The Prime Minister approved the adjustment of the VIII power planning

PHẠM ĐÔNG |

According to the adjustment of VIII electricity planning, striving for commercial electricity in 2030 reached about 500.4 - 557.8 billion kWh and clearly defined the needs of investment capital.

Member of the Party Central Committee and Deputy Prime Minister Bui Thanh Son has just signed Decision No. 768/QD-TTg of April 15, 2025 of the Prime Minister approving the adjustment of the National Power Development Plan for the term 2021-2030, with a vision to 2050 (VIII power plan).

The specific goal is to provide enough domestic electricity demand, meeting the socio-economic development target with an average GDP growth of about 10.0%/year in the period of 2026-2030, about 7.5%/year in the period of 2031-2050.

In which, commercial electricity: In 2030, it will reach about 500.4 - 557.8 billion kWh; the orientation for 2050 is to reach about 1,237.7 - 1,375.1 billion kWh.

Electricity production and import: In 2030, it will reach about 560.4 - 624.6 billion kWh; the orientation for 2050 is about 1,360.1 - 1,511.1 billion kWh.

Maximum capacity: In 2030, it will be about 89,655 - 99,934 MW; in 2050, it will reach about 205,732 - 228,570 MW.

Strive to have 50% of office buildings and 50% of houses using self-produced and self-consumed rooftop solar power by 2030 (serving on-site consumption, not selling electricity to the national power system).

Vietnam's solar power potential is about 963,000 MW (land is 837,400MW, water surface is 77,400 MW and roofing is 48,200 MW).

By 2030, the total capacity of solar power sources (including concentrated solar power and roof solar power, excluding solar power sources under Clause 5, Article 10 of the Electricity Law No. 61/2024/QH15) reached 46,459 - 73,416 MW; Orientation to 2050, total capacity reached 293,088 - 295,646 MW.

By 2030, the total wind power on the shore and near the shore reached 26,066 - 38,029 MW (the total technical potential in Vietnam is about 221,000 MW). Priority is given to the arrangement of newly planned wind power sources in localities with good wind potential and difficult economic conditions.

Maximize the potential of offshore wind power techniques of our country (about 600,000 MW) to produce new electricity and energy: The total offshore wind power capacity serves the domestic electricity demand of about 6,000 - 17,032 MW, expected to operate the period of 2030 - 2035. Orientation to 2050 reached 113,503 - 139,097 MW.

It is estimated that the offshore wind power source is estimated to produce new energy at about 15,000 MW in 2035 and about 240,000 MW in 2050.

The decision stated that the period of 2026-2030: Total investment capital for development source and transmission grid equivalent to US $ 136.3 billion, of which investment in the power supply of about US $ 118.2 billion, for the transmission grid of about US $ 18.1 billion.

Orientation of 2031-2035: Estimated demand for investment capital for development source and transmission grid equivalent to US $ 130.0 billion, of which invest in the power source of about 114.1 billion USD, for the power grid of about US $ 15.9 billion, will be accurate in subsequent plans.

Orientation of the period 2036-2050: Estimated demand for investment capital for development source and transmission grid equivalent to US $ 569.1 billion, of which invest in the power source of about 541.2 billion USD, for the transmission grid of about US $ 27.9 billion, will be accurate in subsequent plans.

PHẠM ĐÔNG
RELATED NEWS

Additional progress points when adjusting Power Plan VIII

|

The Deputy Prime Minister requested that the plan to implement the adjustment of the VIII Power Plan should add progress milestones to monitor and determine implementation responsibilities.

Exemption from electricity license when installing rooftop solar power

|

Organizations and individuals installing rooftop solar power for self-production and self-consumption are exempt from electricity operation licenses and have unlimited capacity.

Hanoi Party Secretary requests drastic removal of urban bottlenecks

|

Hanoi - Hanoi Party Secretary Nguyen Duy Ngoc requests the Construction sector to thoroughly handle congestion, flooding, and urban bottlenecks.

Live football U23 Korea vs U23 Australia in the U23 Asian Cup quarter-finals

|

Live broadcast of the match between U23 Korea and U23 Australia in the quarter-finals of the 2026 AFC U23 Championship, taking place at 10:30 PM today (January 17).

Live football Man United vs Man City in the Premier League

|

Live football match Man United - Man City in round 22 of the Premier League, taking place at 7:30 PM on January 17 (Vietnam time).

15-year traffic jam at the eastern gateway of Ho Chi Minh City is about to be removed

|

Ho Chi Minh City - The bottleneck on National Highway 1, the section of the new Mien Dong Bus Station - Tan Van, is expected to be expanded from the end of 2026, helping to eliminate traffic jams at the eastern gateway.

Excavation of an ancient tomb nearly 2,000 years old in Quang Ninh

|

Quang Ninh - During the excavation of an ancient tomb nearly 2,000 years old in Vang Danh, Quang Ninh province, many important artifacts were discovered.

3-year corporate income tax exemption according to Decree 20

|

3 years of corporate income tax exemption for small and medium-sized enterprises from the date of first issuance of the Enterprise Registration Certificate.

Additional progress points when adjusting Power Plan VIII

PHẠM ĐÔNG |

The Deputy Prime Minister requested that the plan to implement the adjustment of the VIII Power Plan should add progress milestones to monitor and determine implementation responsibilities.

Exemption from electricity license when installing rooftop solar power

PHẠM ĐÔNG |

Organizations and individuals installing rooftop solar power for self-production and self-consumption are exempt from electricity operation licenses and have unlimited capacity.

Ưu tiên điện sinh khối, điện mặt trời áp mái theo Quy hoạch Điện VIII

PHẠM ĐÔNG |

Phó Thủ tướng Chính phủ Trần Hồng Hà nhấn mạnh ý nghĩa quan trọng của việc triển khai Quy hoạch Điện VIII trong bảo đảm an ninh năng lượng quốc gia, được Chính phủ, Thủ tướng Chính phủ chỉ đạo sâu sát, quyết liệt.