According to the objectives, Binh Dinh will start the investment project to build the landing road No. 2 and synchronous works at Phu Cat Airport in August, 2025.

Key project

Currently, Binh Dinh province is urgently completing the procedures to start construction investment projects to build a landing road No. 2 and synchronous works at Phu Cat Airport Airport in August, 2025 (under the August. The project of upgrading and expanding Phu Cat airport).

This is a group A project, with a total investment of more than VND 3,200 billion. In particular, the cost of site clearance (GPMB) is about 1,000 billion dong.

The new landing line will have a length of 3,048m, ensuring the receipt of Code C aircraft such as A320, A321 and can be upgraded to receive Code E aircraft when necessary.

May bay ha canh tai Cang hang khong Phu Cat (Binh Dinh). Anh: Dung Nhan
The aircraft landed at Phu Cat airport. Photo: Dung Nhan

Regarding the implementation progress, Binh Dinh approved the pre -feasibility study report. An environmental impact assessment will be completed before April 2025, approving the feasibility study report in May 525, completing the construction drawing design in July 2025 and aiming to start construction before August 24.

Chairman of Binh Dinh People's Committee Pham Anh Tuan emphasized that this is a key, very serious project, solving bottlenecks, contributing to the socio -economic development of the province.

Chu tich UBND tinh Binh Dinh (mu xanh) kiem ta hien truong du an Nang cap, mo rong Cang hang khong Phu Cat. Anh: Thanh Thanh
Chairman of Binh Dinh People's Committee (Blue Hat) checks the scene of the project upgrading and expanding Phu Cat airport. Photo: Thanh Thanh

"Relevant units need to coordinate closely, accelerate procedures and jobs, especially the site clearance (GPMB) to ensure progress. Along with that, it is necessary to plan the entire translation area. The case, urban, logistics here with long -term, methodical vision.

At the same time, sticking to the plan, coordinating closely, drastic, determined to accelerate the implementation of related tasks, ensuring the start of the project in accordance with the target. 10 months later, it will put into operation phase 1, the take -off line No. 2, "Mr. Pham Anh Tuan directed.

According to the plan approved by the Ministry of Transport, Phu Cat Airport is aimed at a capacity of 5 million passengers/year by 2030 and 7 million passengers/year by 2050.

Do fast but must be careful

Through review, the project affects about 422 households and 6 organizations, with an area of ​​nearly 87.5 hectares recovered, of which more than 4.5 hectares of residential land, nearly 69.5 ha of agricultural land and more 13.5 ha of non -agricultural land. The project also affects 1,000 tombs.

For households affected by the project, Mr. Luu Nhat Phong - Director of Binh Dinh Transport Project Management Board said that the province has agreed to build three resettlement areas in Phu Cat district and An town Nhon to arrange their accommodation. Through the actual survey, most households agree to implement the project in the coming time.

Regarding the handover of national defense land, the province has worked with the Ministry of Defense and related units, currently completing the handover procedures to ensure that it does not affect the operation of the military unit located in the area.

Mr. Pham Anh Tuan suggested that the Transport Project Management Board must do it well and thoroughly the preparation work; The relevant plans and procedures for project implementation, leveling bidding, not to cause errors. Prepare plan for subcontractors.

"Must organize the fastest construction after the bidding is completed. It is necessary to plan the work, the specific detailed plan daily and weekly to implement the project as quickly as possible. Technology and safety in the project implementation process.

Binh Dinh Provincial Party Committee Secretary Ho Quoc Dung said: The province decided to start the project in August 2025. Currently, the capital is sufficient, the province is gathered to be ready to start the second runway. Binh Dinh has worked with the Government, the Prime Minister also supported the bringing Phu Cat airport into an international airport. In the current trend, the central government certainly supports the opening of the sky, so that Binh Dinh will grow two numbers.

Hoài Phương
TIN LIÊN QUAN

Binh Dinh leader directed to focus on cure the victim of the passenger car

|

The Vice Chairman of Binh Dinh province visited and encouraged the victims of the passenger bus accident that occurred in Phu Yen, killing 3 people and injuring many others.

Unique tomorrow at Mai Vang Festival in Binh Dinh

|

Binh Dinh - An Nhon Mai Vang Festival is an opportunity to connect masters with guests, expand the market and bring products to reach far, contributing to the local economic development.

Binh Dinh finds accommodation solutions for people to relocate

|

Facing the concern of more than 24 households in the relocation from the provincial sports training and competition, the Department of Culture and Sports (VHTT) of Binh Dinh province has reported and proposed the provincial People's Committee on aspirations of households.

Tra Vinh issues directives after workers stop work on 26th of Tet

|

Tra Vinh - Regarding the collective work stoppage that occurred on the 26th of Tet, the People's Committee of Tra Vinh province requested that businesses respect workers.

Stocks fluctuate, liquidity drops to low level

|

The stock market on February 12, 2025 continued to struggle with liquidity plunging to its lowest level since the end of January.

Many Department Directors in Bac Ninh and Bac Giang apply for early retirement

|

4 Department Directors of the People's Committees of Bac Ninh and Bac Giang provinces have submitted applications for early retirement to facilitate the work of restructuring the apparatus and organization.

242 officials and workers in Phu Yen apply for early retirement

|

Currently, Phu Yen has 242 cadres, civil servants, public employees and workers who wish to retire early to reorganize and streamline the apparatus.

Fire in 21-storey commercial building in Hanoi, nearly 30 people rescued

|

On the morning of February 12, the electrical technical box on the 4th floor of the 21-story CTM Complex commercial building in Cau Giay district caught fire, causing panic among many people.

Binh Dinh leader directed to focus on cure the victim of the passenger car

Hoài Phương |

The Vice Chairman of Binh Dinh province visited and encouraged the victims of the passenger bus accident that occurred in Phu Yen, killing 3 people and injuring many others.

Unique tomorrow at Mai Vang Festival in Binh Dinh

Hoài Phương |

Binh Dinh - An Nhon Mai Vang Festival is an opportunity to connect masters with guests, expand the market and bring products to reach far, contributing to the local economic development.

Binh Dinh finds accommodation solutions for people to relocate

Hoài Luân |

Facing the concern of more than 24 households in the relocation from the provincial sports training and competition, the Department of Culture and Sports (VHTT) of Binh Dinh province has reported and proposed the provincial People's Committee on aspirations of households.