500kV Lao Cai - Vinh Yen line

Looking back at the 500kV Lao Cai - Vinh Yen transmission line project after 7 months of construction

|

The 500kV Lao Cai - Vinh Yen transmission line project started on March 3, 2025 and was inaugurated on the morning of October 17, 2025, 8 months ahead of schedule.

Lao Cai - Vinh Yen 500kV Power Line Project Powered 8 Months Ahead of schedule

|

The Lao Cai - Vinh Yen 500kV Power Line project has officially been successfully energized, 8 months ahead of schedule.

Another contractor to destroy forests to construct the 500kV Lao Cai - Vinh Yen line was fined

|

Lao Cai - The People's Committee of Thac Ba commune has just fined Dien 2 Construction and Installation Company Limited for destroying forests to construct the 500kV Lao Cai - Vinh Yen line.

Scene of a 500kV Lao Cai - Vinh Yen power line pole falling, killing one person

|

Lao Cai - Workers are urgently dismantling and relocating the power pole to prepare for the resumption of construction of pole 129 of the 500kV Lao Cai - Vinh Yen transmission line project.

crossing mountains and forests to connect the 500kV Lao Cai - Vinh Yen transmission line

|

During the holidays, thousands of workers are still working hard to erect poles and pull ropes to soon open the entire 500kV Lao Cai - Vinh Yen route.

Close-up of the 500kV Lao Cai - Vinh Yen route

|

In the last days at the construction site of the 500kV Lao Cai - Vinh Yen route, workers took advantage of favorable weather to pull the lines and clear the entire route.

Forests, mountains, and mountains will be built towers for the 500kV Lao Cai - Vinh Yen power line

|

To transport steel, cables, and electric poles to the foundation and erect poles for the 500kV Lao Cai - Vinh Yen line, trucks had to move each section over the slope.

Consolidating temporary roads for construction of the 500kV Lao Cai - Vinh Yen transmission line project

|

Yen Bai - The interspersed soil and rock caused many obstacles in the construction of the 500kV Lao Cai - Vinh Yen transmission line project through Luc Yen district.

Overnight on the difficult terrain of the Lao Cai - Vinh Yen 500kV transmission line project

|

regardless of day or night, thousands of workers and technical staff are still working hard to ensure the Lao Cai - Vinh Yen 500kV transmission line project reaches the finish line on schedule.

Vietnam Electricity Trade Union encourages workers at key national projects

|

On April 27, the Vietnam Electricity Trade Union visited units constructing the 500kV Lao Cai - Vinh Yen transmission line, this is a national key project.

Accelerating site clearance for the 500kV Lao Cai - Vinh Yen transmission line

|

To remove difficulties and obstacles in site clearance for the Lao Cai - Vinh Yen 500kV Line project, the localities where the project passes through are urgently implementing site clearance work, ensuring construction progress according to the direction of the Government.

Prime Minister attends the groundbreaking ceremony and launching the emulation of the Lao Cai - Vinh Yen 500kV project

|

On the morning of March 16, Prime Minister Pham Minh Chinh attended the groundbreaking ceremony and launched the emulation campaign to complete the Lao Cai - Vinh Yen 500kV transmission line project.