Additional progress points when adjusting Power Plan VIII

PHẠM ĐÔNG |

The Deputy Prime Minister requested that the plan to implement the adjustment of the VIII Power Plan should add progress milestones to monitor and determine implementation responsibilities.

The Government Office has just issued Notice No. 126/TB-VPCP dated March 19, 2025, concluding the conclusion of Deputy Prime Minister Bui Thanh Son at the meeting to review and adjust the National Power Development Plan for the period 2021-2030, with a vision to 2050.

The conclusion notice clearly states that the adjustment of the National Power Development Plan for the period 2021-2030, with a vision to 2050 (power Plan VIII) must comply with the viewpoints, goals, and planning principles stated in Decision No. 1710/QD-TTg dated December 31, 2024 of the Prime Minister on approving the task of adjusting the Power Plan VIII, ensuring 4 requirements:

First, the highest feasibility.

Second, ensuring energy security.

Third, balance regions and energy types.

Fourth, ensure economic growth in 2025 of over 8% and in the 2026-2030 period strive to reach double digits and the living needs of the people.

The Deputy Prime Minister requested the Ministry of Industry and Trade to continue reviewing and perfecting the Adjustment of the VIII Power Plan, including fully absorbing the instructions of the Government Standing Committee in Notice No. 93/TB-VPCP dated March 10, 2025, and the instructions of the Prime Minister and Deputy Prime Minister Bui Thanh Son.

Quit all efforts to avoid power shortages in any situation; immediately deploy feasible projects and have backup plans for projects behind schedule. Ensure balance between localities; exploit the potential, outstanding opportunities, and competitive advantages of localities.

Projects proposed by localities and enterprises need to be carefully reviewed, appropriately accepted in the overall planning, ensuring the highest national interests and feasibility.

The Ministry of Industry and Trade needs to have solutions to handle the problems of LNG power projects; review projects, continue to supplement background power sources to ensure security of power supply, serve economic development and the daily needs of the people.

In the plan to implement the adjustment of the VIII Power Plan, it is necessary to add specific progress milestones for projects to monitor, urge, and determine responsibilities when implementing.

The Ministry of Industry and Trade coordinates with the Government Office to complete the dossier for the Adjustment of Power Plan VIII, and report to the Prime Minister.

PHẠM ĐÔNG
RELATED NEWS

Prolonged humidity, laundry shops in Hanoi work overtime to serve customers

|

Hanoi - Prolonged humid weather, clothes are difficult to dry, causing the demand for drying and washing to increase sharply, many stores have to operate at full capacity to serve people.

Discussing and giving opinions on the action program to implement the Resolution of the 14th Party Congress

|

The Conference of the Executive Committee of the VGCL Party Committee focused on discussing the Action Program to implement the Resolution of the 14th Party Congress.

NATO pays for all US military equipment aid to Ukraine

|

President Donald Trump confirmed that NATO members have agreed to fully pay all military orders transferred to Ukraine after raising defense spending.

Close-up of "golden jars" that can be eaten and attract customers on the occasion of the God of Wealth 2026

|

Hanoi - On the occasion of the God of Wealth of the Year of the Horse, many golden jar cake products become popular with the meaning of bringing good luck for the new year.

Strong cash flow into the stock market

|

The stock market has broken its upward streak, but the positive thing is that cash flow shows signs of recovery.

My father's house, one room, God-given treasure and the hundred-billion box office race

|

After the Tet movie season, Vietnamese box offices still maintain heat alongside "Thỏ ơi!!" are two other domestic works: "Nhà ba tôi một phòng" and "Báu vật trời cho".

Tourists brave the rain to go to sacred acupoints to participate in the Heaven Gate Opening ceremony

|

Thanh Hoa - Despite the rainy weather, many tourists still flock to the sacred temple area to admire the scenery and offer incense to pray for good luck at the beginning of the new year.

Ưu tiên điện sinh khối, điện mặt trời áp mái theo Quy hoạch Điện VIII

PHẠM ĐÔNG |

Phó Thủ tướng Chính phủ Trần Hồng Hà nhấn mạnh ý nghĩa quan trọng của việc triển khai Quy hoạch Điện VIII trong bảo đảm an ninh năng lượng quốc gia, được Chính phủ, Thủ tướng Chính phủ chỉ đạo sâu sát, quyết liệt.

Không hợp pháp hóa dự án sai phạm khi triển khai Quy hoạch điện VIII

PHẠM ĐÔNG |

Khi thực hiện Quy hoạch điện VIII, Phó Thủ tướng Chính phủ Trần Hồng Hà chỉ đạo không hợp pháp hóa dự án sai phạm; các dự án ở địa phương đáp ứng đầy đủ tiêu chí, khả thi, đúng pháp luật phải được đưa vào kế hoạch.

Quy hoạch điện VIII để phát triển các khu công nghiệp, cụm kinh tế

PHẠM ĐÔNG |

Phó Thủ tướng Trần Hồng Hà nhấn mạnh, Quy hoạch điện VIII là quy hoạch ngành quốc gia đặc biệt quan trọng, có độ phức tạp cao và được nhiều cơ quan, đơn vị, chuyên gia, nhà khoa học cũng như các địa phương trong cả nước đặc biệt quan tâm.