Also attending the meeting were members of the Board of Directors of Vu Thanh Lam Group; Deputy General Director of Phan Xuan Thuy Group; Chief Accountant of the Group Dang Thi Huong; Departments: DT, TCNS, KTTC, KCM, City, VP of the Group...

Reporting to General Director Vu Anh Tuan and the Group's leaders on the production and business situation and the implementation of the Khe Cham II-IV mine tunnel exploitation project, Director of Ha Long Coal Company - TKV Nguyen Dinh Thinh said that in the first 7 months of the year, the Company has made efforts to overcome difficulties, boost production, basically completed and exceeded the main plan targets such as: raw coal production reached 1.226 million tons, equal to 61.3% of production and equal to 59.8% of growth; mine meters reached 9,969m, equal to 52.8% of production and equal to 51.4% of growth; coal consumption reached 1.167 million tons, equal to 59.8% of production and equal to 58.3% of growth; average salary reached 22 million VND/person/month, equal to 111% of growth...
Regarding the implementation of the Khe Cham II-IV Mining tunnel Exploitation Project, implementing the conclusions and instructions of TKV, it is expected that by the end of July 2025: excavating a total of 35,882m of XDCB furnace; remaining furnace meters of 3,007m; completing package 36; the total number of XDCB furnaces put into operation is 08 markets/total of 14 markets.

The completed works on the site include: Administration house for daily life, light house, 500-seat dining room, transformer station 35/6Kv-2x18MVA No. 1; domestic wastewater treatment station 450m3/day and night and underground wastewater treatment station with a capacity of 2,000m3/h; completing the sub- well frame system +35/500...
In the plan for the last 5 months of 2025, the Company directed the implementation of production and business plan targets for the whole year of 2025: raw coal for production according to the plan of 2.050 million tons, striving to reach 2.1 million tons; tunnel meters of 23,700m; coal consumption of 2.026 million tons...
For the Khe Cham II-IV mine tunnel exploitation project, strive to achieve 3,000m of XDCB furnaces for the whole year; deploy mixed-use packages and key equipment; complete legal procedures for the adjusted project (completed on September 20, 2025); report to the EIA expected to be completed on August 15, 2025...
At the meeting, the leaders and the Group's specialized departments participated in opinions related to the project such as implementing homemade packages; project documents adjusted; e-commerce reports; technical and technological work; building a schedule, speeding up excavation, completing excavation of XDCB mines before December 31, 2026 to install equipment; on capital sources, finance...
In his speech, General Director Vu Anh Tuan of the Group acknowledged and highly appreciated the efforts, efforts and results achieved in production and business as well as the implementation of the Khe Cham II-IV mine tunnel exploitation project of Ha Long Coal Company - TKV.
At the same time, he emphasized that this is a key project that the Group is particularly interested in, so the Company continues to speed up the project progress; focus on implementing the bidding packages for supply, installation of 4,000KVA power generation, Wind wells..., complete the project dossier procedures to adjust, report to the EIA according to the set schedule; The Company is proactive in the implementation process in the spirit of "clear people, clear work, clear responsibilities, clear time, clear products, clear results"... The General Director of the Group noted that the Group's professional departments are especially interested, direct, support the unit, and remove difficulties and obstacles.
General Director Vu Anh Tuan Group agreed on the contents related to other work related to investment in production and care for workers' lives, and at the same time wished Ha Long Coal Company - TKV to complete the progress of the Khe Cham II-IV mine tunnel exploitation project, successfully completing the production and business plan for 2025.