Deadline for handling difficulties for renewable energy projects

PHẠM ĐÔNG |

Emphasizing the determination to resolutely handle and resolve difficulties and obstacles of renewable energy projects, the Prime Minister requested to complete them before January 31, 2025.

On the afternoon of December 12, at the Government headquarters, Prime Minister Pham Minh Chinh chaired an online conference to announce and implement the Government's Resolution on policies and directions to remove obstacles and difficulties for renewable energy projects.

In his concluding remarks, Prime Minister Pham Minh Chinh emphasized that the Government has put forward a number of general viewpoints and principles to resolve difficulties for projects in general.

Specific projects will be assigned to localities to proactively work with enterprises to resolve within their authority. If beyond their authority, they will be reported to competent authorities.

Violations need to be isolated and specific responsibilities assigned to relevant individuals. Violations must not be legalized, but solutions, mechanisms, and policies must be found to resolve them.

Criminal proceedings are the last resort to facilitate the removal of obstacles for projects through economic solutions; if the current law changes, does not cause consequences, and there is no corruption, then no criminal proceedings are required.

Thu tuong Chinh phu phat bieu ket luan hoi nghi. Anh: VGP
The Prime Minister delivered a concluding speech at the conference. Photo: VGP

Removing difficulties and obstacles for projects is considered legal when approved by competent authorities. Protecting the rights and legitimate interests of third parties according to the law.

Do not create new violations, do not let negative corruption and bad consequences arise in the handling process, especially mistakes being piled on top of mistakes.

Regarding the solution, agree to handle and allow additional planning for implementation in case the project does not violate regulations related to national security and defense, planning of key national works and projects.

For projects with violations of procedures and processes related to land and construction, they are allowed to be completed according to the provisions of law.

For projects that are enjoying FIT prices but have violated the conclusion of competent authorities due to the fault of the enterprise and do not fully meet the conditions for enjoying FIT prices, they will not be entitled to preferential FIT prices but must re-determine the electricity purchase and sale prices according to regulations; recover the preferential FIT prices that have been enjoyed incorrectly through offset payments for electricity purchases.

The Prime Minister stated that the authority of each level must resolve the issue publicly and transparently according to the solutions proposed by the Government; trying to resolve it completely before January 31, 2025.

Regarding the implementation of the Resolution, the Prime Minister requested ministries, branches and localities to thoroughly grasp the sense of responsibility, remove difficulties, and immediately handle obstacles within their authority for projects on the principle that obstacles at which level must be handled and resolved, and not pushed to higher levels or handled in a roundabout way.

For projects that have been prosecuted, violations will only be handled and remedied after a verdict has come into effect according to the provisions of law. Handling of problems must be public and transparent; handling of problems for the purpose of corruption and group interests is strictly prohibited.

Vietnam Electricity Group focuses on reviewing and overcoming the shortcomings and violations mentioned in the conclusion of the Government Inspectorate or the decision of the competent authority.

Coordinate with ministries and branches to classify groups of violations and agree on handling content. In cases beyond EVN's authority, report to competent authorities for consideration and resolution; direct the Electricity Trading Company to create favorable conditions for renewable energy projects to promptly complete electricity trading procedures with the Group.

PHẠM ĐÔNG
RELATED NEWS

Strictly prohibit lobbying, corruption and then have to deal with it

|

The Prime Minister emphasized the strict prohibition of lobbying, negativity, corruption and then having to deal with it, losing people, losing money, losing time, losing trust, losing opportunities.

The government basically completed the planned restructuring of the apparatus

|

Ministries, ministerial-level agencies, and government agencies have so far basically completed the planned organizational restructuring.

Renewable energy resources need to be put into operation

|

On the afternoon of October 19, in Khanh Hoa, Permanent Deputy Prime Minister Nguyen Hoa Binh chaired a conference to remove difficulties and obstacles in renewable energy projects.

Live football U23 Vietnam vs U23 UAE in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Vietnam and U23 UAE in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 16).

Prosecuting the accident on the highway that killed 4 people in Thanh Hoa

|

Thanh Hoa - The Police Agency has initiated a criminal case related to a particularly serious traffic accident on the highway that killed 4 people.

Live football U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship

|

Live football match between U23 Japan vs U23 Jordan in the quarter-finals of the 2026 AFC U23 Championship at 6:30 PM tonight (January 16).

Ms. Lam Thi Phuong Thanh is introduced to run for National Assembly Deputy of the 16th term

|

Voters at the Ministry of Culture, Sports and Tourism voted to agree to introduce Ms. Lam Thi Phuong Thanh, Standing Deputy Minister, to run for National Assembly Deputy of the 16th term.

Thu Thiem - Long Thanh railway line 42km long connects Long Thanh airport

|

Dong Nai - The Thu Thiem - Long Thanh railway project has a total estimated investment of about 84,753 billion VND, completed in 2031.

Strictly prohibit lobbying, corruption and then have to deal with it

PHẠM ĐÔNG |

The Prime Minister emphasized the strict prohibition of lobbying, negativity, corruption and then having to deal with it, losing people, losing money, losing time, losing trust, losing opportunities.

The government basically completed the planned restructuring of the apparatus

PHẠM ĐÔNG |

Ministries, ministerial-level agencies, and government agencies have so far basically completed the planned organizational restructuring.

Renewable energy resources need to be put into operation

Hữu Long |

On the afternoon of October 19, in Khanh Hoa, Permanent Deputy Prime Minister Nguyen Hoa Binh chaired a conference to remove difficulties and obstacles in renewable energy projects.