Key project
Currently, Binh Dinh province is urgently completing the procedures to start construction investment projects to build a landing road No. 2 and synchronous works at Phu Cat Airport Airport in August, 2025 (under the August. The project of upgrading and expanding Phu Cat airport).
This is a group A project, with a total investment of more than VND 3,200 billion. In particular, the cost of site clearance (GPMB) is about 1,000 billion dong.
The new landing line will have a length of 3,048m, ensuring the receipt of Code C aircraft such as A320, A321 and can be upgraded to receive Code E aircraft when necessary.
![May bay ha canh tai Cang hang khong Phu Cat (Binh Dinh). Anh: Dung Nhan](https://media-cdn-v2.laodong.vn/storage/newsportal/2025/2/9/1460627/Binh-Dinh-10.jpg)
Regarding the implementation progress, Binh Dinh approved the pre -feasibility study report. An environmental impact assessment will be completed before April 2025, approving the feasibility study report in May 525, completing the construction drawing design in July 2025 and aiming to start construction before August 24.
Chairman of Binh Dinh People's Committee Pham Anh Tuan emphasized that this is a key, very serious project, solving bottlenecks, contributing to the socio -economic development of the province.
![Chu tich UBND tinh Binh Dinh (mu xanh) kiem ta hien truong du an Nang cap, mo rong Cang hang khong Phu Cat. Anh: Thanh Thanh](https://media-cdn-v2.laodong.vn/storage/newsportal/2025/2/9/1460627/Binh-Dinh-2.jpg)
"Relevant units need to coordinate closely, accelerate procedures and jobs, especially the site clearance (GPMB) to ensure progress. Along with that, it is necessary to plan the entire translation area. The case, urban, logistics here with long -term, methodical vision.
At the same time, sticking to the plan, coordinating closely, drastic, determined to accelerate the implementation of related tasks, ensuring the start of the project in accordance with the target. 10 months later, it will put into operation phase 1, the take -off line No. 2, "Mr. Pham Anh Tuan directed.
According to the plan approved by the Ministry of Transport, Phu Cat Airport is aimed at a capacity of 5 million passengers/year by 2030 and 7 million passengers/year by 2050.
Do fast but must be careful
Through review, the project affects about 422 households and 6 organizations, with an area of nearly 87.5 hectares recovered, of which more than 4.5 hectares of residential land, nearly 69.5 ha of agricultural land and more 13.5 ha of non -agricultural land. The project also affects 1,000 tombs.
For households affected by the project, Mr. Luu Nhat Phong - Director of Binh Dinh Transport Project Management Board said that the province has agreed to build three resettlement areas in Phu Cat district and An town Nhon to arrange their accommodation. Through the actual survey, most households agree to implement the project in the coming time.
Regarding the handover of national defense land, the province has worked with the Ministry of Defense and related units, currently completing the handover procedures to ensure that it does not affect the operation of the military unit located in the area.
Mr. Pham Anh Tuan suggested that the Transport Project Management Board must do it well and thoroughly the preparation work; The relevant plans and procedures for project implementation, leveling bidding, not to cause errors. Prepare plan for subcontractors.
"Must organize the fastest construction after the bidding is completed. It is necessary to plan the work, the specific detailed plan daily and weekly to implement the project as quickly as possible. Technology and safety in the project implementation process.
Binh Dinh Provincial Party Committee Secretary Ho Quoc Dung said: The province decided to start the project in August 2025. Currently, the capital is sufficient, the province is gathered to be ready to start the second runway. Binh Dinh has worked with the Government, the Prime Minister also supported the bringing Phu Cat airport into an international airport. In the current trend, the central government certainly supports the opening of the sky, so that Binh Dinh will grow two numbers.