Highway 19 and the Pleiku city bypass, a roundabout with a radius of 15m is arranged, combined with a system of signs and paint lines, and the contractor has completed the construction.

However, based on the opinions of the WB (donor), the Traffic Safety Assessment Consultant and relevant agencies, Project Management Board 2 adjusted the design to reduce the size of the traffic island from a radius of 15m to 10m and adjusted the system of marking lines to suit the actual operating conditions of the area.

Currently, the contractor is carrying out roadbed excavation to reduce the size of the roundabout according to the adjusted design documents and is expected to be completed in October 2024.

Regarding the petition of voters in Gia Lai province about the project on National Highway 19, the Ministry of Transport said that the above contents are related to Packages XL03 and XL04B under the Project to Enhance Traffic Connectivity in the Central Highlands, with WB loans to upgrade and expand National Highway 19.

The project has so far basically completed 7/8 packages, the remaining package under construction is Package XL01 in Binh Dinh province, which is being urgently directed by the Ministry of Transport to Project Management Board 2 (Investor) and related units to speed up the progress, and soon put the project into operation and use to serve the travel needs of the people.

Regarding the proposal to design drainage culverts on National Highway 19, the Ministry of Transport said: For the section Km83+700 - Km83+900 (Ta Ly bridge area), Dak Po district: According to the report of Project Management Board 21, during the construction process, the telecommunications unit deployed the construction of an optical cable system along National Highway 19 (this work is not within the scope of the National Highway 19 Upgrade and Expansion Project), digging a residential crossroad broke the drainage systems of the people connected to the old longitudinal ditch system along National Highway 19; at the same time, causing soil and rocks to fall into the old longitudinal ditch system and not yet cleared, leading to affecting the drainage of the area.

After reviewing the actual situation on the ground and working with the local authorities, Dak Po District People's Committee and the People's Committees of related communes, Project Management Board 2 has directed the contractor of the National Highway 19 Upgrade and Expansion Project to clear and dispose of materials and install additional broken drainage pipes, and clear the drainage lines of the old drainage system of the road and area.

Currently, the contractor has completed the construction and ensured drainage for households around this area.

Regarding the section through village 1, Chu A commune, Pleiku city: According to the approved design documents, a drainage system has been designed at this location and the contractor is currently implementing the construction, expected to be completed in October 2024.

However, at the location of the A1 bridgehead of An My bridge (left of the route), there is still 01 household that has not agreed with the compensation and support plan, so it is not possible to organize the relocation of the power line and it affects the construction of the drainage system at this location.

Therefore, we request that voters of Gia Lai province pay attention to giving opinions to local authorities to strengthen propaganda and mobilization work to households to promptly hand over the site for the contractor to implement and ensure the completion schedule of the project.

Xuyên Đông
RELATED NEWS

Hanoi Party Secretary sets deadline for completion of "most expensive road on the planet

|

Hanoi - Regarding the progress of the Ring Road 1 project (Hoang Cau - Voi Phuc section), the Hanoi Party Secretary requested to complete the entire roadbed before September 2, 2026; complete the construction of 2 overpasses on the route before December 31, 2026.

Live volleyball VTV Binh Dien Long An vs Binh Chung Thong Tin

|

Live volleyball match between VTV Binh Dien Long An and Binh Chung Thong Tin, taking place at 5:30 PM today (April 18).

Complete the installation of medical equipment at facility 2 of Bach Mai and Viet Duc Hospitals before June 30

|

Ninh Binh - The investor of Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 project committed to complete the installation of equipment before June 30.

Salary reform from the Central to local levels, implemented in all 3 blocs

|

The Ministry of Home Affairs is assigned to carefully prepare the reform of salaries, allowances and other regimes from the Central to local levels, implemented in all 3 blocs.

Forecast of the risk of receiving strong storms and super typhoons in 2026

|

According to a representative of the meteorological agency, ENSO phase transition along with the impact of climate change leads to the risk of strong storms and super typhoons in 2026.

Circus of nearly 1,400 billion VND, the most modern in Ho Chi Minh City opens for visitors

|

Ho Chi Minh City - For the first time, people can visit and experience the modern architectural space of Phu Tho Multi-purpose Circus and Performance.

Designer Duc Hung: For me, ao dai is perfectly beautiful, it needs to be promoted all over the world

|

In the program "Saturday Afternoon Coffee", designer Duc Hung shared his perspective on Vietnamese fashion in the context of cultural industry development.

Clean water brings many positive changes to rural people

|

Hanoi - After a few years of using clean water, the worries and hardships in daily life of people in Phong Trieu village, Phu Xuyen commune have been improved.

Gia Lai có 3 cơ sở phát thải khí nhà kính

THANH TUẤN |

Gia Lai - Việc kiểm kê các cơ sở phát thải khí nhà kính nhằm bảo đảm an toàn môi trường, tránh để xảy ra nguy cơ gây ô nhiễm.

Chi sai nhiều tỉ đồng, lãnh đạo Sở Nội vụ Gia Lai bị kỷ luật

THANH TUẤN |

Ban Tôn giáo tỉnh Gia Lai chi sai tiền ngân sách Nhà nước nhiều tỉ đồng, vi phạm nghiêm trọng đến mức phải xử lý kỷ luật.

Gia Lai quyết tâm giữ rừng để có nguồn thu từ tín chỉ carbon

THANH TUẤN |

Tại buổi làm việc với tỉnh Gia Lai mới đây, Bộ trưởng Bộ Nông nghiệp và Phát triển nông thôn Lê Minh Hoan khẳng định, Gia Lai có diện tích rừng tự nhiên lớn, bảo vệ được màu xanh của rừng sẽ thu được lợi nhuận từ bán tín chỉ carbon.