Slow disbursement of foreign capital, barriers need to be removed

Minh Ánh |

Disbursement of foreign capital for public investment in 2024 will only reach 39%. The Ministry of Finance's conference proposed key solutions to achieve the target of 95%.

Disbursement rate is still low, many units have not completed

On December 3, 2024, at the headquarters of the Ministry of Finance, a conference between the Ministry of Finance and ministries and branches on the disbursement of foreign capital public investment capital took place.

According to data from the TABMIS system and reports from central ministries and branches, by the end of November 2024, the disbursement rate of foreign-funded public investment capital only reached 39.06% of the adjusted plan. Of which, two ministries with a disbursement rate of over 50% are the Ministry of Transport and the Ministry of Natural Resources and Environment. However, four ministries and branches including the Ministry of Education and Training, the Ministry of Construction, the Ministry of Labor, War Invalids and Social Affairs, and the Ministry of Health have not yet disbursed the assigned capital plan.

This poses a major challenge in achieving the target of disbursing at least 95% of the capital plan as set by the Government.

Main reasons for slow disbursement

At the Conference, delegates discussed and pointed out the causes leading to slow disbursement, including:

Delayed site clearance: Many projects face difficulties in compensation and land acquisition.

Prolonged bidding and engineering design: The bidding process is not synchronized, causing delays.

Adjusting investment policies many times: Many projects have to change the content of loan agreements, prolonging the approval time.

Slow response from sponsors: Processing of bidding documents and amendments to loan agreements is slow from foreign partners.

The conference agreed on key solutions including:

Strengthen progress monitoring: Accelerate the implementation of projects that have completed investment preparation work.

Urgently handle problems: Focus on removing difficulties in site clearance, bidding and project adjustment.

Timely reporting to superiors: For issues beyond their authority, ministries and branches need to promptly synthesize and report to the Government.

Determined to complete the 2024 goal

2024 is the fourth year of the 2021-2025 Socio-Economic Development Plan, an important period to create a strong shift in implementing development goals. Disbursement of public investment not only promotes domestic production but also contributes to infrastructure development, removing bottlenecks and promoting sustainable economic growth.

The Ministry of Finance and other ministries and branches are committed to implementing the proposed solutions, striving to achieve a disbursement rate of at least 95% of the 2024 capital plan as set out in Resolution 01/NQ-CP.

Minh Ánh
TIN LIÊN QUAN

Disbursement of public investment capital in Tuyen Quang is difficult to reach the finish line

|

Disbursement of public investment capital in Tuyen Quang has only reached more than 45%, slower than the set plan, while there is less than 1 month left until the end of 2024.

Problems causing Vinh Phuc to slow down disbursement of public investment capital

|

The disbursement rate of public investment capital of Vinh Phuc province in the first 10 months of 2024 was nearly 30% lower than the same period in 2023, ranking 21st in the country.

Yen Bai has disbursed more than 2,800 billion VND in budget capital

|

Up to now, Yen Bai province has disbursed over 2,800 billion VND of state budget capital, equal to 47.1% of the plan.

Spreading love from the National Humanitarian Month in 2025

|

HCMC - On May 8, the launching ceremony of the National Humanitarian Month 2025 was held in HCMC, with the theme "Humanitarian Journey - Spreading Love".

Mass fish deaths, white water surface on Nhieu Loc - Thi Nghe canal in Ho Chi Minh City

|

HCMC - Nhieu Loc - Thi Nghe Canal has a series of dead fish floating on the water surface, giving off a foul smell, suspected of causing pollution due to the first rains of the season.

Mr. Ngo Quyen The - owner of Long Chat Quan advertises a "40m longeu xe"

|

On the morning of May 8, the interdisciplinary food safety inspection team of Cau Giay district, Hanoi city suddenly inspected the cigarette butts facility - "Long Chat Quan".

Reviewing Principal who sent sensitive photos to school's Zalo

|

Gia Lai - The principal sent sensitive photos to the school's internal Zalo group and was criticized.

Disbursement of public investment capital in Tuyen Quang is difficult to reach the finish line

Việt Bắc |

Disbursement of public investment capital in Tuyen Quang has only reached more than 45%, slower than the set plan, while there is less than 1 month left until the end of 2024.

Problems causing Vinh Phuc to slow down disbursement of public investment capital

Trần Bùi |

The disbursement rate of public investment capital of Vinh Phuc province in the first 10 months of 2024 was nearly 30% lower than the same period in 2023, ranking 21st in the country.

Yen Bai has disbursed more than 2,800 billion VND in budget capital

Trần Bùi |

Up to now, Yen Bai province has disbursed over 2,800 billion VND of state budget capital, equal to 47.1% of the plan.