Deputy Prime Minister inspects expressway project in Da Nang

Nguyễn Linh |

On the morning of March 13, Deputy Prime Minister Nguyen Hoa Binh inspected the Hoa Lien - Tuy Loan Expressway (Da Nang City).

The Hoa Lien - Tuy Loan Expressway project has a total length of 11.47km, passing through Da Nang city. The project started in September 2023 and is expected to be completed in November 2025, however, the Government aims to shorten the completion progress to August 2025. The total investment of the project is 2,112.985 billion VND.

Permanent Deputy Prime Minister Nguyen Hoa Binh listened to a report on the project implementation progress, difficulties and obstacles, as well as solutions to resolve them. According to the report, the site clearance work has been 100% completed, and contractors have reached the construction of 11.37/11.47km. However, there are still some problems related to the relocation of some technical infrastructure works and the construction of resettlement areas.

Pho Thu tuong Thuong truc Nguyen Hoa Binh tang qua cho cac don vi thi cong tai cao toc Hoa Lien. - Tuy Loan. Anh: Nguyen Linh
Permanent Deputy Prime Minister Nguyen Hoa Binh presented gifts to construction units at the Hoa Lien - Tuy Loan Expressway. Photo: Nguyen Linh

Regarding construction materials, the report shows that the supply has been identified to ensure inventory and quality. However, some actual materials that contractors buy from the mines have higher prices than the local price announcement. This needs to be inspected and reviewed by competent authorities to avoid price increases, causing difficulties for construction units. At the same time, the increase in the capacity of Truong Ban quarry is still facing difficulties in administrative procedures, affecting the supply of materials for the project. The Permanent Deputy Prime Minister requested local authorities to urgently and thoroughly handle these problems to ensure construction progress.

The Permanent Deputy Prime Minister also directed construction units and Da Nang City to work with the Southern Da Son II stone quarry of Phu My Hoa Company Limited (about nearly 600,000m3) to remove obstacles to provide the Hoa Lien - Tuy Loan Expressway Project with about 200,000m3 of stone.

In addition, the Permanent Deputy Prime Minister highly appreciated the efforts of investors, contractors and local authorities in implementing the project. At the same time, it is required that units focus on removing difficulties and obstacles, especially the issue of construction materials and relocation of technical infrastructure, ensuring the project completion progress is on schedule. Mr. Nguyen Hoa Binh also emphasized the importance of the project for the socio-economic development of Da Nang city and the Central region, and requested units to make every effort to put the project into operation as soon as possible.

Nguyễn Linh
RELATED NEWS

Deputy Prime Minister Le Thanh Long highly appreciates the Da Nang health sector

|

The Da Nang health sector will promote the tradition and achievements, continue to make efforts, and effectively implement assigned tasks.

Da Nang establishes 5 new departments

|

On February 20, at the 22nd session, term X, 2021 - 2026, the People's Council of Da Nang City approved the proposal to establish 5 new departments.

Da Nang operates the new administrative apparatus smoothly after the merger

|

In 2025, Da Nang will operate the commune-level administrative apparatus more effectively with 17 merged units. Notable is the "Wednesday Morning No Appointment" model.

Land recovery for more than 1,000 households in the center of Ho Chi Minh City, highest compensation of 256 million VND/m2

|

Ho Chi Minh City - The expected land price for compensation at the Van Thanh canal renovation project is highest at about 256 million VND/m2, applied to the frontage location of Dien Bien Phu street.

Transferring Major General Cao Minh Huyen to be Director of the Immigration Department

|

On the afternoon of August 10, in Hanoi, the Ministry of Public Security organized a ceremony to announce the decision of the Minister of Public Security on the mobilization of one Lieutenant General and one Major General.

Two Hanoi Medical University students disciplined after making statements about patients on TikTok

|

Two students of Hanoi Medical University were disciplined and dismissed from the position of deputy class monitor for inappropriate statements about patients on social networks.

Verifying clip of a girl sitting close to the railway track, her phone thrown off by a train in Hanoi

|

Hanoi - Functional forces are verifying a clip of a girl sitting close to the track turning a train, causing her phone to be hit by a train and thrown away while passing by.

Be stricter with workers who violate the law when working abroad

|

National Assembly deputies believe that the situation of workers absconding when working abroad negatively affects the national image.

Deputy Prime Minister Le Thanh Long highly appreciates the Da Nang health sector

Trần Thi |

The Da Nang health sector will promote the tradition and achievements, continue to make efforts, and effectively implement assigned tasks.

Da Nang establishes 5 new departments

Nguyễn Linh |

On February 20, at the 22nd session, term X, 2021 - 2026, the People's Council of Da Nang City approved the proposal to establish 5 new departments.

Da Nang operates the new administrative apparatus smoothly after the merger

Nguyễn Linh |

In 2025, Da Nang will operate the commune-level administrative apparatus more effectively with 17 merged units. Notable is the "Wednesday Morning No Appointment" model.