1 bottom spillway of Hoa Binh Hydropower Reservoir, 2 spillways of Thac Ba Reservoir were ordered to close this afternoon

Huy Hùng |

The Ministry of Agriculture and Environment requested to close the bottom spillway of Hoa Binh hydroelectric reservoir at 2:00 p.m. this afternoon.

The Ministry of Agriculture and Environment has just issued a telegram on closing the bottom spillway of Hoa Binh hydroelectric reservoir. The dispatch clearly stated that at 2:00 p.m. on July 30, 2025, the upstream water level of Hoa Binh Lake was at 100.42m, the downstream water level was 13.29m, the flow to the lake was 3,449 m3/s, the total downstream flow was 3,940 m3/s.

Implement the Inter-reservoir operation process in the Red River basin in Decision No. 740/QD-TTg dated June 17, 2019 of the Prime Minister, Decision No. 922/QD-TTg dated May 14, 2025 of the Prime Minister amending and supplementing a number of articles of the Inter-reservoir operation process in the Red River basin; Resolution No. 102/NQ-CP dated June 29, 2024 of the Government on ensuring the direction and operation of natural disaster prevention and control during the period of perfecting the direction and command of civil defense agencies at all levels, Document No. 3995/VPCP-NN dated May 8, 2025 of the Government Office on organizing monitoring, supervision and implementation of natural disaster prevention and control work, Minister of Agriculture and Environment and Order of Director of Hoa Binh Hydropower Company:

Closing 01 bottom spillway of Hoa Binh Lake at 14:00 on July 31, 2025. Closely monitor the development of floods, safety of works, flow to the reservoir, water levels upstream and downstream of the reservoir and promptly report to the Ministry of Agriculture and Environment.

The Ministry also sent an official dispatch to the People's Committees of the provinces and cities: Phu Tho, Hanoi, Bac Ninh, Hai Phong, Hung Yen, Ninh Binh on ensuring safety downstream when operating Hoa Binh hydroelectric reservoir. The Ministry of Agriculture and Environment requests the People's Committees of provinces and cities:

Notify authorities at all levels, people, and organizations operating on rivers and along rivers to know information to proactively take measures to ensure safety and adjust operations accordingly. Timely report any unusual situations to the Ministry of Agriculture and Environment.

On the same day, the Ministry of Agriculture and Environment also issued a telegram on closing the Thac Ba hydroelectric reservoir's discharge gate. Accordingly, at 7:00 a.m. on July 31, 2025, the upstream water level of Thac Ba Lake was at 55.93 m, the downstream water level was 24.50 m, the flow to the lake was 292 m3/s, the total downstream flow was 503 m3/s.

The Minister of Agriculture and Environment ordered the Director of Thac Ba Hydropower Joint Stock Company: close 02 face-to-face gates (No. 01 and No. 03) at 4:00 p.m. on July 31, 2025. Closely monitor the development of floods, safety of works, flow to the reservoir, water levels upstream and downstream of the reservoir and promptly report to the Ministry of Agriculture and Environment.

To ensure safety when operating Thac Ba hydroelectric reservoir, the Ministry of Agriculture and Environment recommends that the People's Committees of Lao Cai, Tuyen Quang, Phu Tho provinces and cities, Hanoi notify all levels of government, people, and organizations operating on rivers and along rivers to know information to proactively take measures to ensure safety and adjust operations accordingly.

Timely report any unusual situations to the Ministry of Agriculture and Environment (through the Department of Dyke Management and Natural Disaster Prevention and Control).

Huy Hùng
RELATED NEWS

Order to close 2 consecutive bottom spillways of Hoa Binh hydroelectric reservoir, 6 provinces and cities must ensure safety

|

The Ministry of Agriculture and Environment has just issued a telegram on closing the bottom spillway of Hoa Binh Lake.

Close-up of Hoa Binh Hydropower Plant releasing water, creating a unique scene on the Da River

|

Phu Tho - Hoa Binh Hydropower Plant released its bottom on the morning of July 9, the rushing water released white foam, creating a majestic scene.

Nearly 1 year after the historic flood, Tuyen Quang Hydropower Plant opens 3 bottom spillways

|

Tuyen Quang Hydropower Plant opens 3 bottom spillways, floods on the Gam and Lo rivers rise.

Thai Nguyen approves policy on expressway project worth nearly 30,000 billion VND

|

The People's Council of Thai Nguyen province has just passed a Resolution on agreeing on the policy of assigning the People's Committee of Cao Bang province as the managing agency to implement the Bac Kan - Cao Bang Expressway Construction Investment Project.

To get rid of motorbikes faster, many people in Hanoi receive fines for traveling on prohibited routes

|

Hanoi - Many people were fined for riding motorbikes on the elevated Ring Road 2.

Son La urban area is about to escape flooding thanks to a drainage project worth over VND900 billion

|

Son La - The drainage and wastewater treatment project worth more than 900 billion VND is being urgently completed, in time to be inaugurated on the occasion of the 80th anniversary of the August Revolution (August 19, 2025).

VCCI solemnly organizes the 9th Congress of Delegates, term 2025-2030

|

On July 31, the Party Executive Committee of the Vietnam Federation of Commerce and Industry (VCCI) solemnly held the 9th VCCI Party Congress, term 2025-2030.

Rach Mieu 2 Bridge completes final items, ready to open to traffic

|

Vinh Long - Rach Mieu 2 Bridge is completing the final stage, ready to open to traffic on September 2. Workers are happy when the project is about to reach the finish line.

Order to close 2 consecutive bottom spillways of Hoa Binh hydroelectric reservoir, 6 provinces and cities must ensure safety

Huy Hùng |

The Ministry of Agriculture and Environment has just issued a telegram on closing the bottom spillway of Hoa Binh Lake.

Close-up of Hoa Binh Hydropower Plant releasing water, creating a unique scene on the Da River

Đặng Tình - Bình Khang |

Phu Tho - Hoa Binh Hydropower Plant released its bottom on the morning of July 9, the rushing water released white foam, creating a majestic scene.

Nearly 1 year after the historic flood, Tuyen Quang Hydropower Plant opens 3 bottom spillways

Việt Bắc |

Tuyen Quang Hydropower Plant opens 3 bottom spillways, floods on the Gam and Lo rivers rise.