Disbursement of public investment capital in Tuyen Quang is difficult to reach the finish line

Việt Bắc |

Disbursement of public investment capital in Tuyen Quang has only reached more than 45%, slower than the set plan, while there is less than 1 month left until the end of 2024.

Many bottlenecks

In early December 2024, at the Tuyen Quang - Ha Giang expressway project through Tuyen Quang province, the entire route could not be completed on schedule, partly due to lack of land and partly due to lack of land for embankment.

The section from Km23+00-Km43+00, part of Package 20, is currently short of nearly 2 million cubic meters of fill. Many locations cannot yet construct the foundation, which greatly affects the committed project progress.

"The hilly land within the project area is available but cannot be exploited yet due to regulations related to mineral exploitation. We have worked with the investor and relevant departments but have not been able to resolve the issue yet," said a contractor.

Mot so goi thau cao toc Tuyen Quang  - Ha Giang bi thieu dat dap, chua ban giao xong mat bang khien tien do thi cong bi anh huong. Anh: Viet Bac.
Some Tuyen Quang - Ha Giang expressway packages lacked fill soil and had not yet completed the site handover, affecting the construction progress. Photo: Viet Bac.

Meanwhile, the entire Tuyen Quang - Ha Giang expressway, a 77km section through Tuyen Quang province, is currently being constructed in a "slow-moving" manner due to a lack of land. According to the investor, by the end of November, the project still had 12.74km that had not been handed over due to problems with the people.

Tuyen Quang General Hospital project with an investment of nearly 1,800 billion VND. After more than 10 months of construction, the total value of completed volume reached 250 billion VND, equivalent to 23% of the contract value. Currently, the project is lacking about 60,000m3 of land for filling and leveling. This is also a key project of Tuyen Quang province.

Find a solution

The total public investment capital plan managed by Tuyen Quang province is over 6.1 trillion VND. Of which, the capital allocated in 2024 is over 5.8 trillion VND, the rest is capital from the previous year carried over to this year. By the end of October, the province had disbursed about 45%, slower than the set plan.

Currently, with the Tuyen Quang - Ha Giang Expressway Project, the investor is developing a comprehensive adjustment plan as a basis for implementation, closely coordinating with districts and cities to focus on removing obstacles in terms of land to speed up construction. There are currently 265 households whose compensation plans have not been approved.

Tien do giai ngan von dau tu cong tai Tuyen Quang dang bi cham va kho ve dich trong nam 2024. Anh: Viet Bac.
The progress of disbursement of public investment capital in Tuyen Quang is slow and unlikely to reach the target in 2024. Photo: Viet Bac.

Mr. Nguyen Thien Tuyen - Director of the Project Management Board of Tuyen Quang Province's Traffic Construction Investment said that to ensure the progress by December 31, 2024, the Board is approaching each household with problems to work with the locality to resolve difficulties for each household and each point; coordinating with relevant departments and branches to advise the Provincial People's Committee to resolve dumping points and embankment soil.

At the end of November, Mr. Nguyen Van Son - Chairman of Tuyen Quang Provincial People's Committee issued an Official Dispatch directing to promote disbursement of public investment capital in 2024 and accelerate the implementation of key projects in the area.

In particular, it is recommended that investors and contractors increase human resources, materials, construction machinery and equipment in the spirit of "3 shifts, 4 shifts". Timely acceptance and payment of completed volume to disburse public investment capital, with special attention to labor safety.

Tuyen Quang State Treasury has increased the arrangement of officials and civil servants to control state budget expenditures, receive and process payment records to meet the disbursement of public investment capital in 2024.

Việt Bắc
RELATED NEWS

Hundred billion dong embankment in Tuyen Quang devastated after 8 years of collapse

|

A section of the Lo River embankment through Tuyen Quang City was eroded and collapsed in 2017. Although it has been repaired, this billion-dollar embankment project is still in ruins.

Problems causing Vinh Phuc to slow down disbursement of public investment capital

|

The disbursement rate of public investment capital of Vinh Phuc province in the first 10 months of 2024 was nearly 30% lower than the same period in 2023, ranking 21st in the country.

Series of hundred billion road projects in Tuyen Quang are unlikely to finish on time

|

A series of hundred-billion-dong road projects in Tuyen Quang are unlikely to be completed on time in late 2024 and early 2025 due to a number of unresolved issues.

U22 Indonesia stops in the group stage of the 33rd SEA Games

|

On the evening of December 12, U22 Indonesia defeated U22 Myanmar 3-1 but still could not win a place in the semi-finals of the 33rd SEA Games men's football tournament.

Strong cold air forecast causing bad weather

|

Strong cold air causes unfavorable weather in many sea areas; The Gulf of Tonkin has northeast winds of level 7, sometimes level 8, gusting to level 9 from noon and afternoon of December 13.

The secret to helping Vietnamese karate fighters overcome Thailand

|

Boxer Khuat Hai Nam defeated host Thailand to win the gold medal for Vietnamese karate at the 33rd SEA Games.

Kim Chung CT3 social housing application is paid in large numbers due to lack of salary table photos for the whole company

|

Hanoi - On December 12, many people who came to submit documents at the CT3 Kim Chung social housing project had their documents returned due to the lack of photocopy of the salary table of the whole company.

Lieutenant General Le Van Huong holds the position of Deputy Chief of the General Staff of the People's Army

|

Lieutenant General Le Van Huong - Director of the Department of Military Affairs, General Staff was appointed to the position of Deputy Chief of the General Staff of the Vietnam People's Army.

Hundred billion dong embankment in Tuyen Quang devastated after 8 years of collapse

Việt Bắc |

A section of the Lo River embankment through Tuyen Quang City was eroded and collapsed in 2017. Although it has been repaired, this billion-dollar embankment project is still in ruins.

Problems causing Vinh Phuc to slow down disbursement of public investment capital

Trần Bùi |

The disbursement rate of public investment capital of Vinh Phuc province in the first 10 months of 2024 was nearly 30% lower than the same period in 2023, ranking 21st in the country.

Series of hundred billion road projects in Tuyen Quang are unlikely to finish on time

VIỆT BẮC |

A series of hundred-billion-dong road projects in Tuyen Quang are unlikely to be completed on time in late 2024 and early 2025 due to a number of unresolved issues.