Accordingly, the People's Committee of Hai Duong province has just approved the investment policy and approved the investor to implement the Tan Viet 220kV Transformer Station Project and the Tan Viet 220kV line (Binh Giang) - Gia Loc branch - Pho Noi.
The project has a total investment of more than 783 billion VND, the investor is the National Power Transmission Corporation (EVNNPT), headquartered in Hoan Kiem district, Hanoi city.
The project implementation location is in Hung Thang commune, Binh Giang district; Cam Dong commune, Cam Giang district, Hai Duong province with a total area of about 75,900 m2.
The investment scale of the project includes: Tan Viet 220kV transformer station, Binh Giang 110kV transformer station and connecting lines. The project is expected to be completed and put into operation in the first quarter of 2028.
Upon completion, the project will help improve the capacity of electricity transmission and distribution to meet the growing demand for load in Hai Duong province; improve the quality of electricity supply and reduce power loss on the transmission grid and support existing 220 kV substations in the area; strengthen regional power system connectivity, improve safety, reliability and stability in the operation of regional and national power systems; increase the efficiency of electricity production and business of EVN and EVNNPT.
Hai Duong Provincial People's Committee requests investors to implement the project in compliance with the laws on investment, land, environment, tax, electricity, fire prevention and fighting and related laws during the implementation of the investment project; subject to inspection and supervision by competent State agencies. Quarterly, responsible for preparing a report assessing the implementation status of the project, sending it to the Department of Planning and Investment for synthesis and reporting to the Provincial People's Committee.