National Highway 28B upgrade project worth over VND1,400 billion is 3 months behind schedule

Duy Tuấn |

Lam Dong - The National Highway 28B renovation and upgrade project has just had its completion schedule adjusted to 2026 instead of the original 2025 target.

The project to renovate and upgrade National Highway 28B through Lam Dong province has a total length of about 68km. The total investment of the project is 1,435 billion VND.

On October 25, news from the Ministry of Construction said that the Ministry had sent a document to the Vietnam Road Administration approving the adjustment of the construction progress of the National Highway 28B renovation and upgrade project through Lam Dong province.

Accordingly, the project's construction progress was adjusted to complete the project in March 2026 and complete the procedures to complete the project in 2026.

Mot vi tri thi cong tren Quoc lo 28B. Anh: Duy Tuan
A construction site on National Highway 28B. Photo: Duy Tuan

The Ministry of Construction requires investors to review capital plans, strictly manage costs, ensure that they do not exceed the total investment and "not generate funds when extending the implementation period".

At the same time, clearly identify objective and subjective causes, strictly handle contractors who are behind schedule (if any).

The investor closely coordinates with the locality to soon complete the site clearance work and disburse the site clearance capital in accordance with regulations.

The project to renovate and upgrade National Highway 28B aims to be completed before December 31, 2025. However, due to some problems in site clearance, the construction progress has not met the plan.

On October 22, Mr. Ho Van Muoi - Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Lam Dong province - led a working group to inspect the progress of site clearance and construction of this project.

At the inspection, Mr. Ho Van Muoi emphasized that the project implementation was too slow. If the coming time is still slow and does not meet the set schedule, he will sign a document requesting to replace the investor.

Vi tri thi cong cau can giua deo Dai Ninh. Anh: Duy Tuan
Construction location of the overpass in the middle of Dai Ninh Pass. Photo: Duy Tuan

The Department of Construction said that up to now, the project's site clearance work has not yet been handed over for construction.

Mainly concentrated in Luong Son commune with 90 households. Regarding the construction progress, 44/62km of crushed stone and 37/62km of asphalt concrete have been provided.

National Highway 28B is the shortest route connecting Phan Thiet to the provincial administrative center, with a large volume of traffic.

Accelerating the progress is even more urgent as Lien Khuong Airport is preparing to temporarily suspend operations for upgrading, making this route an important traffic axis for travel and transportation.

Duy Tuấn
RELATED NEWS

Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

|

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.

National Highway 28B upgrade project is sluggish due to slow handover of land

|

Lam Dong - The construction progress of the National Highway 28B upgrade project is still sluggish due to slow site handover and contractors not focusing on construction equipment and materials.

National Highway 28B project is in disarray, construction is sluggish, lacking labor

|

Lam Dong - On National Highway 28B, many construction sites are shabby, with only signs and markers but no workers or machinery.

Affirming the pioneering role of workers and civil servants in the cause of national renewal

|

On the morning of October 26, President of the Vietnam General Confederation of Labor Nguyen Dinh Khang emphasized that honoring and praising advanced examples and new factors strongly encourages the team of workers, civil servants and laborers to constantly rise up, affirming their pioneering role in the cause of national renewal.

Israel announces new attack in Gaza

|

The Israeli military said it had launched a targeted attack in the central Gaza Strip.

Hanoi the most beautiful autumn days

|

Hanoi - The wind blows the scent of new green rice, mixed with golden sunlight scattered all over the streets, bringing a pleasant feeling in the fall days.

Khanh Hoa Provincial Chairman brave the rain to cheer on the finalists of the Road to Olympia

|

Khanh Hoa - At the beginning of Khanh Hoa Bridge, it rained heavily, but thousands of spectators still wore the rain to cheer for Doan Thanh Tung to conquer the Road to Olympia.

beat Brighton at home, Man United in the top 4 of the Premier League

|

On the night of October 25 (Vietnam time), Man United extended their winning streak in the Premier League to 3 when defeating Brighton at Old Trafford.

Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

Duy Tuấn |

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.

National Highway 28B upgrade project is sluggish due to slow handover of land

Duy Tuấn |

Lam Dong - The construction progress of the National Highway 28B upgrade project is still sluggish due to slow site handover and contractors not focusing on construction equipment and materials.

National Highway 28B project is in disarray, construction is sluggish, lacking labor

Duy Tuấn |

Lam Dong - On National Highway 28B, many construction sites are shabby, with only signs and markers but no workers or machinery.