Construction and site clearance at the VND1,800 billion project in Dak Lak

BẢO TRUNG |

Dak Lak - The investor of the Ho Chi Minh road project (the eastern bypass section of Buon Ma Thuot) is taking advantage of both construction and mobilization of people to hand over the site.

On August 9, Mr. Dang Tho Dan - Head of the Traffic Project Management Department (Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board) - said that the unit is continuing to coordinate with the People's Committee of Cuor Dang Commune and the Provincial Land Fund Development Center.

The goal is to complete the mobilization of people to hand over the site to construct the Ho Chi Minh road project, the section avoiding the East of Buon Ma Thuot.

Cong tac giai phong mat bang ve co ban da hoan tat. Anh: Bao Trung
Site clearance is being implemented in Dak Lak province. Photo: Bao Trung

According to Mr. Dan, there are still some households in the project area that have not handed over the site. For the households that have handed over, the investor and the construction unit have supported human resources to dismantle and clean up for handover.

The project is implemented in the form of rolling: both construction and mobilization of people, to ensure completion and putting into use in 2025.

The authorities have stepped up propaganda so that people clearly understand the meaning and importance of the project. Households subject to relocation will be compensated and supported in accordance with regulations.

"We hope that people will accompany and share the difficulties of the investor so that the project can be completed on schedule. If it is not completed in 2025, the project will face many risks, Mr. Dan emphasized.

Nha thau thi cong lap bien canh bao, tiep tuc trien khai hang muc xay lap de som hoan hien du an. Anh: Bao Trung
The contractor has installed warning signs and continued to deploy construction items to complete the project soon. Photo: Bao Trung

Recorded at the scene, most households had demolished their houses in areas subject to site clearance. The contractor is focusing on vehicles and materials to speed up the construction progress, completing the project that has been delayed for many years.

As reported by Lao Dong Newspaper, the Ho Chi Minh Road Project, the section avoiding the East of Buon Ma Thuot (Dak Lak province) has a total investment of more than VND1,800 billion from the central budget with a length of more than 39km.

The project is invested by the Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board.

However, for more than a year, the project still has 1km (from Km0+000 to Km1+000) that has not been constructed due to land clearance.

This has led to existing roads being damaged with mud, potholes, buffalo holes... greatly affecting the travel and living needs of the people.

BẢO TRUNG
RELATED NEWS

Many households have not agreed to the draft compensation for a project worth over VND1,800 billion in Dak Lak

|

Dak Lak - Many households have not agreed with the draft compensation at the Ho Chi Minh Road Project, the eastern bypass section through Buon Ma Thuot city worth more than VND1,800 billion.

Reasons for not yet completing site clearance for a project worth over VND1,800 billion in Dak Lak

|

Dak Lak - The authorities have not been able to complete the clearance of 113m of the urban bypass project worth more than VND1,800 billion because many households have not agreed to the compensation plan.

Project worth over VND1,800 billion in Dak Lak risks losing central government capital due to slow site clearance

|

Dak Lak - If there are still problems with the site, the Ministry of Construction will zoning the project for more than VND1,800 billion and hand over the unfinished part to the locality for self-management and capital completion.

Thai government requests to return home people in border areas

|

Thai authorities have deployed emergency measures to support people to return to their homes and overcome the consequences of the conflict.

Body of young man found after many days missing on Hoang Nguu Son mountain

|

Khanh Hoa - After 6 days of searching until noon on August 10, the search force for the missing young man on Hoang Nguu Son mountain found the victim's body.

Girl lost contact after getting on a motorbike taxi has returned home safely

|

HCMC - After more than three days of being out of contact, Ms. Nguyen Phuong Mai has been found. The family and Nha Nam Company confirmed that she had returned home safely.

Kẻ gian cắt trộm cáp ngầm dự án đường giao thông hơn 1.800 tỉ đồng ở Đắk Lắk

BẢO TRUNG |

Đắk Lắk - Kẻ gian liên tục cắt trộm cáp ngầm, thiết bị tại dự án đường Hồ Chí Minh đoạn tránh phía Đông Buôn Ma Thuột, gây thiệt hại cho nhà thầu.

Many households have not agreed to the draft compensation for a project worth over VND1,800 billion in Dak Lak

THANH QUỲNH |

Dak Lak - Many households have not agreed with the draft compensation at the Ho Chi Minh Road Project, the eastern bypass section through Buon Ma Thuot city worth more than VND1,800 billion.

Reasons for not yet completing site clearance for a project worth over VND1,800 billion in Dak Lak

THANH QUỲNH |

Dak Lak - The authorities have not been able to complete the clearance of 113m of the urban bypass project worth more than VND1,800 billion because many households have not agreed to the compensation plan.

Project worth over VND1,800 billion in Dak Lak risks losing central government capital due to slow site clearance

THANH QUỲNH |

Dak Lak - If there are still problems with the site, the Ministry of Construction will zoning the project for more than VND1,800 billion and hand over the unfinished part to the locality for self-management and capital completion.