Removing obstacles in the migration out of Hue Citadel

ĐẠT LUÂN |

HUE - The project to relocate people out of Hue Citadel is being removed from land difficulties, as many households have not yet moved because of many reasons.

Focus on site clearance

The project to relocate residents and clear ground in area 1 of Hue Citadel has helped thousands of households leave their cramped houses close to the foot of the citadel, Eo Bau, and Ho Thanh Hao to move to new, more spacious residences.

After many years of implementation, the appearance of the Hue Citadel area has changed a lot. Many relic spaces that were once obscured by people's houses are gradually being returned.

However, the journey to complete site clearance work still faces many difficulties when there are still cases of problems related to compensation policies, legal documents on land and houses, resettlement benefits for auxiliary households or cases with complex historical factors.

Bên cạnh những nhà dân đã chuyển đi vẫn còn nhiều hộ vẫn đang ở lại, chưa bàn giao mặt bằng cho dự án. Ảnh: Nguyễn Luân
Besides the houses that people have moved out, there are still many households staying, not yet handing over land for the project. Photo: Nguyen Luan

According to the Project Management Board for Construction Investment Area 1 of Hue City, most of the remaining cases are complex dossiers, prolonged over many periods, related to state-owned houses, public assets, land origin disputes or cases of land transfer and use with many factors that need to be further verified.

In addition, some households have not agreed with the compensation and support plan or still have concerns about the arrangement of resettlement, especially cases of auxiliary households with specific circumstances.

According to the Project Management Board for Construction Investment Area 1 of Hue City, phase 1 of the project has a scope of implementation in 11 areas, with a total area of about 25.5ha, with 2,233 households to be relocated.

Nhiều công trình chưa thể tháo dỡ vì nằm cạnh nhà dân chưa di dời. Ảnh: Phúc Đạt
Many works cannot be dismantled because they are located next to people's houses that have not been relocated. Photo: Phuc Dat

To date, functional agencies have approved compensation, support and resettlement plans reaching a rate of over 99%. The total value approved reached about 1,902 billion VND out of a total capital of 1,905 billion VND. However, according to statistics by the end of April 2026, only about 1,756 households handed over land, reaching a rate of 78.6%; nearly 500 households have not yet handed over.

Despite many difficulties, local functional agencies are still continuing to review each dossier, coordinating with departments and branches to remove obstacles with the spirit of ensuring legitimate rights for people, and at the same time meeting the progress requirements of the project to preserve and promote the value of Hue Citadel heritage.

Need to ensure the rights of the people

Recorded by Lao Dong Newspaper reporters in the Xa Tac altar area, besides the houses that have been dismantled, many other houses are still inhabited by people. The unsynchronized clearance has made some areas become messy, with vacant land interspersed with houses and construction waste scattered, affecting the aesthetics of the relic area.

Công tác giải phóng mặt bằng tại khu vực đàn Xã Tắc vẫn còn dang dở. Ảnh: Nguyễn Luân
Site clearance work in the Xa Tac altar area is still unfinished. Photo: Nguyen Luan

Ms. Nguyen Thi Be (67 years old, living in Xa Tac collective area) said that she completely agreed with the policy of relocation to serve relic conservation work. However, what worries her is that after receiving compensation and paying land use fees at the resettlement area, the remaining funds are not enough to build a new stable house.

We really hope the project will be completed soon, but we also hope that functional agencies will consider more difficult cases so that people have conditions to stabilize their lives in new places of residence" - Ms. Be said.

Căn nhà của bà Nguyễn Thị Bé nằm đối diện di tích đàn Xã Tắc. Ảnh: Phúc Đạt
Ms. Nguyen Thi Be's house is located opposite the Xa Tac altar relic. Photo: Phuc Dat

Similarly, Ms. Le Thi Minh Hai (64 years old) said that her family of many generations lives together, while the cost of building a new house is a heavy burden after completing the expenses related to resettlement land.

According to Ms. Hai, the family does not object to the relocation policy but only hopes that functional agencies will consider the actual conditions of each household to have appropriate support plans to help people feel secure in moving to a new place.

According to the Project Management Board for Construction Investment Area 1 of Hue City, in the coming time, functional units will continue to strengthen propaganda and mobilize the remaining households to comply with the relocation policy, and at the same time complete dossiers to implement coercion for cases that meet the conditions according to regulations but still do not hand over land.

ĐẠT LUÂN
RELATED NEWS

Vinh Long Party Secretary directs to remove obstacles for key irrigation projects

|

Vinh Long - Provincial Party Secretary Tran Van Lau requested to remove obstacles, accelerate site clearance, and ensure the progress of key irrigation projects.

Removing bottlenecks for sustainable marine exploitation

|

The amendment of the Law on Marine and Island Resources and Environment is expected to remove institutional bottlenecks and move towards sustainable marine economic development.

Removing bottlenecks at key traffic projects in Quang Tri

|

Quang Tri - Land is the biggest bottleneck affecting the progress of key transport projects, forcing localities to continuously direct removal.

People rescue goods to help drivers reduce damage after collision

|

Lam Dong - Many people in Lien Huong commune have joined hands to collect and buy goods to help drivers reduce damage after collisions.

Removing obstacles in the migration out of Hue Citadel

|

HUE - The project to relocate people out of Hue Citadel is being removed from land difficulties, as many households have not yet moved because of many reasons.

Waste treatment plant stops operating, wards in Da Lat flooded with domestic waste

|

Lam Dong - After 3 days of collection interruption due to the treatment plant stopping operation, waste in the center of Da Lat is congested, smelly, causing serious pollution.

Vinh Long Party Secretary directs to remove obstacles for key irrigation projects

HOÀNG LỘC |

Vinh Long - Provincial Party Secretary Tran Van Lau requested to remove obstacles, accelerate site clearance, and ensure the progress of key irrigation projects.

Removing bottlenecks for sustainable marine exploitation

Linh Chi - Dương Anh |

The amendment of the Law on Marine and Island Resources and Environment is expected to remove institutional bottlenecks and move towards sustainable marine economic development.

Removing bottlenecks at key traffic projects in Quang Tri

THƠ LUÂN |

Quang Tri - Land is the biggest bottleneck affecting the progress of key transport projects, forcing localities to continuously direct removal.