Disbursement of public investment capital in 2024: No time for delay

Vũ Long |

According to a report from the Ministry of Finance, the estimated disbursement rate of public investment capital in 2024 of the whole country by the end of July will reach 32.22% of the total plan, reaching 34.68% of the plan assigned by the Prime Minister. and lower than the same period last year. To achieve the set economic targets, it is necessary to speed up disbursement progress in ministries, branches and localities that are "perplexed".

Estimated in 7 months of 2024, disbursement of Pope's capital will reach 232,091.4 billion VND

A report from the Ministry of Finance said that the cumulative payment of public capital from the beginning of the year to the end of June 2024 is 188,406.3 billion VND, reaching 26.15% of the plan and reaching 28.15% of the plan assigned by the Prime Minister. Estimated payment from the beginning of the year to July 31, 2024 is 232,091.4 billion VND, reaching 32.22% of the total plan, reaching 34.68% of the plan assigned by the Prime Minister.

Overall, in the first 7 months of 2024, 11/44 ministries, central agencies and 38/63 localities have estimated disbursement rates above the national average. Some ministries, central agencies and localities with good disbursement rates include: Ministry of Transport: 50.83%, Ministry of Construction: 47.91%, Thanh Hoa province: 58.45%, Hoa Binh : 56.79%, Long An: 52.22%...

Drastically promote public investment disbursement for economic growth

According to Dr. Dao Cong Nghinh (former lecturer at Hanoi University of Pedagogy 2), the Pope is an important driving force to promote economic growth, so it is necessary to speed up disbursement progress at "sluggish" ministries and localities. .

“There are only 5 months left until the end of the year, but currently there are still 33 ministries, central agencies and 25 localities disbursing lower than the national average, which is hindering the country's GDP growth rate. Time is running out, so agencies and localities that are "sluggish" cannot be confused forever, they need to come up with solutions to speed up the disbursement of papal capital" - Dr. Dao Cong Nghinh said.

To promptly remove difficulties and obstacles and promote disbursement of the 2024 financial plan, recently, at the Conference to promote 2024 financial planning chaired by the Prime Minister (July 16, 2024), the Ministry of Planning and Investment (KHDT) has proposed to the Standing Government to direct ministries, central agencies and localities to proactively and decisively implement tasks and solutions set out in Resolutions of the National Assembly and the Government. , direction of the Prime Minister; Strive to disburse government capital in 2024 to reach over 95% of the plan assigned by the Prime Minister; accelerate the progress of completing investment and bidding procedures for projects...

To speed up the disbursement of papal capital, the Prime Minister requested to continue maintaining the activities of the Prime Minister's working groups to inspect, urge, remove difficulties and obstacles, and promote disbursement. CCP capital, including an additional working group headed by Deputy Prime Minister Le Thanh Long; Maintain a quarterly mechanism for Government members to work with localities to inspect, urge and remove difficulties according to Decision No. 435/QD-TTg of the Prime Minister.

Vũ Long
TIN LIÊN QUAN

Nguyên nhân nhiều tỉnh thành ở Tây Nguyên chậm giải ngân vốn đầu tư công

THANH TUẤN |

Hàng loạt dự án đầu tư xây dựng trọng điểm ở hai tỉnh Gia Lai, Kon Tum đang bị chậm tiến độ, tỉ lệ giải ngân vốn đầu tư công đạt thấp. Chủ đầu tư cũng như đơn vị thi công thì không khỏi lo lắng bởi những vướng mắc, khó khăn khách quan đến từ cơ chế chính sách.

Ninh Bình chỉ đạo thu hồi tạm ứng vốn đầu tư công quá hạn

NGUYỄN TRƯỜNG |

UBND tỉnh Ninh Bình yêu cầu các đơn vị liên quan tiến hành kiểm tra thu hồi tạm ứng vốn đầu tư công quá hạn hoặc sử dụng không đúng mục đích.

Đẩy mạnh đầu tư công, không để dự án trọng điểm chờ mặt bằng

Phạm Đông |

Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính chỉ đạo không để tình trạng dự án chờ mặt bằng, đặc biệt là các dự án quan trọng quốc gia, dự án cao tốc, trọng điểm, đường liên vùng, đường ven biển.

Khơi thông dòng vốn đầu tư công tại Ninh Bình

NGUYỄN TRƯỜNG |

Tỉnh Ninh Bình đang triển khai đồng bộ các giải pháp tài chính, ngân sách nhằm khơi thông nguồn lực, đẩy mạnh giải ngân vốn đầu tư công.

Chủ tịch Bến Tre yêu cầu đẩy mạnh giải ngân vốn đầu tư công

Thành Nhân |

Chủ tịch Bến Tre yêu cầu tập trung tối đa các nguồn lực để đẩy nhanh tiến độ 11 công trình, dự án, chương trình, đặc biệt là dự án cầu Rạch Miễu 2.

Hàng loạt dự án đầu tư công ở Đắk Nông mắc kẹt vì quy hoạch bô xít

Phan Tuấn |

Quy hoạch bô xít đã và đang gây ra nhiều khó khăn, vướng mắc đến việc phát triển kinh tế - xã hội của Đắk Nông. Trong đó, đầu tiên phải kể đến việc toàn tỉnh đang có hơn 1.000 công trình dự án đầu tư công không thể triển khai thực hiện.

Nguyên nhân Khánh Hòa giải ngân vốn đầu tư công thấp

Hữu Long |

Khánh Hòa - Đề xuất các chủ đầu tư phải cam kết giải ngân vốn năm 2024 đạt 95% trở lên và chịu trách nhiệm về việc không hoàn thành giải ngân kế hoạch năm.

Vinafco lãi 2,8 tỉ, chưa bồi thường vụ rơi pin xuống biển

Lục Giang |

Vinafco đang phối hợp cùng các chủ hàng, công ty bảo hiểm và các cơ quan chức năng giải quyết sự cố vụ 37 container rơi xuống biển, trong đó có hơn 10 tấn pin.