The Prime Minister requested determination to complete the 500kV Lao Cai - Vinh Yen line by August 19, 2025

Tuyết Lan |

Prime Minister Pham Minh Chinh requested that by August 19, 2025, the 500kV Lao Cai - Vinh Yen transmission line must be completed so that the national power system can operate safely and stably.

On August 9, inspecting the construction of the 500kV Lao Cai - Vinh Yen line at the VT404 pole foundation (Thai Hoa commune, Phu Tho) and the VT369 pole foundation (Dan Chu commune, Phu Tho), Prime Minister Pham Minh Chinh praised the enthusiastic, proactive and determined labor spirit of localities and forces participating in the project.

Thu tuong Chinh phu Pham Minh Chinh truc tiep kiem tra Du an Duong day 500kV Lao Cai - Vinh Yen. Anh: Tuyet Lan
Prime Minister Pham Minh Chinh directly inspected the Lao Cai - Vinh Yen 500kV Power Line Project. Photo: Tuyet Lan

The Prime Minister noted that units should pay attention to, care for the lives, and maintain the health of workers in the current hot weather conditions. The Ministry of National Defense directed Military Region 2 to arrange military forces to deploy logistics work for construction such as setting up field fields to support workers in all weather conditions; supporting food, drinking water, pulling ropes, etc.

Thu tuong trao doi voi cac don vi tai vi tri mong cot VT404 tren dia ban xa Thai Hoa. Anh: Tuyet Lan
The Prime Minister discussed with units at the VT404 pole foundation in Thai Hoa commune (Phu Tho). Photo: Tuyet Lan

"Units apply and promote good experiences from the construction of the 500kV line 3 Quang Trach - Pho Noi to quickly construct the 500kV line Lao Cai - Vinh Yen" - the Prime Minister emphasized.

Thu tuong Chinh phu Pham Minh Chinh tang qua dong vien cac luc luong thi cong tai cong truong. Anh: Tuyet Lan
Prime Minister Pham Minh Chinh presented gifts to encourage the construction forces at the construction site. Photo: Tuyet Lan

After inspecting the construction site, right in Dan Chu commune, the Prime Minister had a working session with leaders of ministries, branches, Vietnam Electricity Group and leaders of Lao Cai and Phu Tho provinces to resolve difficulties and problems, determined to complete the project "as soon as possible".

Reporting to the Prime Minister, Mr. Dang Hoang An - Chairman of the Board of Members of Vietnam Electricity Group (EVN) - said that the project's site clearance work has completed 468/468 pole foundation locations; handed over the route corridor with 196/242 anchorages, reaching 81%. The construction units have completed 468/468 pole foundation locations; installed 306/468 steel column locations, and are transporting, gathering and installing the remaining 162 locations. Along with that, the rope is being spread and pulled at 22/242 anchorage areas.

"During the project construction process, there were some difficulties. For example, difficulties due to weather conditions, high and rugged terrain, sloping, muddy and slippery construction roads. The project also encountered difficulties in human resources, the contractor's labor force did not meet the project's needs in the conditions of high construction demand, short time and simultaneous implementation of many tasks. In addition, difficulties in site clearance have not been completed, and some households have even caused difficulties and obstructed construction" - EVN representative reported.

Thu tuong Chinh phu Pham Minh Chinh yeu cau dut khoat den 19.8.2025 phai hoan thanh du an de tang cuong kha nang van hanh an toan, on dinh cua He thong dien quoc gia. Anh: Tuyet Lan
Prime Minister Pham Minh Chinh requested that the project must be completed by August 19, 2025 to enhance the safe and stable operation of the National Power System. Photo: Tuyet Lan

At the working session, Prime Minister Pham Minh Chinh requested that the project must be completed by August 19, 2025 to enhance the safe and stable operation of the National Power System, unblock the capacity of hydropower plants in the Northwest region and neighboring provinces, promote socio-economic development, urban development, industry and services.

