Accelerating the construction of the nearly 200 billion VND Cultural and Sports Square in Hue
PHÚC ĐẠT - NGUYỄN LUÂN |
HUE - The key project of Hue City is being urgently constructed after a period of delay, aiming to complete before the National Day on September 2.
The Hue City Cultural and Sports Square project is being implemented on the land of the old Thua Thien Hue Provincial Sports Center, in Xuan Phu Ward, now Vy Da Ward after the merger.With a central location, adjacent to important traffic routes such as Ha Huy Tap, To Huu, Ly Tu Trong and Bui San, the project is expected to become a new highlight of the modern public space of Hue City.The project started in July 2024, with the initial goal of completion in March 2025. However, unfavorable weather at the end of 2024 and problems in the relocation of the old Provincial Sports Center have affected the progress.According to the reporter of Lao Dong Newspaper, excavators and bulldozers are currently busy leveling the soil and rocks of the old construction site, creating a clean site for the construction of the square.Many areas have completed stone paving and dividing the path, just waiting to be used.The tree system has been basically planted, and stone materials are "lined up" waiting to gather the foundation.Inside the corrugated iron area, the campus is being dug up and poured with reinforced concrete and is still in disarray, which may take a long time to complete.The site has not been completed and handed over, causing many items to stagnate. In that situation, the investor has submitted a document to the Hue City People's Committee requesting an adjustment to the progress, with the new goal of completing the project before the National Day on September 2.Currently, tasks such as renovating technical infrastructure, leveling, and paving stone are being implemented. The lighting system is also being installed, workers and machinery are operating urgently.The representative of the Project Management Board affirmed that they will continue to urge and direct strongly to ensure progress according to the extended time frame.
The Hue City Cultural and Sports Square project has a total investment of nearly 200 billion VND, the construction cost alone has exceeded 156 billion VND. The Hue City People's Committee approved and assigned the Hue Urban Development and Investment Project Management Board as the investor.
This unit coordinated to implement with a consortium of contractors including: Thua Thien Hue Irrigation Construction Joint Stock Company, Thanh An Joint Stock Company and An Bao Construction and Trading Joint Stock Company.
According to the design, the total square area is more than 7 hectares, divided into 3 main functional subdivisions: public works, green areas and road yard system, parking lot with electricity, water, lighting technical infrastructure.
The area of the stadium has also been increased from over 11,900m2 to 19,500m2, with an additional grandstand of 720m2. After completion, it can accommodate about 4,000 people in the stadium and up to 10,000 people at the outdoor campus.
Public opinion needs Hue University to answer whether Ms. Le Thi An Hoa's 12-page doctoral thesis accused of plagiarism violates academic integrity or not?
HUE - The review council of Ms. Le Thi An Hoa's thesis recorded many errors, 1/6 members said that it would not meet the requirements if the plagiarism section was removed.
Lam Dong - Recklessly overtaking while National Highway 20 was congested, a passenger bus crashed head-on into a motorbike, causing an 11th grade male student in Ward 3, Bao Loc to die on the spot.
Quang Tri - The smugglers are sophisticated, finding every way to smuggle smuggled and banned goods from the border area into the inland for consumption.
Public opinion needs Hue University to answer whether Ms. Le Thi An Hoa's 12-page doctoral thesis accused of plagiarism violates academic integrity or not?
HUE - The review council of Ms. Le Thi An Hoa's thesis recorded many errors, 1/6 members said that it would not meet the requirements if the plagiarism section was removed.