Quang Trung Software Park solves public land waste

Huân Cao |

HCMC - Quang Trung Software Park Development One Member Co., Ltd. (QTSC) has found a solution to the waste of public land as reported by Lao Dong Newspaper.

According to QTSC, Quang Trung Software Park (QTSC) has a total planned land area of ​​43.25 hectares, divided into 52 functional lots, including 5 lots of technical infrastructure land, parks, parking lots, fuel stations and 47 lots planned according to functional subdivisions such as office buildings for software production, information technology services, training; conference exhibitions, entertainment, restaurants; accommodation for experts, dormitories.

Up to now, the land rental rate in QTSC Area is about 87%.

Cong trinh nay nam ngay goc duong To Ky va Dong Bac, duoc vi la vi tri vang tai QTSC nhung da bo hoang hang chuc nam. Anh: Huan Cao
This project is located at the corner of To Ky and Dong Bac streets in Quang Trung Software Park, considered a prime location in QTSC but has been abandoned for decades. Photo: Huan Cao

Regarding the building at the corner of To Ky and Dong Bac streets, which was stopped after construction reached the 5th floor and abandoned since 2004, QTSC said that it has sent many documents requesting the investor to continue construction of the project to avoid waste. Most recently, on September 23, 2024, QTSC sent a document reminding the investor, V.Life Company Limited, about the project's investment progress. On October 2, 2024, V.Life Company Limited responded in writing, expecting to restart the project in the first quarter of 2025.

Regarding the issue of many plots of land in the QTSC Area that have not been built or have had their foundations built and then left abandoned for many years, causing waste, QTSC said that for the project that has had its foundations built and stopped construction since 2007 until now, in Lot 18, QTSC has also sent many documents reminding the investor about the delay in completing the project.

On July 31, 2024, District 12 Judgment Enforcement Office handed over the property Lot No. 18 to the auction winner, Van Thanh An Technology Investment and Development Joint Stock Company.

Currently, Van Thanh An Company has completed the procedures for registering changes in land use rights and is carrying out procedures to adjust the construction permit according to regulations to implement construction investment projects.

Regarding the remaining vacant land plots that have not been implemented, QTSC said that they are waiting for the adjustment of the QTSC Area planning. Currently, QTSC has reviewed the report and evaluated the project to adjust the detailed urban construction planning at a scale of 1/500 of the QTSC Area according to regulations and sent it to the Department of Planning and Architecture to report to the Ho Chi Minh City People's Committee.

Mot cong trinh xay xong phan mong roi bo hoang hang chuc nam gay lang phi. Anh: Huan Cao
A building with its foundation completed and then abandoned for many years is a waste. Photo: Huan Cao

Regarding the issue of land use for the wrong purpose, illegal sale and profiteering by investors such as Van Trung Company Limited, Hong Minh Duc Company Limited, Lien Phuong Company Limited, QTSC said that after Lao Dong Newspaper reported the incident, QTSC sent a document to the Ho Chi Minh City People's Committee. The Ho Chi Minh City People's Committee assigned the Department of Construction to preside over the inspection and review of cases of transfer, sale, and lease of houses and land to the wrong subjects and purposes of use in the QTSC Area.

At the same time, QTSC coordinates with relevant departments to conduct inspections and handle construction investment activities in QTSC Area, report and advise the Ho Chi Minh City People's Committee to issue decisions on administrative sanctions against investors with violations as reported by Lao Dong Newspaper.

Huân Cao
RELATED NEWS

Expectations when expanding Quang Trung Software Park

|

The construction of Quang Trung Software Park in Thu Duc City plays a very important role in the digital transformation of Ho Chi Minh City, with many major goals set by 2030.

Party cell secretary persistently educates revolutionary traditions for the younger generation

|

Ở độ tuổi ngoài 80, Bí thư chi bộ Lâm Văn Bảng vẫn bền bỉ lan tỏa giá trị lịch sử, góp phần bồi dưỡng lý tưởng và niềm tin cách mạng cho thế hệ trẻ.

Lao Dong Newspaper contributes to encouraging officers and soldiers to feel secure in their work

|

In 2025, Lao Dong Newspaper encouraged and motivated officers and soldiers of the Army in general and the Border Guard in particular to successfully complete their assigned tasks.

Gold prices continue to decline, many stores temporarily stop selling

|

Ngày 2.2, giá vàng trong nước tiếp đà giảm sâu. Lượng khách giao dịch vàng tấp nập nhưng cửa hàng đưa ra thông báo bất ngờ.

Blue license plate car driver explains about license plate stained with mud

|

When handling the illegal parking of a blue license plate car, functional forces also requested the driver to explain because the license plate was covered with mud and soil.

Expectations when expanding Quang Trung Software Park

NGUYỄN ĐĂNG |

The construction of Quang Trung Software Park in Thu Duc City plays a very important role in the digital transformation of Ho Chi Minh City, with many major goals set by 2030.

Vì sao mất điện tại Công viên Phần mềm Quang Trung vào ngày 5.7?

Nam Dương |

Chiều 7.7, Tổng Công ty Điện lực TP Hồ Chí Minh (EVNHCMC) đã có thông cáo báo chí về sự cố gây mất điện khoảng 28 phút tại Công viên phần mềm Quang Trung vào ngày 5.7.

Vụ trục lợi đất công tại Công viên Phần mềm Quang Trung: Sẽ xử lý dứt điểm

Huân Duy |

Liên quan đến tuyến bài điều tra "Trục lợi đất công tại công viên Phần mềm Quang Trung", Sở Xây dựng TPHCM cho biết, vụ việc đang được tiếp tục xử lý sai phạm dứt điểm theo chỉ đạo của lãnh đạo UBND TPHCM.