Completing key cultural projects in Nghe An in 2025

QUANG ĐẠI |

Nghe An – Phase 2 of the Project on the Center for Preservation and Promotion of Nghe Tinh Vi and Giam Folk Song Heritage is expected to be completed in 2025.

On December 21, speaking with Lao Dong Newspaper reporters, Mr. Pham Ngoc Anh, Head of Finance - Planning Department - Department of Culture and Sports of Nghe An province, said that up to now, the Project of Center for Preservation and Promotion of Nghe Tinh Vi, Giam Folk Heritage in Vinh City has completed phase 1.

The project has completed the administrative and performance building, collection, research, preservation, storage of folk heritage, leveling, water supply, and overall electricity supply...

According to Mr. Anh, during the implementation of phase 1 of the project, the contractor encountered financial difficulties, leading to the project being suspended. However, up to now, the contractor has tried to repair and replace damaged parts due to long-term storage and has completed phase 1 of the project.

To synchronize the facilities and promote investment efficiency, phase 2 of the project needs to add some new items such as: Outdoor public toilets; Lightning protection, ventilation, air conditioning and some other items; Installation of working and specialized equipment (sound, lighting, performance and practice equipment; Curtains, operating floors, stage frames, display screens, surveillance cameras; Audience seating system; Interior of the main hall and offices, other equipment and machinery...); Construction of the exterior architecture of the main building; staging, practicing and performing art shows to serve tourists every week...

According to a representative of the Department of Culture and Sports of Nghe An, phase 2 of the project is expected to be completed by the end of 2025.

Du kien giai doan 2 cua du an se hoan thanh trong nam 2025. Anh: Quang Dai
Phase 2 of the project is expected to be completed in 2025. Photo: Quang Dai

The project of the Center for Preservation and Promotion of Nghe Tinh Vi and Giam Folk Heritage was approved by the People's Committee of Nghe An province to design construction drawings and estimate the construction of main items on September 20, 2016.

The project is divided into 2 phases. Phase 1 includes main items such as: Administrative building for performing and collecting, researching, preserving and storing folk heritage; leveling the ground; general water supply; general electricity supply; underground water tank for daily life and fire prevention and fighting, equipment.

Phase 2 includes items such as: landscape garden, equipment, sound and lighting...

The project is invested from the central budget under the target program for cultural and sports development with an investment of 69 billion VND, with the Department of Culture, Sports and Tourism of Nghe An province as the investor; the contractor is Hoang Kim Company.

The main scale of the project includes: 500-seat auditorium, administrative, research, collection, conservation and auxiliary rooms. The architectural complex is 5 stories high, with a floor plan of 55.5m x 36m; construction area of ​​2,195m2.

The project's phase 1 implementation period was no more than 5 years from 2016, however, after more than 8 years, the project has just completed phase 1 and construction has been suspended for 8 years.

As Lao Dong reported, at the end of 2024, the People's Committee of Nghe An province issued a document urging and assigning responsibility to the Department of Culture and Sports of Nghe An to urgently complete and put the province's key cultural project into use to promote efficiency.

QUANG ĐẠI
TIN LIÊN QUAN

Progress of the 68 billion VND park renovation project in Hai Phong

|

Hai Phong - The project to renovate and beautify Dam Vuong Park (Do Son District, Hai Phong) has been underway for nearly a month and is expected to be completed in April 2025.

Nghe An urges slow-progressing and wasteful projects

|

Nghe An - The province requires speeding up progress and putting slow-progressing cultural, health and educational projects into use soon to avoid waste.

Northwest end of day: Speeding up progress of 3 hundred billion projects in Yen Bai

|

Progress of 3 key projects in Yen Bai; 8 cases of smuggled cigarettes caught in 1 day; On the construction site dismantling the remaining part of Phong Chau bridge..

Queue up to buy gold for good luck at the beginning of the year

|

On the morning of the 6th day of Tet (February 3), domestic gold prices increased sharply. However, many people still spent time lining up to buy gold with the hope of bringing more luck in the new year.

President of Vietnam General Confederation of Labor wishes a happy new year to Lao Dong Newspaper

|

On the morning of February 3, Party Central Committee member and President of the Vietnam General Confederation of Labor Nguyen Dinh Khang congratulated the staff, reporters, editors and employees of Lao Dong Newspaper on the New Year.

Actress Barbie Hsu suddenly passed away

|

According to Chinese media reports on February 3, Barbie Hsu's relatives confirmed that she died of seasonal flu.

Mr. Nguyen Thanh Nghi received a new assignment

|

Ho Chi Minh City - Mr. Nguyen Thanh Nghi - Standing Deputy Secretary of the Ho Chi Minh City Party Committee holds the position of Secretary of the Party Committee of Ho Chi Minh City Party agencies for the 2020 - 2025 term.

Hai Phong announces 3 subjects for 10th grade high school exam 2025-2026

|

The Chairman of Hai Phong City People's Committee has just agreed in principle to the plan for selecting subjects for the 10th Grade Public High School Entrance Exam, school year 2025 - 2026.

Progress of the 68 billion VND park renovation project in Hai Phong

Hoàng Khôi |

Hai Phong - The project to renovate and beautify Dam Vuong Park (Do Son District, Hai Phong) has been underway for nearly a month and is expected to be completed in April 2025.

Nghe An urges slow-progressing and wasteful projects

QUANG ĐẠI |

Nghe An - The province requires speeding up progress and putting slow-progressing cultural, health and educational projects into use soon to avoid waste.

Northwest end of day: Speeding up progress of 3 hundred billion projects in Yen Bai

Nhóm PV |

Progress of 3 key projects in Yen Bai; 8 cases of smuggled cigarettes caught in 1 day; On the construction site dismantling the remaining part of Phong Chau bridge..