My Thuy Interchange

The An Phu and My Thuy intersections will be completed in 2026, and the East of Ho Chi Minh City will soon reduce traffic congestion

|

HCMC - The An Phu and My Thuy intersection projects are preparing to complete many important items before reaching the finish line in 2026.

The largest complex intersection in the east of Ho Chi Minh City is gradually taking shape after more than 9 months of construction

|

HCMC - After more than 9 months of construction in phase 3, My Thuy intersection is gradually taking shape, aiming to be put into operation in 2026.

2 major intersections to relieve traffic jams in the East of Ho Chi Minh City are about to open many overpasses and underpasses

|

HCMC - An Phu intersection and My Thuy intersection are required to complete many branches of bridges and underpasses before the Lunar New Year 2026 to reduce traffic congestion in the East.

Barricading 2/3 of My Thuy roundabout to repair road surfaces, increasing risk of congestion

|

HCMC - My Thuy roundabout is blocked 2/3 of the lane to repair damaged road surfaces. Cat Lai Traffic Police recommend that drivers find an alternative route to avoid congestion.

HCMC completes 4-storey intersection project to relieve congestion by 2026

|

HCMC - The My Thuy intersection project with 4 floors is expected to help relieve traffic congestion in the East of HCMC, and will be completed in 2026.

The crane crashing into a vehicle at My Thuy intersection, Ho Chi Minh City Chairman urgently directs

|

HCMC - The Chairman of the HCMC People's Committee directed the establishment of an investigation team for the crane collapse incident at the My Thuy intersection project (Thu Duc City).

The 3,400 billion VND intersection in Ho Chi Minh City has been under construction for 9 years but is still stuck with site clearance

|

HCMC - After nearly 9 years of construction, the My Thuy intersection project worth more than VND3,400 billion is still sluggish due to land clearance problems, with 61 households not yet handed over.

4 key projects to rescue traffic jams in Ho Chi Minh City are delayed due to land clearance problems

|

HCMC - Expanding Hanoi Highway and National Highway 1, My Thuy intersection, An Phu intersection, expanding National Highway 50 are 4 projects to rescue traffic jams but are delayed due to land clearance problems.

The first 4-storey intersection in Ho Chi Minh City still has 72 land clearance problems

|

HCMC - My Thuy intersection has a scale of 4 floors, the first in the city to be implemented since 2016 but has not yet been completed due to land clearance problems, with 72 households not yet handed over.

The billion-dollar intersection in the East of Ho Chi Minh City is expected to be completed in 2026

|

HCMC - After 9 years of construction, the My Thuy intersection project - a project expected to "rescue" traffic congestion in the East of HCMC continues to start construction in phase 3.

HCMC builds 2 more bridges to relieve traffic jams in Thu Duc City

|

HCMC - The My Thuy Intersection Project (Thu Duc City) is implementing phase 3 with the construction of an overpass on Ring Road 2 and Ky Ha 3 Bridge, with a total capital of 312 billion VND.

Current status of the billion-dollar intersection in Ho Chi Minh City has been congested for 9 years due to land clearance

|

HCMC - Construction started in 2016, but the My Thuy intersection (Thu Duc City) has not yet been completed due to land clearance problems.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

|

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

5 key projects worth 24,300 billion VND in Ho Chi Minh City to be completed by 2025

|

HCMC - Tan Son Nhat T3 Terminal, Tran Quoc Hoan - Cong Hoa connecting road, An Phu intersection, My Thuy intersection, and National Highway 50 expansion will be completed in 2025.

The 3-storey, trillion-dong intersection in the East of Ho Chi Minh City has been under construction for 8 years and is not yet completed

|

After 8 years of construction, the My Thuy intersection project - a project expected to "rescue" traffic congestion in the East of Ho Chi Minh City - is only 48% complete, despite an investment of more than 3,600 billion VND.