Lao Cai Secretary inspects progress of resettlement projects

Đinh Đại |

On November 16, Mr. Dang Xuan Phong - Secretary of Lao Cai Provincial Party Committee - inspected the construction progress of residential area reconstruction projects in Bao Yen and Bac Ha districts.

At Nam Tong village, Nam Luc commune and Kho Vang village, Coc Lau commune (Bac Ha), Lao Cai Provincial Party Secretary Dang Xuan Phong and the working delegation directly inspected the construction site.

Accordingly, Nam Tong village has leveled the ground, built roads, built a water supply dam, and completed the transformer station; 15/15 houses are under construction; kindergarten walls have reached 90%...

For Kho Vang village: Counted, counted, and handed over the construction site; supplied electricity and water to the construction site; dug the foundations of 35/35 houses, and is currently constructing items; the kindergarten has poured concrete gate pillars, and completed drainage ditches...

Cac cong trinh tai Du an tai thiet khu dan cu thon Kho Vang dang duoc day nhanh tien do thi cong. Anh: Lan Huong
Construction works at the Kho Vang residential area reconstruction project are being accelerated. Photo: Lan Huong

After the field inspection, Mr. Dang Xuan Phong requested the local authorities to uphold their sense of responsibility, take advantage of favorable weather, speed up construction progress, and ensure completion on schedule.

In addition, it is necessary to pay attention to thoroughly and reasonably resolving legitimate aspirations and properly, sufficiently and fairly implementing policies for the people.

Bi thu Tinh uy Lao Cai Dang Xuan Phong (phai) tang qua dong vien can bo, ky su, nguoi lao dong thi cong du an. Anh: Lan Huong
Lao Cai Provincial Party Secretary Dang Xuan Phong (right) presents gifts to encourage officers, engineers and workers working on the project. Photo: Lan Huong

Next, the working delegation directly inspected the residential area reconstruction project in Lang Nu village, Phuc Khanh commune, Bao Yen district.

Currently, the floor structure installation for 40/40 houses has been completed; 36/40 houses have walls installed; 30/40 houses have concrete foundations poured...

Nhieu ngoi nha tai Lang Nu da dan hien hinh. Anh: Dinh Dai
Many houses in Lang Nu have gradually taken shape. Photo: Dinh Dai

The school has poured concrete for the foundation, poured concrete for the beam foundation, and erected steel columns. The construction of roads and drainage ditches has completed many items...

Earlier, on the afternoon of November 13, representatives of 33 households were damaged by flash floods chose the new home position. So far, 21 houses have completed the roof, the construction teams are continuing to complete the final items, striving to complete before December 22.

Lao Cai Provincial Party Secretary Dang Xuan Phong emphasized that residential area reconstruction projects are of special importance, demonstrating the Party and State's concern for people affected by natural disasters in Lao Cai province.

Du an cap dien cho Lang Nu se hoan thanh vao cuoi thang 12.2024, nhung voi no luc cua cac nhan vien nganh dien tren cong truong, cong trinh da vuot tien do 45 ngay. Anh: Dinh Dai
The project to supply electricity to Lang Nu village was due to be completed by the end of December 2024, but thanks to the efforts of the electricity workers on site, the project was 45 days ahead of schedule. Photo: Dinh Dai

Mr. Dang Xuan Phong also praised and encouraged the staff, engineers and workers to continue promoting the spirit of "overcoming the sun and overcoming the rain", striving to complete the project on the occasion of the 80th anniversary of the founding of the Vietnam People's Army (December 22, 1944 - December 22, 2024).

As reported by Lao Dong Newspaper, the flash flood in the early morning of September 10 in Lang Nu village, Phuc Khanh commune, Bao Yen district buried 33 households, affected 40 families, killed 60 people, and left 7 people missing.

The landslide that occurred on the afternoon of September 9 in Nam Tong village, Nam Luc commune, Bac Ha district killed 18 people.

Đinh Đại
TIN LIÊN QUAN

The shape of the 450 billion VND bridge connecting the two banks of the Red River in Lao Cai

|

After 2 years of construction, the Phu Thinh bridge project connecting the two banks of the Red River in Lao Cai City with an investment capital of 450 billion VND has gradually been completed.

Lao Cai proposes 4,000 billion VND in support to overcome storms and floods

|

Due to the unbalanced budget, Lao Cai province requested the Central Government to support 4,000 billion VND to overcome storms and floods.

Hundreds of Lao Cai workers participate in job fair

|

On November 13, Bao Yen district (Lao Cai) coordinated to organize a festival for consulting, introducing jobs and exporting labor in 2024.

A department in Son La has not detected corruption or negativity for 5 years

|

Son La - In 5 years, the Department of Agriculture and Rural Development (DARD) and its affiliated units have had no cases or incidents of corruption.

Pigs for poor households infected with African swine fever

|

Gia Lai - A herd of pigs allocated under the National Target Program for Sustainable Poverty Reduction in Ia Ly town was confirmed to have African swine fever.

There are no protective markers around the Tien Tan gas station, Dan Phuong

|

The risk of encroachment on the dyke in Dan Phuong, including Tien Tan gas station, has not been determined because this dyke section does not have protective markers.

The shape of the 450 billion VND bridge connecting the two banks of the Red River in Lao Cai

Đinh Đại |

After 2 years of construction, the Phu Thinh bridge project connecting the two banks of the Red River in Lao Cai City with an investment capital of 450 billion VND has gradually been completed.

Lao Cai proposes 4,000 billion VND in support to overcome storms and floods

Đinh Đại |

Due to the unbalanced budget, Lao Cai province requested the Central Government to support 4,000 billion VND to overcome storms and floods.

Hundreds of Lao Cai workers participate in job fair

Đinh Đại |

On November 13, Bao Yen district (Lao Cai) coordinated to organize a festival for consulting, introducing jobs and exporting labor in 2024.