Therefore, the relevant entities "are determined, are even more determined; have tried, are trying more; have been determined, are more determined; have focused on focusing, are more focused, are more focused". Thereby, promoting the assurance of progress, quality, technique, art, labor safety, environmental protection along the entire route; ensuring the material and spiritual life, legitimate rights and interests of people affected by the project, the new place is better than the old place.

The Prime Minister requested the entire political system to get involved, promoting the mastery of the people.

The Prime Minister directed the establishment of a forward command team to direct the implementation of the project, led by the Chairman of the EVN Board of Members, the Standing Deputy Head of the Team is the General Director of EVN, members are the two Secretaries of Lao Cai and Phu Tho Provincial Party Committees, Deputy Ministers of National Defense, First Secretary of the Central Committee of the Ho Chi Minh Communist Youth Union, leaders of Military Region 2 and coordinated closely, synchronously, smoothly and effectively.

Du an Duong day 500kV Lao Cai - Vinh Yen (Du an) la du an quan trong quoc gia, duoc Thu tuong Chinh phu giao EVN lam chu dau tu, co muc tieu tang cuong kha nang van hanh an toan, on dinh cua He thong dien quoc gia. Anh: Tuyet Lan
The Lao Cai - Vinh Yen 500kV Power Line Project is a national important project, assigned by the Prime Minister to EVN as the investor, with the goal of enhancing the safe and stable operation capacity of the National Power System. Photo: Tuyet Lan

The 500 kV Lao Cai - Vinh Yen Line project has a total investment of more than VND 7,410 billion, with a total length of about 229.5km passing through 31 communes in Lao Cai and Phu Tho provinces, with a total of 468 electric pole foundation locations. The project affects 2,189 households, of which 213 households must be resettled.

Tuyết Lan
RELATED NEWS

Continue to focus on taking care of workers constructing the 500kV Lao Cai - Vinh Yen line

|

The leaders of the Vietnam General Confederation of Labor directly presented gifts and encouraged workers constructing the 500kV Lao Cai - Vinh Yen line.

The Electricity Trade Union presented 228 million VND to workers on the 500kV Lao Cai - Vinh Yen power line

|

The leaders of the Vietnam Electricity Trade Union encouraged workers constructing the 500kV Lao Cai - Vinh Yen transmission line.

Urgently constructing, striving to energize the 500kV power line on August 19

|

The 500kV Lao Cai - Vinh Yen transmission line project, nearly 230km long, is entering the final stage, striving to energize on August 19 under the direction of the Prime Minister.

Ukrainian President makes tough statement ahead of US-Russia meeting

|

Ukrainian President Zelensky stressed the principle of territorial integrity, rejecting any agreement requiring a territorial transfer to Russia.

Madam Pang sells shirt to help the Football Association of Thailand pay off debt

|

Madam Pang has officially launched the "Thai Football Lover" shirt model to help the Football Association of Thailand pay off the debts it is carrying.

Risk of a hot spot arising from taxi monopoly at Thai Nguyen bus station

|

Thai Nguyen - The fact that the bus station only allows a taxi company to pick up passengers inside is determined to be not in accordance with regulations, potentially causing a hot spot for order.

Continue to focus on taking care of workers constructing the 500kV Lao Cai - Vinh Yen line

Hà Anh |

The leaders of the Vietnam General Confederation of Labor directly presented gifts and encouraged workers constructing the 500kV Lao Cai - Vinh Yen line.

The Electricity Trade Union presented 228 million VND to workers on the 500kV Lao Cai - Vinh Yen power line

Đắc Cường |

The leaders of the Vietnam Electricity Trade Union encouraged workers constructing the 500kV Lao Cai - Vinh Yen transmission line.

Urgently constructing, striving to energize the 500kV power line on August 19

NHÓM PHÓNG VIÊN |

The 500kV Lao Cai - Vinh Yen transmission line project, nearly 230km long, is entering the final stage, striving to energize on August 19 under the direction of the Prime Minister.