Project report submitted to National Assembly is all rosy

CAO NGUYÊN |

Delegates recommended that in the pre-feasibility assessment report, subjective and objective causes must be predicted in advance in order to have solutions to overcome project difficulties.

On the morning of November 13, continuing the 8th Session, the National Assembly discussed in groups the investment policy for the high-speed railway project on the North-South axis.

Speaking at the group, delegate Nguyen Van Quan (Hau Giang Delegation) said that the Government's report needs to assess and clarify the limitations and forecast the difficulties when implementing this project.

“In the pre-feasibility report, the impact assessments did not clearly identify the limitations and difficulties, and did not predict the difficulties. The report stipulates some specific policies, but whether they are consistent or not has not been clearly assessed,” said delegate Nguyen Van Quan.

Next are the difficulties in site clearance and technology. “We will carry out this project for 10 years, what will the technology be like at that time? What about capital, capital increase, price, price depreciation, and difficulties in progress?” - this delegate asked.

Another issue in the pre-feasibility report shows that it will be basically completed by 2035. This delegate wondered why the word “basically” was used, it must be affirmed that it is completed, but saying that it is basically completed 10 years later is unacceptable.

Through monitoring key national projects, large projects are almost always behind schedule, have capital increases, time schedules or design adjustments. Long Thanh airport is an example.

“Almost all national key projects are stuck and still have many difficulties. While the project initially submitted its pre-feasibility report and feasibility report, we only saw rosy results.

The Government project report submitted to the National Assembly was all rosy, but when implemented, it was entangled in a series of policy mechanisms, capital, processes, and technology..." - delegate Nguyen Van Quan emphasized.

Therefore, delegates recommend that in pre-feasibility assessment reports, objective and subjective causes must be predicted so that delegates can understand clearly. When difficulties and obstacles are predicted in advance, there will be solutions to overcome them.

"9 out of 10 projects are stuck and facing difficulties such as delays, capital overruns, and project adjustments" - the delegate affirmed.

According to delegate Nguyen Van Quan, during the implementation process, the responsibility of the Ministry of Transport must also be bound.

On the same issue, delegate Nguyen Thi Xuan (Dak Lak delegation) said that if we are determined to implement it, this will be a symbolic project of the century. However, when implementing it, we must calculate the effectiveness of the project. This is an unprecedented project when we first researched and applied high-speed rail technology, so we need to set requirements on technology.

"We must catch up with world trends, be progressive, and not be out of date even in 50 years" - delegate Nguyen Thi Xuan stated.

In the report, the Government presented a very bright future, promising many good prospects when implementing the project. In fact, we have implemented many national key projects such as the North-South Expressway, although the Government has directed strongly, there are still problems with policy mechanisms, investment resources, site clearance, etc., leading to progress impacts.

Therefore, delegates suggested that the Government study and carefully consider choosing contractors and investors, and learn from the experience of some projects where investors were not guaranteed or did not have enough capacity, affecting the progress and quality of the project.

CAO NGUYÊN
RELATED NEWS

It costs 25,000 billion each year to operate and maintain high-speed railways

|

According to the report, from 2036 to 2066, the annual operating and maintenance costs of the North-South high-speed railway project will be over VND25,000 billion.

Malaysian press says Vietnam accuses 7 naturalized players

|

Malaysian newspapers believe that the Asian Football Confederation (AFC) has received a complaint from Vietnam about the status of 7 ineligible naturalized players.

The first Trade Union bus takes Da Nang workers home for Tet

|

Da Nang - On the morning of February 11, the first "Trade Union Buses" officially rolled, taking thousands of Da Nang workers to go home for Tet.

Peach blossoms bloom early, small traders throw away branches exposed on the sidewalk

|

Thanh Hoa - Because some peach trees bloomed early and there were no buyers, small traders cut down branches and left them exposed on the sidewalk.

Factory fire in industrial cluster in Ninh Binh

|

Ninh Binh - A factory under construction at Le Ho Industrial Cluster caught fire fiercely, causing many properties to be burned down.

North Korea reacts toughly to Japan's military move

|

Japan's establishment of close security and defense relations with Canada recently has caused significant concern for North Korea.

Ministry of Health "whistles" for refusing to pay for health insurance when taking X-rays for less than 6 minutes

|

Faced with the situation of scans not being scanned for 6 minutes and being refused payment, the Ministry of Health requested not to use electro-optical techniques as a basis for health insurance assessment.

Dự án bãi đỗ xe tại Hà Nội hơn 10 năm vẫn nằm trên giấy

Nhật Minh |

Hà Nội - Hiện nay, dự án xây dựng bãi đỗ xe dọc bờ sông Tô Lịch tại quận Hoàng Mai (Hà Nội) đang bị bỏ hoang, trở thành nơi đổ trộm rác thải.

It costs 25,000 billion each year to operate and maintain high-speed railways

CAO NGUYÊN |

According to the report, from 2036 to 2066, the annual operating and maintenance costs of the North-South high-speed railway project will be over VND25,000 billion.

Giải phóng mặt bằng bế tắc, dự án cải tạo Quốc lộ 7 nham nhở

QUANG ĐẠI |

Nghệ An – Dự án cải tạo, nâng cấp Quốc lộ 7 sau hơn 2 năm thi công vẫn chưa giải phóng xong mặt bằng, hiện trạng nhiều vị trí dở dang, nham nhở.