The tidal barrier project is immobile, who will pay the interest of 1.7 billion VND/day?

Lê Thanh Phong |

Among the projects that have caused waste due to being "shelved", the most infuriating is the tidal dam project in Ho Chi Minh City.

Because the nearly 10,000 billion VND flood prevention project has completed 93% of the volume, but has been "shelved" for many years, causing daily interest to be more than 1.7 billion VND.

The project has been suspended 3 times in the past 8 years, the most recent suspension lasting from November 15, 2020 to present (about 48 months). When operations are suspended, costs arise, including bank loan interest. With a daily payment of more than 1.7 billion VND, along with other costs, the total investment of the project has increased to more than 14,000 billion VND. Of course, it must be completed by the end of 2025, but if it is extended, it is not known how much it will be.

Thus, the shelving scenario resulted in capital increase, just like many other projects. The flood prevention project with an initial total investment of 10,000 billion VND has increased by 4,000 billion VND.

That figure is not yet satisfactory, because according to the investor, if the investment adjustment procedures are not carried out soon, after the capital source is resolved, the project completion time may take another 28 months (including 12 months for handling procedures, 4 months for negotiating contract appendices and 12 months for the remaining construction). With each passing day, the interest payable increases, expected to generate an additional 845 billion VND for 16 months of procedures.

The question is why can't the procedures be shortened, why does it take 12 months to process and not a few months or half that time. Why does it take 4 months to negotiate a contract and not 1 month?

Procedures are set by humans, humans can proactively change or flexibly shorten them. If you are determined to do it, you will definitely do it.

Here, shortening the time is not only saving hundreds of billions, thousands of billions of dong, but also putting the project into operation soon, which will bring many benefits to the people and society.

A flood season, the damage to people is difficult to calculate, that is what individuals and responsible agencies pay attention to in order to shorten the time.

The interest payments and the additional costs of several thousand billion VND are included in the total investment of the project and the city government must bear them. After all, it is the people's tax money, not anyone else's.

Therefore, we must find every way to resolve the problems and complete the project as soon as possible, it cannot be delayed any longer.

Lê Thanh Phong
TIN LIÊN QUAN

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

|

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

The nearly 10,000 billion VND tide prevention project is an example of waste

|

The nearly 10,000 billion VND super project to prevent tides in Ho Chi Minh City has become a typical example of waste and stagnation in public investment management.

Ho Chi Minh City requests review of Cambridge International certificates

|

Ho Chi Minh City People's Committee requires units to inspect and review officials who have declared the use of foreign language certificates named "Cambridge International".

SPT Company must pay nearly 500 million VND after tax inspection

|

Thanh Hoa Provincial Tax Department has requested SPT Architecture Joint Stock Company to pay nearly 500 million VND due to incorrect tax declaration.

Tens of thousands of people flock to watch the Ngo boat racing festival in Soc Trang

|

Mekong Delta - From November 14-15, 60 boat teams from provinces and cities in the Mekong Delta will compete in the Ngo Boat Race with fierce and exciting matches.

My Boss Expressed His Love Even Though He Knew I Was Getting Married (Part 1)

|

Hour 9 - The female employee is expressed her feelings by her manager when she is about to get married. What will this girl decide?

8pm News: Merging many wards in 6 central districts of Hanoi

|

News at 8pm on November 14: Hanoi merged many wards in 6 central districts; Arrested and took statements from singer Chi Dan, model An Tay...

Construction is in full swing at the two blocks of the Bac Lieu Three-Conical Hat Theater

|

Bac Lieu - The construction unit is working overtime to open the interior exhibition project of the provincial museum in December 2024.

Dự án ngăn triều nằm im, lãi vay phát sinh 1,7 tỉ đồng mỗi ngày

MINH QUÂN |

Là một trong những dự án bị Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính điểm tên, dự án chống ngập do triều cường gần 10.000 tỉ đồng tại TPHCM dù đạt 93% khối lượng, nhưng lại "đắp chiếu" nhiều năm, khiến lãi vay phát sinh hằng ngày hơn 1,7 tỉ đồng.

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

MINH QUÂN |

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

The nearly 10,000 billion VND tide prevention project is an example of waste

Hoàng Văn Minh |

The nearly 10,000 billion VND super project to prevent tides in Ho Chi Minh City has become a typical example of waste and stagnation in public investment management.