Appearance of Lại Xuân Bridge in Hải Phòng after 18 months of construction.

Mai Dung |

After more than 18 months of construction, to date, the Lại Xuân Bridge project, which connects Hải Phòng to Quảng Ninh, has only achieved 63% of its total volume due to land clearance issues.

Investment project for the construction of Lại Xuân Bridge and the improvement and expansion of Provincial Road 352 connecting Thủy Nguyên District of Haiphong City and Dong Trieu Town of Quang Ninh Province across the Đá Bạch River. The construction period is expected to be from February 2023 to December 2024.
Investment project for the construction of Lại Xuân Bridge and the improvement and expansion of Provincial Road 352 connecting Thủy Nguyên District of Haiphong City and Dong Trieu Town of Quang Ninh Province across the Đá Bạch River. The construction period is expected to be from February 2023 to December 2024.

The total investment for the project is approximately 1.335 billion VND from Haiphong City's budget; Quang Ninh Province will pay for land clearance costs on its territory. The project is expected to improve the capacity to serve transportation, create a regional transportation network, meet the transportation needs between industrial zones, industrial clusters, and serve the travel needs of the people on the territory of Thủy Nguyên District, Dong Trieu Town in particular and Haiphong City, Quang Ninh Province in general. At the same time, the project will gradually complete the transportation network of Haiphong City, Quang Ninh Province, and the North Vietnam key economic region, contributing to the development of the economy, society, and culture of the localities in the project area.
The total investment for the project is approximately 1.335 billion VND from Haiphong City's budget; Quang Ninh Province will pay for land clearance costs on its territory. The project is expected to improve the capacity to serve transportation, create a regional transportation network, meet the transportation needs between industrial zones, industrial clusters, and serve the travel needs of the people on the territory of Thủy Nguyên District, Dong Trieu Town in particular and Haiphong City, Quang Ninh Province in general. At the same time, the project will gradually complete the transportation network of Haiphong City, Quang Ninh Province, and the North Vietnam key economic region, contributing to the development of the economy, society, and culture of the localities in the project area.

bv
According to the report of the Haiphong City's Transportation Infrastructure Investment and Construction Project Management Board, as of August 7, the contractors have completed 104/130 bored piles, are working at 11/16 pier and column locations; are working on suspended beams and super T beams. The estimated volume of work completed is approximately 63% of the contract.

vd
11/16 pier and column locations are currently under construction.
Workers are working enthusiastically under the high-temperature weather of the first days of August with the hope of completing the project on schedule.
Workers are working enthusiastically under the high-temperature weather of the first days of August with the hope of completing the project on schedule. The entire construction site has approximately over 100 workers, working in two shifts per day.
However, the land clearance work of the project still faces many difficulties. Specifically, on the Thủy Nguyên District side of Haiphong City, there is still a remaining area of approximately 9,800 m2 of land to be recovered from Trại giam Xuân Nguyên for the construction of 3 piers. The General Department of Administration and Doanh trại (Ministry of Public Security) is cooperating with the city to resolve related procedures. On the Dong Trieu Town side of Quang Ninh Province, there are still difficulties in clearing land for the construction of 2 piers and the approach road to the bridge on the territory of Yên Đức Commune related to 3 households with land for residential and agricultural purposes. In particular, the land clearance progress in Quang Ninh Province is delayed by many months.
However, the land clearance work of the project still faces many difficulties. Specifically, on the Thủy Nguyên District side of Haiphong City, there is still a remaining area of approximately 9,800 m2 of land to be recovered from Trại giam Xuân Nguyên for the construction of 3 piers. The General Department of Administration and Doanh trại (Ministry of Public Security) is cooperating with the city to resolve related procedures. On the Dong Trieu Town side of Quang Ninh Province, there are still difficulties in clearing land for the construction of 2 piers and the approach road to the bridge on the territory of Yên Đức Commune related to 3 households with land for residential and agricultural purposes. In particular, the land clearance progress in Quang Ninh Province is delayed by many months.

