Investing in Flexible Power Plants and stopping operations of Ninh Binh Thermal Power Plant

NGUYỄN TRƯỜNG |

Ninh Binh - The province is speeding up the implementation of the Flexible Power Plant project and stopping the operation of the old Thermal Power Plant to solve the problem of environmental pollution.

Ninh Binh province is currently focusing on investing in the Ninh Binh Power Plant project with a total capacity of 1,500 MW. Of which, phase I is 300MW and phase II is 1,200MW.

The project is invested by a consortium of investors, Power Generation Corporation 3 - JSC and Thuan Hai Transport Service Joint Stock Company.

Theo lo trinh, den nam 2029, Nha may nhiet dien Ninh Binh hien nay se duoc di doi xong va dua vao van hanh Nha may dien linh hoat. Anh: Nguyen Truong
According to the roadmap, by 2029, the Ninh Binh Thermal Power Plant will be relocated and put into operation. Photo: Nguyen Truong

As planned, the factory will use ICE flexible power technology of Wartsila Group of Finland. To implement the roadmap to stop the operation of the current Ninh Binh Thermal Power Plant (in Hoa Lu ward, Ninh Binh province).

Mr. Nguyen Cao Son - Vice Chairman of Ninh Binh Provincial People's Committee said that planning and investing in the construction of an integrated power plant (ICE) project in Kim Dong commune towards the production of electricity from liquefied natural gas (LNG).

Thereby, supplementing flexible sources for the power system, ensuring the goal of developing the green industry - Energy of Ninh Binh province...

According to Vice Chairman of Ninh Binh Provincial People's Committee Nguyen Cao Son, the expected investment scale for the construction of the Flexible Power Plant Phase I, with a capacity of 300MW with an area of about 8 hectares, and a fuel port of about 9.9 hectares in Kim Dong commune is expected.

The line connecting to the safety corridor affects about 29 hectares. The total investment capital is about 7,100 billion VND from non-budgetary capital, project implementation progress in 2025 - 2027.

Up to now, the project has completed procedures on power planning VIII, power planning VIII, Ninh Binh province planning, land use planning, construction planning and port planning.

In addition, the People's Committee of Ninh Binh province has also requested Power Generation Corporation 3, Thuan Hai Transport Service Joint Stock Company, Ninh Binh Thermal Power Joint Stock Company - JSC, Ninh Binh Power Transmission, to closely coordinate with local departments, branches and sectors to implement investment procedures and procedures to build Ninh Binh Flexible Power Plant and relocate Ninh Binh Thermal Power Plant.

Du an Nha may dien linh hoat Ninh Binh duoc quy hoach dau tu, xay dung tai xa Kim Dong. Anh: Nguyen Truong
The Ninh Binh Flexible Power Plant project is planned to be invested and built in Kim Dong commune. Photo: Nguyen Truong

"Investing in and building Ninh Binh Flexible Power Plant along with stopping operations and relocating Ninh Binh Thermal Power Plant at present aims to thoroughly solve the problem of environmental pollution and urban beautification in a civilized and modern direction, in line with the viewpoint and orientation of urban development of Ninh Binh province" - Vice Chairman of Ninh Binh Provincial People's Committee Mr. Nguyen Cao Son said.

Ninh Binh province is making efforts to speed up the project implementation progress, striving to generate half a capacity of electricity by the end of 2027, the beginning of 2028 and 100% of the capacity by 2029. After the plant comes into operation, it will stop operations and relocate the current thermal power plant.

NGUYỄN TRƯỜNG
RELATED NEWS

The Politburo requests to start construction of international railways and nuclear power plants from the beginning of 2026

|

The Politburo requested to start construction of a number of important projects in fields such as international railway projects, nuclear power... from the beginning of 2026.

In the fourth quarter of 2025, Quang Ninh started construction of a 3,200 billion VND waste-to-energy plant

|

Quang Ninh - Quang Ninh is making efforts to complete procedures to start a number of key projects outside the budget by the end of 2025, including waste-to-energy plants.

Proposal to bid for investment in Long Son Solar Power Plant Phase 2 with a capital of VND1,700 billion

|

Khanh Hoa is carrying out the process for the land to conduct bidding to select investors for the Long Son Solar Power Plant project - Phase 2.

Resolutely handle households placing containers in the construction site of the Ring Road 2.5 project

|

Hanoi - The authorities of Phuong Liet ward have cleared the areas encroaching on the underpass project and Ring Road 2.5.

Car catches fire in the middle of rush hour in Hanoi

|

Hanoi - During rush hour this afternoon, a car was traveling at the Xuan La - Vo Chi Cong intersection when it suddenly caught fire.

Advising Vietnamese citizens on the Cambodia - Thailand conflict

|

The Ministry of Foreign Affairs recommends that Vietnamese citizens living in border provinces between Cambodia and Thailand.

China completes testing new stealth UAV

|

The flight marks an important step forward in China's stealth UAV program.

SEA Games 33 Medal Schedule on December 15

|

Updated total medal table of the 33rd SEA Games on December 15.

The Politburo requests to start construction of international railways and nuclear power plants from the beginning of 2026

Vương Trần |

The Politburo requested to start construction of a number of important projects in fields such as international railway projects, nuclear power... from the beginning of 2026.

In the fourth quarter of 2025, Quang Ninh started construction of a 3,200 billion VND waste-to-energy plant

Nguyễn Hùng |

Quang Ninh - Quang Ninh is making efforts to complete procedures to start a number of key projects outside the budget by the end of 2025, including waste-to-energy plants.

Proposal to bid for investment in Long Son Solar Power Plant Phase 2 with a capital of VND1,700 billion

Hữu Long |

Khanh Hoa is carrying out the process for the land to conduct bidding to select investors for the Long Son Solar Power Plant project - Phase 2.