Chairman of Lam Dong province warns investors and department leaders if National Highway 28B is still behind schedule

Duy Tuấn |

Lam Dong - The Chairman of the Provincial People's Committee warned that he would change the department's leaders and propose to change the investor and contractor if the National Highway 28B project continued to be behind schedule.

The project to renovate and upgrade National Highway 28B through Lam Dong province is 68km long with a total investment of more than VND 1,400 billion. The project investor is the Vietnam Road Administration and assigned Project Management Board 5 as the project management unit.

To date, the project implementation value has only reached about 55% of the contract value, while the remaining time to complete the project is only 4 months. The project's site clearance has 6/68 km (about 9%) that have not been handed over.

Mot vi tri thi cong tren Quoc lo 28B. Anh: Duy Tuan
A construction site on National Highway 28B. Photo: Duy Tuan

On October 22, Mr. Ho Van Muoi - Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Lam Dong province - led a working group to inspect the progress of site clearance and construction of this project.

Chairman of Lam Dong Provincial People's Committee - Ho Van Muoi emphasized that the project implementation is too slow. If the coming time is still slow and not reach the set progress, it will be forced to change leaders and heads of departments, branches and management boards.

"If contractors cannot do it, they must withdraw immediately" - Mr. Muoi warned. Because according to him, contractors lack means and human resources and have not organized construction synchronously. Many sections have land but there are no workers or machinery to deploy.

Chu tich UBND tinh Lam Dong - Ho Van Muoi cung lanh dao cac so va cac don vi kiem tra thuc te cong trinh. Anh: Duy Tuan
Chairman of Lam Dong Provincial People's Committee - Ho Van Muoi and leaders of departments and units inspected the actual construction. Photo: Duy Tuan

"If by November the situation is not as positive as approved, I will be the one to sign the document proposing to replace the investor" - Mr. Ho Van Muoi emphasized.

Mr. Ho Van Muoi requested the parties to develop a detailed plan, clearly detailing each time frame, so that the project can be completed at all costs according to plan.

According to a report by the Lam Dong Department of Construction, by October 22, the project site clearance had 6 km that had not been handed over for construction. Mainly concentrated in Luong Son commune with 90 households.

In addition, the project is still stuck with un relocated technical infrastructure such as water pipes, medium voltage power, lighting poles, etc., so it cannot be implemented synchronously.

Ong Ho Van Muoi - Chu tich UBND tinh Lam Dong phat bieu chi dao, day nhanh tien do du an Quoc lo 28B. Anh: Duy Tuan
Mr. Ho Van Muoi - Chairman of Lam Dong Provincial People's Committee gave a speech directing and speeding up the progress of National Highway 28B project. Photo: Duy Tuan

According to Project Management Board 5, up to now, 44/62km of crushed stone and 37/62km of asphalt concrete have been provided. The unit requested the contractor to focus on human resources and equipment to speed up the progress.

At the same time, it is required that localities promptly appraise and approve compensation plans to have a basis for paying to households. If the site is handed over in November 2025, the project will be implemented on schedule.

National Highway 28B is the shortest route connecting Phan Thiet to the provincial administrative center, with a large volume of traffic. Accelerating the progress is even more urgent as Lien Khuong Airport is preparing to temporarily suspend operations for upgrading, making this route an important traffic axis for travel and transportation.

Duy Tuấn
RELATED NEWS

National Highway 28B upgrade project is sluggish due to slow handover of land

|

Lam Dong - The construction progress of the National Highway 28B upgrade project is still sluggish due to slow site handover and contractors not focusing on construction equipment and materials.

National Highway 28B project is in disarray, construction is sluggish, lacking labor

|

Lam Dong - On National Highway 28B, many construction sites are shabby, with only signs and markers but no workers or machinery.

1,400 billion VND project to renovate National Highway 28B in Lam Dong is stuck with more than 6km of site clearance

|

Lam Dong - The project to renovate and upgrade National Highway 28B is stuck with more than 6km of site clearance. The Department of Construction has inspected and committed to promptly reporting to remove obstacles and speed up progress.

Workshop "Promoting self-respect and full tax contributions - Building a strong era"

|

Improving tax compliance is not only a technical task, but a step forward in cultural development and trust between the State and citizens.

A good doctor is to consider patients as teachers

|

The Deputy Minister of Health said that good doctors must examine patients, study them, consider patients as teachers, the greatest book of his life.

Quang Tri has heavy rain before the wedding of Miss Do Thi Ha and the young master of Son Hai Group

|

The wedding of Miss Do Thi Ha and the young master of Son Hai Group is taking place in Quang Tri. Heavy rain with winds as storm No. 12 is approaching.

Minister Nguyen Kim Son talks about the roadmap to build a shared textbook set

|

Minister Nguyen Kim Son said that it is expected that in November the Ministry will complete the plan to build a shared textbook set and submit it to the Government for approval.

Thailand investigates new link suspected of involving Cambodian scam leader Chen Zhi

|

Thailand has officially opened an investigation into Prince International - a business suspected of being involved in the network of Cambodian scammer Chen Zhi.

National Highway 28B upgrade project is sluggish due to slow handover of land

Duy Tuấn |

Lam Dong - The construction progress of the National Highway 28B upgrade project is still sluggish due to slow site handover and contractors not focusing on construction equipment and materials.

National Highway 28B project is in disarray, construction is sluggish, lacking labor

Duy Tuấn |

Lam Dong - On National Highway 28B, many construction sites are shabby, with only signs and markers but no workers or machinery.

1,400 billion VND project to renovate National Highway 28B in Lam Dong is stuck with more than 6km of site clearance

Duy Tuấn |

Lam Dong - The project to renovate and upgrade National Highway 28B is stuck with more than 6km of site clearance. The Department of Construction has inspected and committed to promptly reporting to remove obstacles and speed up progress.