Construction throughout the New Year holiday on the National Highway 28B upgrade project

Duy Tuấn |

Lam Dong - Currently, there are many construction teams with workers and machinery operating continuously, throughout the New Year holiday on National Highway 28B construction site.

The project to renovate and upgrade National Highway 28B through Lam Dong province is about 68km long, is one of the key traffic projects of the region, invested by the Vietnam Road Administration.

Project Management Board 5 is directly assigned to manage and operate construction, the entire route is divided into 2 construction packages.

May moc thi cong xuyen Tet Duong lich tren cong truong du an nang cap Quoc lo 28B. Anh: Duy Tuan
Construction machinery during the New Year holiday on the construction site of the National Highway 28B upgrade project. Photo: Duy Tuan

Recorded during the New Year holiday, many sections on the route still maintain continuous construction. Excavators, excavators, and trucks transporting materials operate smoothly.

Workers also take advantage of the time when traffic volume is low to construct roadbeds and grade crushed stone.

On January 2, Mr. Le Van Chung - Deputy Director of Project Management Board 5 - said that the organization of construction throughout the New Year to compensate for progress was affected in October and November due to heavy rain and extreme weather.

We encourage contractors and workers to take advantage of the holiday to construct, ensuring the overall progress of the project," Mr. Chung said.

Cac cong nhan dang tri cong cau can tren deo Dai Ninh. Anh: Duy Tuan
Workers are constructing an overpass on Dai Ninh Pass. Photo: Duy Tuan

To date, the total construction volume has reached about 70% of the contract value. The project implementation process once faced many difficulties due to harsh weather and obstacles in site clearance.

Currently, the entire route only has about 2km of land that has not been handed over, mainly in densely populated areas. At the same time, some technical infrastructure such as water pipelines about 2.5km long and 13 medium-voltage power poles are being coordinated by the locality to relocate.

Cong nhan thi cong tren cong truong. Anh: Duy Tuan
Workers constructing on the construction site. Photo: Duy Tuan

In the area near Dai Ninh Hydropower Plant, construction teams are focusing on handling the roadbed. Because only one side of the road surface is being constructed, two-way vehicles must circulate in the same lane and have workers regulating to ensure safety.

During the holidays, the traffic volume of tourist vehicles from Phan Thiet to Da Lat increased. Therefore, construction was adjusted flexibly, limiting congestion.

Mot vi tri thi cong gan UBND xa Phan Son. Anh: Duy Tuan
A construction site near Phan Son Commune People's Committee. Photo: Duy Tuan

According to the plan, the entire project will be completed in March 2026. Package No. 2 (Km42–Km69) has a faster progress, expected to be basically completed in early January 2026.

Package No. 1 (Km0–Km42) started construction later, so the goal is to complete it in March 2026.

Cong nhan va xe lu thi cong nen duong. Anh: Duy Tuan
Workers and rollers constructing the roadbed. Photo: Duy Tuan

For sections that already have favorable ground, the contractor sets a goal to complete asphalt concrete paving before the Lunar New Year.

Thereby, creating favorable conditions for people and tourists to travel during peak times.

Mot doan tuyen dang tham nhua mat duong. Anh: Duy Tuan
A section of the route is being asphalted. Photo: Duy Tuan

National Highway 28B is the shortest connecting route between Phan Thiet and the administrative center of Lam Dong province, with a large traffic volume, especially tourist and transport vehicles.

In the context that Lien Khuong Airport is about to be temporarily suspended for upgrade, the role of this route becomes even more important.

Maintaining construction throughout Tet shows the determination of the investor and contractors to soon complete the project. Thereby, contributing to ensuring smooth traffic and promoting socio-economic development of the region.

Duy Tuấn
RELATED NEWS

Construction throughout Tet on roads connecting Long Thanh airport

|

Dong Nai - Ho Chi Minh City Ring Road 3, Bien Hoa - Vung Tau expressway, provincial road 25B are under construction throughout the 2026 New Year to connect Long Thanh airport in time.

200 workers construct the Chau Doc - Can Tho - Soc Trang expressway during the New Year holiday

|

An Giang - 200 officials, engineers, and workers constructing the Chau Doc - Can Tho - Soc Trang expressway, determined to stick to the construction site throughout the New Year.

National Highway 28B upgrade project worth over VND1,400 billion is 3 months behind schedule

|

Lam Dong - The National Highway 28B renovation and upgrade project has just had its completion schedule adjusted to 2026 instead of the original 2025 target.

New Year's Eve fire in a bar, more than 100 casualties in Switzerland

|

A fire broke out in the middle of New Year's Eve at a crowded bar in Switzerland, killing at least 40 people and injuring more than 100 others.

Defender Tran Thi Duyen: I used to think I couldn't return to the top

|

Defender Tran Thi Duyen, who suffered a serious injury, has made efforts to return and shine in the Vietnamese women's team, making her mark with a fierce and strong playing style.

Man City held to a goalless draw by Sunderland

|

In the early morning of January 2nd (Vietnam time), Man City had a lackluster goalless draw against Sunderland in the Premier League.

Weather today January 2nd: Strong cold air causes cooling down

|

Weather today, January 2nd, the North turns cold, mountainous areas are very cold, with dangerous cold in some places. Central and South Central regions have rain, showers, locally moderate rain, heavy rain and thunderstorms.

Ukrainian army suffers heavy casualties in 2025

|

According to estimates by TASS news agency based on data from the Russian Ministry of Defense, more than 510,000 Ukrainian soldiers were killed and injured in 2025.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Construction throughout Tet on roads connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Ho Chi Minh City Ring Road 3, Bien Hoa - Vung Tau expressway, provincial road 25B are under construction throughout the 2026 New Year to connect Long Thanh airport in time.

200 workers construct the Chau Doc - Can Tho - Soc Trang expressway during the New Year holiday

Thành Nhân |

An Giang - 200 officials, engineers, and workers constructing the Chau Doc - Can Tho - Soc Trang expressway, determined to stick to the construction site throughout the New Year.

National Highway 28B upgrade project worth over VND1,400 billion is 3 months behind schedule

Duy Tuấn |

Lam Dong - The National Highway 28B renovation and upgrade project has just had its completion schedule adjusted to 2026 instead of the original 2025 target.