Deputy Prime Minister inspects expressway project in Da Nang

Nguyễn Linh |

On the morning of March 13, Deputy Prime Minister Nguyen Hoa Binh inspected the Hoa Lien - Tuy Loan Expressway (Da Nang City).

The Hoa Lien - Tuy Loan Expressway project has a total length of 11.47km, passing through Da Nang city. The project started in September 2023 and is expected to be completed in November 2025, however, the Government aims to shorten the completion progress to August 2025. The total investment of the project is 2,112.985 billion VND.

Permanent Deputy Prime Minister Nguyen Hoa Binh listened to a report on the project implementation progress, difficulties and obstacles, as well as solutions to resolve them. According to the report, the site clearance work has been 100% completed, and contractors have reached the construction of 11.37/11.47km. However, there are still some problems related to the relocation of some technical infrastructure works and the construction of resettlement areas.

Pho Thu tuong Thuong truc Nguyen Hoa Binh tang qua cho cac don vi thi cong tai cao toc Hoa Lien. - Tuy Loan. Anh: Nguyen Linh
Permanent Deputy Prime Minister Nguyen Hoa Binh presented gifts to construction units at the Hoa Lien - Tuy Loan Expressway. Photo: Nguyen Linh

Regarding construction materials, the report shows that the supply has been identified to ensure inventory and quality. However, some actual materials that contractors buy from the mines have higher prices than the local price announcement. This needs to be inspected and reviewed by competent authorities to avoid price increases, causing difficulties for construction units. At the same time, the increase in the capacity of Truong Ban quarry is still facing difficulties in administrative procedures, affecting the supply of materials for the project. The Permanent Deputy Prime Minister requested local authorities to urgently and thoroughly handle these problems to ensure construction progress.

The Permanent Deputy Prime Minister also directed construction units and Da Nang City to work with the Southern Da Son II stone quarry of Phu My Hoa Company Limited (about nearly 600,000m3) to remove obstacles to provide the Hoa Lien - Tuy Loan Expressway Project with about 200,000m3 of stone.

In addition, the Permanent Deputy Prime Minister highly appreciated the efforts of investors, contractors and local authorities in implementing the project. At the same time, it is required that units focus on removing difficulties and obstacles, especially the issue of construction materials and relocation of technical infrastructure, ensuring the project completion progress is on schedule. Mr. Nguyen Hoa Binh also emphasized the importance of the project for the socio-economic development of Da Nang city and the Central region, and requested units to make every effort to put the project into operation as soon as possible.

Nguyễn Linh
RELATED NEWS

Deputy Prime Minister Le Thanh Long highly appreciates the Da Nang health sector

|

The Da Nang health sector will promote the tradition and achievements, continue to make efforts, and effectively implement assigned tasks.

Da Nang establishes 5 new departments

|

On February 20, at the 22nd session, term X, 2021 - 2026, the People's Council of Da Nang City approved the proposal to establish 5 new departments.

Da Nang operates the new administrative apparatus smoothly after the merger

|

In 2025, Da Nang will operate the commune-level administrative apparatus more effectively with 17 merged units. Notable is the "Wednesday Morning No Appointment" model.

Memories of Independence Day of old soldiers

|

On Independence Day, memories of wartime and the warm voice of Uncle Ho return intact in the minds of veterans in Ho Chi Minh City.

From August 27, traffic police will fine for not keeping a safe distance on the Phap Van - Nghi Son expressway

|

From August 27, 2026, traffic police will fine drivers who do not comply with regulations on safe distance with cars running in front on the Phap Van - Nghi Son expressway.

Bonuses exceeding regulations and a series of violations, a multi-level marketing company fined 710 million VND

|

Total Swiss Vietnam has just been fined 710 million VND, including violations of not delivering contracts to multi-level marketing participants according to the provisions of law.

Inspectors point out a series of errors at hospitals in Gia Lai

|

Gia Lai - Inspectors discover many errors at hospitals, from overtime, equipment management to prescribing and dispensing addictive drugs.

Lao Dong Newspaper acts as a bridge for readers to send "Words from the Heart" to parents during Vu Lan season

|

Write loving words from your heart during the Vu Lan season, Lao Dong Newspaper will help you convey messages to your parents on live television...

Deputy Prime Minister Le Thanh Long highly appreciates the Da Nang health sector

Trần Thi |

The Da Nang health sector will promote the tradition and achievements, continue to make efforts, and effectively implement assigned tasks.

Da Nang establishes 5 new departments

Nguyễn Linh |

On February 20, at the 22nd session, term X, 2021 - 2026, the People's Council of Da Nang City approved the proposal to establish 5 new departments.

Da Nang operates the new administrative apparatus smoothly after the merger

Nguyễn Linh |

In 2025, Da Nang will operate the commune-level administrative apparatus more effectively with 17 merged units. Notable is the "Wednesday Morning No Appointment" model.