Panorama of raising the steel roof of Long Thanh airport terminal weighing 5,300 tons using a pull-up and push-up solution

HÀ ANH CHIẾN (Ảnh, video: Tổng Công ty Cảng hàng không Việt Nam (ACV) cung cấp) |

Dong Nai - The steel roof of the Long Thanh airport passenger terminal weighing 5,300 tons was successfully lifted with a towing and pushing solution using a hydraulic shock system.

h1
On April 4, in Dong Nai, Vietur consortium, contractor of package 5.10 "Construction and installation of equipment for passenger terminal works", steel structure member ATAD coordinated with subcontractor VSL to successfully upgrade the steel roof structure of Long Thanh International Airport (abbreviated as Long Thanh airport) by combining the solution of pulling and pushing with the hydraulic shock system (Lifting) after more than 8 days, ensuring accuracy, quality, and safety.
h2
The total weight of the steel roof is up to more than 5,300 tons, assembled from 256 connection points, meeting European control standards. The roof has a curved arch structure with an area of nearly 20,000 m2, including a cantilever (cantilever) up to 41 m long that emerges. The entire giant structure is powered by 56 specialized hydraulic shock devices, each of which can withstand a load of 40 to 330 tons, helping to ensure a safe and accurate installation process.
h3
According to the Vietnam Airport Corporation (ACV), the successful increase in the steel structure system of the passenger terminal is an important milestone in the construction progress of Long Thanh Airport project, as concluded by the Ministry of Construction: "To ensure the progress of the passenger terminal, the steel structure of the station center is extremely important, deciding on the progress of the whole project. This is also a symbol of technical progress in Vietnam's construction industry, proving the management capacity of the Long Thanh Airport Project Management Board as well as the technical level of the Vietnamese engineer team not inferior to advanced countries in the world.
h4
The roof system is divided into many large modules for assembly underground, then lifted. Each modular must be assembled accurately, ensuring no deformation when under pressure during the lifting process. The roof has a curved, wavy structure, with many layers stacked, simulating lotus petals, requiring detailed 3D modeling and accurate calculation to ensure consistency with the overall architecture. This not only requires high aesthetics but also meets the strict technical requirements of an international airport that meets 4F standards according to the International Aviation Organization (ICAO).
h5
The technical research, design and preparation of solutions were carried out by the Long Thanh Airport Project Management Board together with the Vietur - ATAD consortium of engineers throughout the 12 months before the construction.
h6
Passenger terminal is the most important category at Long Thanh Airport Construction Project. Currently, the station has completed the reinforced concrete structure of the underground part and floors (4 floors), which is installing steel structure, glass wall surface, station equipment; At the end of December 2025, the passenger terminal will basically complete the construction component.
h7
The Long Thanh airport construction project is simultaneously implementing bidding packages, in which the runway and connecting traffic route (route T1) will be completed and technically exploited by the end of April 2025, 3 months ahead of schedule. Bidding packages such as: garages, aircraft fuel supply systems, and inland transport are being accelerated, basically completed by the end of this year - 2025.
h8
Mr. Duong Quang Dien - Permanent Deputy Director of the Long Thanh Airport Project Management Board said: "In 2025, we are determined to basically complete the construction work of the Long Thanh Airport Project Phase 1".
h9
According to ACV, on the construction site, construction units have mobilized hundreds of construction stitches with nearly 10,000 experts, engineers, workers, workers and nearly 3,000 construction equipment to accelerate the construction progress with the basic goal of completing the construction component before December 31, 2025 to welcome the 11th National Delegation Congress of the Party; Celebrating the 80th anniversary of the National Day of the Socialist Republic of Vietnam; The 50th anniversary of the complete liberation of the South and the reunification of the country.
The clip records the process of successfully raising the steel roof structure of the Long Thanh International Airport's central passenger terminal.

HÀ ANH CHIẾN (Ảnh, video: Tổng Công ty Cảng hàng không Việt Nam (ACV) cung cấp)
TIN LIÊN QUAN

Successfully raising the 5,300-ton steel roof to the roof of Long Thanh airport terminal

|

Dong Nai - The steel roof structure of the central passenger terminal of Long Thanh airport with a weight of 5,330 tons has been successfully raised to the top.

Prime Minister gives lucky money to workers constructing Long Thanh airport

|

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.

Close-up of the road collapsed and a large frog's jaw appeared in Can Tho

|

Can Tho - The Mat Cat canal road in Cai Rang district has many cracks, large subsidence and frog jaw making it difficult for people to travel.

The Bach Mai Hospital project, Viet Duc facility 2, is behind schedule due to a culprit with the people

|

The Permanent Deputy Prime Minister requested to overcome the shortcomings to continue investing; put the Bach Mai Hospital project, Viet Duc Hospital 2, facility 2 into operation by the end of this year.

HCMC plans to end the operation of Thu Duc City, 16 districts and 5 counties

|

Ho Chi Minh City - Thu Duc City and 16 districts and 5 towns are expected to end operations from July 1, 2025.

Adding more than VND4,000 billion to the Ministry of Health to settle epidemic relief

|

The Government has added VND4,327 billion to the 2025 budget estimate, of which the Ministry of Health has nearly VND4,081 billion to settle epidemic relief.

Current status of nearly 4,000m2 of agricultural land about to be reclaimed to expand the Capital Youth Park

|

Hanoi Hai Ba Trung District is preparing to implement a plan to reclaim nearly 4,000m2 of agricultural land to serve the project to build and expand the Capital Youth Park.

Organizing many bidding rounds but for many consecutive years only one winning contractor

|

National Assembly deputies cited that in the past, in some places, there was only one contractor who had won the bidding for dozens of projects in several consecutive years.

Successfully raising the 5,300-ton steel roof to the roof of Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - The steel roof structure of the central passenger terminal of Long Thanh airport with a weight of 5,330 tons has been successfully raised to the top.

Đồng Nai giải phóng mặt bằng 3 đường nối sân bay Long Thành

HÀ ANH CHIẾN |

Đồng Nai yêu cầu 6 huyện, thành phố khẩn trương giải phóng mặt bằng 3 dự án đường ĐT 770B, đường ĐT 773, đường ĐT 769 kết nối sân bay Long Thành.

Prime Minister gives lucky money to workers constructing Long Thanh airport

HÀ ANH CHIẾN - NHƯ QUỲNH |

Dong Nai – Prime Minister Pham Minh Chinh wished a happy new year, gave gifts and lucky money to officials, engineers and workers who are working during Tet at Long Thanh airport.