Regarding the construction of Provincial Road 352, currently, the contractors are working on expanding the road and drainage system. The completed volume is approximately 42% of the contract value. On the entire Provincial Road 352, there is still 1 household with land for residential purposes in Quảng Thanh Commune that has not yet handed over the land for construction, and in Thiên Hương Commune, there are 24 households with land for residential purposes that have received compensation but the progress of handing over the land to the contractor is slow due to the cutting and dismantling of... Photo: Đàm Thanh
Regarding the construction of Provincial Road 352, currently, the contractors are working on expanding the road and drainage system. The completed volume is approximately 42% of the contract value. On the entire Provincial Road 352, there is still 1 household with land for residential purposes in Quảng Thanh Commune that has not yet handed over the land for construction, and in Thiên Hương Commune, there are 24 households with land for residential purposes that have received compensation but the progress of handing over the land to the contractor is slow due to the cutting and dismantling of... Photo: Đàm Thanh

dgv
At a recent on-site inspection, Haiphong City's Vice Chairman Nguyễn Đức Thọ requested the relevant units to urgently complete the procedures for land recovery and land allocation, temporarily handing over the land to serve the construction of piers and bridge abutments for Lại Xuân Bridge. For the Provincial Road 352 improvement and expansion project, Vice Chairman Thọ requested the contractors to complete the concrete paving on the road before August 30, complete the sidewalk before September 30, and the lighting system in October 2024... During the construction process, they must comply with environmental sanitation regulations and ensure traffic safety... Photo: Đàm Thanh
Mai Dung
TIN LIÊN QUAN

Hàng nghìn người Hải Phòng dự đêm hội Hoa đăng mùa Vu Lan

Mai Chi |

“Đêm hội Hoa Đăng kính mừng Mùa Vu lan báo hiếu” do Thành hội Phật giáo phối hợp với Thành đoàn Hải Phòng tổ chức thu hút hàng nghìn người dân tham dự.

Tiến độ thi công cầu hơn 1.300 tỉ nối Hải Phòng-Quảng Ninh

Hà Vi |

Đến thời điểm hiện tại, dự án đầu tư xây dựng cầu Lại Xuân nối Hải Phòng - Quảng Ninh đạt khoảng 63% giá trị hợp đồng, dự kiến hoàn thành trong năm 2024.

Hơn 300 tỉ đồng mở rộng tuyến đường khu du lịch ở Hải Phòng

Mai Dung |

TP.Hải Phòng vừa có quyết định chủ trương đầu tư Dự án mở rộng tuyến đường Lý Thái Tổ tại Khu I Đồ Sơn và phát triển vùng phụ cận.

Lần đầu thiết lập cầu vận chuyển miễn phí hàng cứu trợ bão lũ

phóng viên |

Lần đầu thiết lập cầu vận chuyển miễn phí hàng cứu trợ bão lũ.

Bão số 3 ảnh hưởng thế nào đến đường dây 500kV

Anh Tuấn |

Tập đoàn Điện lực Việt Nam cho biết, bão số 3 (Yagi) đã gây ra một số sự cố lưới điện 500kV, tập trung chủ yếu ở Quảng Ninh, Hải Phòng.

Vờ mua vàng rồi mang vàng bỏ chạy, tên cướp bị bắt sau 3 giờ

DUY TUẤN |

Bình Thuận – Tên cướp đến tiệm vàng giả vờ mua vàng rồi mang theo vàng bỏ chạy. Công an đã bắt giữ đối tượng sau 3 giờ truy xét.

"Check VAR" lòi hồ sơ phông bạt những người làm màu

Tiến Nguyễn |

Sau công bố sao kê tiền ủng hộ của Ủy ban Mặt trận Tổ quốc (MTTQ) Việt Nam, cộng đồng mạng đã "check VAR", từ đó lòi hồ sơ những người thích làm màu.

Thêm 3 người thoát nạn vụ lở núi ở Làng Nủ, Lào Cai

Đinh Đại |

Lực lượng chức năng ghi nhận thêm nhiều người tại thôn Làng Nủ (Bảo Yên, Lào Cai) trở về an toàn.

Thousands of people from Hai Phong attended the Hoa đăng festival during the Vu Lan season.

Mai Chi |

“Mid-Autumn Festival Night of Hoa Đăng to Celebrate Vu Lan Season and Express Filial Piety” organized by the Buddhist Association in collaboration with the Youth Union of Hải Phòng attracted thousands of local residents to attend.

Construction Progress of the Bridge Exceeds VND 1.300 Trillion Connecting Hải Phòng-Quảng Ninh

Hà Vi |

As of the current time, the investment project for the construction of the Lại Xuân Bridge connecting Hải Phòng - Quảng Ninh has reached approximately 63% of the contract value, with a projected completion date in 2024.

Over 3 trillion VND Expands Tourist Road in Hải Phòng

Mai Dung |

Hải Phòng City has recently made a decision on the investment plan for the Expansion Project of Lý Thái Tổ Street in Zone I, Đồ Sơn, and the development of the surrounding area.