The tidal barrier project is immobile, who will pay the interest of 1.7 billion VND/day?

Lê Thanh Phong |

Among the projects that have caused waste due to being "shelved", the most infuriating is the tidal dam project in Ho Chi Minh City.

Because the nearly 10,000 billion VND flood prevention project has completed 93% of the volume, but has been "shelved" for many years, causing daily interest to be more than 1.7 billion VND.

The project has been suspended 3 times in the past 8 years, the most recent suspension lasting from November 15, 2020 to present (about 48 months). When operations are suspended, costs arise, including bank loan interest. With a daily payment of more than 1.7 billion VND, along with other costs, the total investment of the project has increased to more than 14,000 billion VND. Of course, it must be completed by the end of 2025, but if it is extended, it is not known how much it will be.

Thus, the shelving scenario resulted in capital increase, just like many other projects. The flood prevention project with an initial total investment of 10,000 billion VND has increased by 4,000 billion VND.

That figure is not yet satisfactory, because according to the investor, if the investment adjustment procedures are not carried out soon, after the capital source is resolved, the project completion time may take another 28 months (including 12 months for handling procedures, 4 months for negotiating contract appendices and 12 months for the remaining construction). With each passing day, the interest payable increases, expected to generate an additional 845 billion VND for 16 months of procedures.

The question is why can't the procedures be shortened, why does it take 12 months to process and not a few months or half that time. Why does it take 4 months to negotiate a contract and not 1 month?

Procedures are set by humans, humans can proactively change or flexibly shorten them. If you are determined to do it, you will definitely do it.

Here, shortening the time is not only saving hundreds of billions, thousands of billions of dong, but also putting the project into operation soon, which will bring many benefits to the people and society.

A flood season, the damage to people is difficult to calculate, that is what individuals and responsible agencies pay attention to in order to shorten the time.

The interest payments and the additional costs of several thousand billion VND are included in the total investment of the project and the city government must bear them. After all, it is the people's tax money, not anyone else's.

Therefore, we must find every way to resolve the problems and complete the project as soon as possible, it cannot be delayed any longer.

Lê Thanh Phong
RELATED NEWS

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

|

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

The nearly 10,000 billion VND tide prevention project is an example of waste

|

The nearly 10,000 billion VND super project to prevent tides in Ho Chi Minh City has become a typical example of waste and stagnation in public investment management.

Cold air strengthens, forecast for rain in the area on January 3-4.1

|

It is forecasted that the south of the North Central region will have rain, showers, locally moderate rain, heavy rain and thunderstorms on January 3 - 4 due to the impact of cold air.

After a New Year's Eve drinking party, a series of drivers violated the maximum alcohol concentration limit

|

Hanoi - Many drivers believe that they have been drinking alcohol since last night, drinking little, but the measurement results show that the alcohol concentration is very high.

Tan Beo's family responds to the case of not inviting Tan Bo to his grandson's wedding

|

According to the reporter's investigation, it is true that artist Tan Beo's family did not invite Tan Bo to Tan Loc's wedding ceremony, but there is a deep reason.

Vietnamese organ transplants mark the world medical map

|

From multiple organ transplants to the first heart-lung transplant, 2025 marked a strong breakthrough for Vietnamese organ transplantation on the world medical map.

Hanoi is about to recover land to build Ring Road 3.5, Provincial Road 70

|

Hanoi - In 2026, Dai Thanh commune will deploy land acquisition and site clearance to deploy the construction of Ring Road 3.5 and Provincial Road 70.

Ministry of Education and Training refutes information distorting the content of History - Geography textbooks

|

The Ministry of Education and Training warns of false and distorted information related to the content in the History - Geography textbook of grade 5 (set "Connecting Knowledge with Life").

Dự án ngăn triều nằm im, lãi vay phát sinh 1,7 tỉ đồng mỗi ngày

MINH QUÂN |

Là một trong những dự án bị Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính điểm tên, dự án chống ngập do triều cường gần 10.000 tỉ đồng tại TPHCM dù đạt 93% khối lượng, nhưng lại "đắp chiếu" nhiều năm, khiến lãi vay phát sinh hằng ngày hơn 1,7 tỉ đồng.

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

MINH QUÂN |

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

The nearly 10,000 billion VND tide prevention project is an example of waste

Hoàng Văn Minh |

The nearly 10,000 billion VND super project to prevent tides in Ho Chi Minh City has become a typical example of waste and stagnation in public investment management.