Signing of 4,334 billion VND contract to build Bac Ai pumped storage hydropower plant

Tuyết Lan |

It is expected that in December 2029, Bac Ai pumped storage hydropower plant (Ninh Thuan) will generate electricity from the first unit and complete the entire project in May 2031.

On the afternoon of February 13, Vietnam Electricity Group (EVN), Power Project Management Board 3 and the Contractor Consortium held the Signing Ceremony of Package 02XL-BA "Construction and installation of Bac Ai pumped-storage hydropower plant - phase 2, phase 1 of Bac Ai pumped-storage hydropower plant project - Ninh Thuan province".

The Bac Ai pumped storage hydropower plant project in Ninh Thuan province (the Project) was approved by the Prime Minister in the national power development plan for the 2021-2030 period, with a vision to 2050.

The project has a scale of 1,200 MW, including 4 turbine/pump - generator/engine units with a capacity of 300 MW/unit. The total investment of the Bac Ai pumped storage hydropower project is about 21,100 billion VND, the capital for the project is arranged from loans and capital allocated by EVN. It is expected that the first unit will generate electricity by December 2029 and the entire project will be completed by May 2031.

Through the process of open domestic bidding via the Internet, the Contractor Consortium: Lung Lo Construction Corporation, Song Da Corporation, LILAMA 10 Joint Stock Company, SCI E&C Joint Stock Company, Construction Joint Stock Company 47, Truong Son Construction Corporation and Vietnam Construction and Import-Export Joint Stock Corporation won the bid for package 02XL-BA with a value of 4,334 billion VND.

The contract implementation period is approximately 81 months, with the construction progress of unit 1 in December 2029, unit 2 in April 2030, unit 3 in August 2030, unit 4 in December 2030 and the entire contract completed in May 2031.

Speaking at the signing ceremony, a representative of the Vietnam Electricity Group said that this is the first pumped storage hydropower project built in Vietnam and is one of EVN's key projects to be implemented in 2025.

During the investment preparation and project implementation process, EVN received close attention and direction from the Government, the Ministry of Industry and Trade, the State Capital Management Committee at Enterprises, along with the support and close coordination of the Ninh Thuan Provincial People's Committee and the provincial Departments and Branches to develop a construction organization plan, select suitable contractors, and ensure requirements on safety, progress, and quality of the project.

Vietnam Electricity Group assigned the Power Project Management Board 3 and the 02XL-BA Package Joint Venture to manage the project, organize construction to ensure compliance with quality and environmental requirements, focus resources and equipment to speed up progress, and strive to complete the project according to the set plan.

Tuyết Lan
RELATED NEWS

Late afternoon on the largest hydroelectric reservoir in Tuyen Quang

|

Fishermen on the Tuyen Quang hydroelectric reservoir are still busy on the last afternoon of the year, hoping for a less difficult life in the mountainous region.

Union encourages workers to construct Hoa Binh Hydropower Expansion Project

|

A delegation of the Vietnam Electricity Trade Union recently had a meeting to encourage and visit workers at the construction site of the Hoa Binh Hydropower Plant expansion project.

Hydroelectric power plant discharges water, how is the Lo River in Tuyen Quang, Phu Tho?

|

After hydroelectric reservoirs released water, the water level of Lo River in Phu Tho and Tuyen Quang provinces has changed rapidly in recent days.

Fire on the 16th floor of PH apartment building in Khanh Hoa, black smoke rises high

|

Khanh Hoa - Fire on the 16th floor of PH apartment building in Khanh Hoa caused black smoke to rise high, firefighters are urgently extinguishing the fire.

Hanoi exempts bus and metro ticket prices to serve people during Tet 2026

|

Hanoi exempts bus and urban railway tickets for 9 days of the 2026 Lunar New Year, serving people and tourists to travel conveniently.

Golden horse 4.0, a mascot carrying a clear development message of Da Nang

|

Horse mascots simultaneously appear throughout squares and parks, from urban to rural areas across the country. The 4.0 horse in Da Nang is different.

Party and State leaders will visit Uncle Ho's Mausoleum on the occasion of the 2026 Lunar New Year

|

The delegation of Party and State leaders will visit President Ho Chi Minh's Mausoleum and commemorate heroic martyrs on the occasion of the Binh Ngo Lunar New Year 2026.

House fire in Ho Chi Minh City, black smoke rises tens of meters high

|

Ho Chi Minh City - On February 12, a large fire occurred at a house near the Le Duc Anh - Pham Dang Giang intersection, right next to the Go May overpass area.

Late afternoon on the largest hydroelectric reservoir in Tuyen Quang

Nguyễn Tùng |

Fishermen on the Tuyen Quang hydroelectric reservoir are still busy on the last afternoon of the year, hoping for a less difficult life in the mountainous region.

Union encourages workers to construct Hoa Binh Hydropower Expansion Project

Lương Nguyễn |

A delegation of the Vietnam Electricity Trade Union recently had a meeting to encourage and visit workers at the construction site of the Hoa Binh Hydropower Plant expansion project.

Hydroelectric power plant discharges water, how is the Lo River in Tuyen Quang, Phu Tho?

Tô Công |

After hydroelectric reservoirs released water, the water level of Lo River in Phu Tho and Tuyen Quang provinces has changed rapidly in recent days.