Quang Binh drastically handled investment projects slowly scheduled

CÔNG SÁNG |

Quang Binh - the province reviews weak investors, recovers a series of projects behind schedule, especially in coastal areas.

Control the weak investor

The disbursement rate of public investment capital in the first quarter of the province is only 10.7% of the assigned government target, causing the locality to implement many strong measures to rectify and handle violations, including the review of the investor's responsibility and the recovery of long and low -efficiency projects.

Quang Binh People's Committee said that the total public investment capital was disbursed only VND 478 billion. The main reason comes from the delay in the direction and administration of investors. Facing this situation, the Provincial People's Committee requested to strictly review the units that did not complete the task, and at the same time consider replacing weak and irresponsible individuals.

Notably, the City People's Committee. Dong Hoi and Minh Hoa District People's Committee were criticized for not disbursing all public investment capital in 2023, leading to the cancellation of capital, many projects were not completed. The province requires the investors to send the monthly progress report, the case of delayed no reason will be strictly handled.

In parallel with the promotion of disbursement, Quang Binh also promotes the review and recovery of projects behind schedule. From 2021 to now, the province has recovered 54 projects, of which in 2024, in 2024, accounting for 45 projects. It is expected that in the coming time, Quang Binh will continue to recover 59 more projects out of the remaining 90 projects.

A number of large projects with the "golden land" of the abandoned coastal coastal for many years are also in the context of recovery such as Saigon - Bao Ninh eco -tourism area that has been licensed since 2009 but has only built the rough part of the hotel; The 5 -star Pullman hotel project has been licensed from 2016 to now still unfinished.

Project recovery

Mr. Nguyen Xuan Dat - Director of Quang Binh Department of Finance - said that the Department was assigned to be a standing agency for working groups to remove difficulties in disbursement of public investment. The criticism of investors delayed disbursement is held periodically and publicly on the communication information system. The violating units will not only be recovered but also responsible for explanation before the meeting.

Also in the first quarter of 2025, Quang Binh province approved the investment policy for 7 domestic projects with a total registered capital of over VND 2,900 billion, including 4 projects outside the economic zone and 3 projects in economic zones and industrial parks.

The People's Committee of Quang Binh province said that the handling of projects behind schedule is being drastically directed. Of the 59 projects preparing to withdraw, 8 projects have agreed to terminate the operation and are carrying out legal procedures; The remaining 51 projects are slow, have not deposited or have been allocated land but implemented too slowly.

The provincial People's Committee requires relevant departments and agencies to continue reviewing and proposing plans to completely resolve outstanding and inefficient projects. Resolutely recover the works that are no longer needed to release investment resources for key and more practical projects.

CÔNG SÁNG
TIN LIÊN QUAN

Many projects of the 4,500 classroom project are behind schedule

|

HCMC - Many school construction projects are facing difficulties, so it will be difficult to complete the goal of having 4,500 new classrooms in use by the end of 2025.

Nearly 6 years behind schedule, the 396 billion VND project in Binh Dinh is under a comprehensive review

|

The Chairman of the People's Committee of Binh Dinh province directed the review and clarification of issues related to the Ngo May extended road project, after the proposal to temporarily suspend the project from the Department of Finance.

ADB warns of many projects in Quang Tri at risk of being behind schedule

|

Many projects using ADB loans in Quang Tri still have large unfinished volumes, posing a potential risk of not being able to complete on schedule.

Man suspected of falling from a high-rise apartment building in Long Bien

|

Hanoi After a loud noise, people discovered a man lying motionless on the ground, suspected of falling from a high floor of an apartment building.

Meritorious Artist Hoai Linh speaks out before a series of news of a rare disease and passed away

|

In the face of many negative rumors about him, Meritorious Artist Hoai Linh has responded.

Advising Vietnamese people to proactively leave Israel through road border gates

|

The Vietnamese Embassy in Israel recommends that people proactively leave Israel through the border gate, especially towards Jordan or Egypt.

Dak Nong Secretary speaks out about rumors of daughter being restructured to become commune leader

|

Dak Nong - Mr. Ngo Thanh Danh - Secretary of the Provincial Party Committee responded after rumors that daughters were restructured to become commune leaders.

Many projects of the 4,500 classroom project are behind schedule

Chân Phúc |

HCMC - Many school construction projects are facing difficulties, so it will be difficult to complete the goal of having 4,500 new classrooms in use by the end of 2025.

Nearly 6 years behind schedule, the 396 billion VND project in Binh Dinh is under a comprehensive review

Thảo Phương |

The Chairman of the People's Committee of Binh Dinh province directed the review and clarification of issues related to the Ngo May extended road project, after the proposal to temporarily suspend the project from the Department of Finance.

ADB warns of many projects in Quang Tri at risk of being behind schedule

HƯNG THƠ |

Many projects using ADB loans in Quang Tri still have large unfinished volumes, posing a potential risk of not being able to complete on schedule.